Thu Jun 27 11:09:14 2024, Liu, Update, Scripts/Programs, Straight edge STEP files and ray loss analysis   
|
Wed Jun 26 16:39:34 2024, Luke, Update, VAC, Vacuum chamber leak checking 
|
Thu Jun 20 18:01:11 2024, Jon, Infrastructure, Computers, New workstation ws3 in 1129
|
Wed Jun 26 15:33:41 2024, Jon, Infrastructure, Computers, New workstation ws3 in 1129
|
Tue Jun 25 17:19:42 2024, Luke, Update, VAC, Vacuum chamber leak checking   
|
Tue Jun 25 12:34:18 2024, Shane, Update, Cleanroom, cleanroom cleaning and particle count
|
Mon Jun 24 21:38:25 2024, Pooyan, Infrastructure, Computers, Computer server changes in 1119 and 1129 
|
Mon Jun 24 14:28:51 2024, Cynthia , Update, Interferometer Simulations, SIS cavity with thermal effect
|
Fri Jun 21 11:47:30 2024, Liu, Update, Scripts/Programs, COMSOL simulation on alternative straightened heater elements design 6x
|
Wed Jun 19 18:45:14 2024, Luke, Update, , Vacuum chamber reassembly  
|
Mon Jun 17 11:47:46 2024, Liu, Infrastructure, General, Temporary cooling units for the labs 
|
Fri Jun 14 13:32:13 2024, Liu, Update, Scripts/Programs, COMSOL simulation on rectangular heater elements design 6x
|
Mon Jun 3 14:14:39 2024, Tyler, Update, FLIR, Initial CIT FROSTI Analysis
|
Mon Jun 10 14:52:38 2024, Tyler, Update, FLIR, CIT FROSTI Analysis Update
|
Mon Jun 3 14:59:44 2024, Cynthia, Update, Interferometer Simulations, Created cavity scan with LG modes
|
Mon Jun 3 09:24:48 2024, Aiden, Update, VAC, Vacuum Chamber Rendering 
|
Fri May 31 19:37:47 2024, Luke, Update, , Vacuum chamber Disassembly   
|
Thu May 16 15:23:14 2024, Shane, Update, Cleanroom, Cleanroom cleaning and particle count
|
Mon May 13 14:53:29 2024, Peter, Update, VLC Update, VLC
|
Mon May 13 14:48:27 2024, Aiden, Update, VAC, New Vacuum Chamber Design
|
Mon May 13 13:03:41 2024, Tyler, Update, FLIR, Readout Code Updates
|
Tue May 7 20:34:31 2024, shane, Update, CDS, frosti MEDM screen update
|
Thu May 2 22:43:36 2024, Tyler, Update, Electronics, RTD Readout Chassis Redesign
|
Mon Apr 22 15:06:33 2024, Cynthia , Update, Interferometer Simulations, cavity scan update
|
Wed Apr 17 15:07:04 2024, Shane, Update, Cleanroom, Cleanroom cleaning and particle count
|
Mon Apr 15 15:25:10 2024, Cynthia, Update, Interferometer Simulations, progress on simulation so far
|
Mon Apr 15 11:51:03 2024, Peter, Update, VLC Update, VLC
|
Mon Apr 8 14:57:41 2024, Cynthia, Pooyan, Update, Interferometer Simulations, performed cavity scans for O4 O5, and coupled cavity
|
Mon Apr 8 14:43:29 2024, Pooyan, Update, Interferometer Simulations, SIS update single and coupled cavities 
|
Sun Apr 7 13:42:51 2024, Michael, Update, Interferometer Simulations, Update on status of gtrace project 
|
Wed Mar 27 00:03:57 2024, Pooyan, Update, Computers, Chimay relocation to Physics 1129 
|
Sun Mar 24 11:50:37 2024, Aiden, Update, Clean & Bake, Cal Tech FROSTI Parts
|
Sun Mar 24 11:49:27 2024, Aiden, Update, General, FROSTI RGA Scan 
|
Tue Mar 19 15:22:27 2024, Aiden, Update, Clean & Bake, FROSTI Legs Clean and Bake
|
Tue Mar 19 10:55:30 2024, Tyler, Update, FLIR, In-Air Optical Test
|
Fri Mar 15 16:58:55 2024, Aiden, Update, VAC, Vacuum Chamber Frosti Testing 
|
Wed Mar 6 09:57:52 2024, Tyler, Update, TCS, FROSTI Wiring
|
Thu Feb 29 17:16:48 2024, Shane, Update, CDS, MEDM screen for FROSTI T/P readouts
|
Mon Feb 26 21:23:27 2024, Jon, Update, TCS, FROSTI Assembly - Day 1 7x
|
Wed Feb 28 17:49:18 2024, Tyler, Update, TCS, FROSTI Assembly - Days 2-3   
|
Wed Jan 17 15:47:49 2024, Aiden, Update, General, Resistors for Heater Elements
|
Wed Feb 28 12:02:08 2024, Tyler, Update, General, Resistors for Heater Elements Update
|
Tue Feb 27 09:06:29 2024, Cynthia , Update, Interferometer Simulations, cavity scan with higher order input laser
|
Tue Feb 27 03:26:28 2024, Michael, Update, Interferometer Simulations, Reverse aLIGO Layout Created in Gtrace 
|
Mon Feb 26 15:15:39 2024, Aiden, Update, General, Vacuum Chamber Baking Update
|
Sat Feb 24 08:53:38 2024, Jon, Infrastructure, Computers, Matlab upgraded to 2023b on Chimay
|
Fri Feb 23 18:03:27 2024, Tyler, Update, FLIR, Optical Test Setup in Cleanroom
|
Fri Feb 23 15:01:48 2024, Shane, Update, CDS, Latest draft of MEDM screen for FROSTI readouts 
|
Thu Feb 22 21:48:16 2024, Jon, Update, VAC, Vacuum vent for RGA testing of reflector 
|
Wed Feb 21 23:15:07 2024, Michael, Update, Interferometer Simulations, Long Shoelaces 1 Layout Created in Gtrace and Fixed Ghosting in Beamsplitter  
|
Wed Feb 21 11:58:30 2024, Shane, Update, Cleanroom, cleanroom cleaning and particle count
|
Tue Feb 20 18:08:24 2024, Aiden, Update, General, Degassing the RGA 
|
Tue Feb 20 11:31:49 2024, Tyler, Update, Cleanroom, Garment Cabinet Door Replacement 
|
Mon Jan 15 22:29:34 2024, Jon, Infrastructure, General, Cabinet installation & lab clean-up completed 
|
Tue Feb 20 08:01:30 2024, Jon, Infrastructure, General, Power and network equipment installed in 1129 rack   
|
|