23
|
Tue Feb 7 17:27:30 2023 |
Aiden | Physics | ELOG | Clean and Bake Batch #1 | Cleaned SS parts with liquinox for 20 min.
Then put in oven for 5 steps;
1. Ramp, 100
degC, 15 min
2. Const, 100 degC, 30 min
3. |
|
|
25
|
Fri Feb 10 15:15:30 2023 |
Aiden | Update | General | Bagging First Batch | Aiden Bagged and Tagged the first batch of
stainless steel parts shown on the google
spread sheet.
1. Removed two parts from |
|
|
29
|
Mon Feb 13 18:57:53 2023 |
Aiden | Summary | General | Clean and Bake batch 2 | Cleaned second batch of SS parts with liquinox
for 20 min. Then put in oven for 5 steps;
1. Ramp, 100 degC, 15 min 2. Const, 100 degC, |
|
|
30
|
Fri Feb 17 19:12:39 2023 |
Aiden | Update | General | Clean and Bake batch 3 | Bagged and Tagged batch 2 parts by placing
no more than two parts per ESD bag then taped
them with kapton tape and tagged them with |
 |
|
31
|
Tue Feb 21 17:51:04 2023 |
Aiden | Summary | General | Clean and Bake batch 4 | Bagged and Tagged batch 3 parts by placing
no more than two part numbers per bag and
taped them with kapton tape and labeled them |
 |
|
38
|
Tue Feb 28 19:37:22 2023 |
Aiden | Summary | General | Clean and Bake batch 5 | Bagged and Tagged batch 4 parts by placing
no more than two part numbers per bag and
taped them with kapton tape and labeled them |
  |
|
42
|
Fri Mar 3 19:13:33 2023 |
Aiden | Summary | General | Clean and Bake Batch 6 | Started to clean the dirtiest of the valves.
I could not finish but I definitely made
good progress on it. The MDC valve is very |
 |
|
47
|
Wed Mar 8 19:29:00 2023 |
Aiden | Summary | General | Clean and Bake batch 7 | Today gave another cleaning to the MDC gate
valve. It is still very dirty an will need
more cleaning. I also cleaned the other 3 |
 |
|
51
|
Tue Mar 14 18:21:41 2023 |
Aiden | Summary | General | Clean and Bake batch 8 | Starting off Peter and I refilled the deionized
water barrel.
Then Aiden Cleaned and Bake
the FROSTI arms and bases in liquinox for |
|
|
52
|
Fri Mar 17 19:46:39 2023 |
Aiden | Summary | General | Clean and Bake batch 9 | Bagged and Tagged the reflector arms and bases
and placed them inside the clean room. Total
of 2 bags used. Cleaned and Baked parts in |
 |
|
60
|
Mon Apr 3 17:04:05 2023 |
Aiden | Summary | General | IDP Scroll Pump Assembly | Aiden installed the isolation valve and the
exhaust silencer kits on the IDP-3 Scroll
pump. The entire assembly still needs to |
|
|
69
|
Wed Apr 12 10:53:02 2023 |
Aiden | Summary | General | Valve Cleaning | Bagged and Tagged the parts from batch 10
and placed them inside the clean room.
Then
cleaned the last gate valve in liquinox for |
|
|
72
|
Mon Apr 17 17:06:49 2023 |
Aiden | Summary | General | Clean and Bake batch 11 | Cleaned the Viton O-Ring for the main chamber
in Liquinox for 10 minutes. Then put it in
the oven to back for;
1. Ramp to 100 degC |
|
|
77
|
Mon Apr 24 17:38:45 2023 |
Aiden | Summary | General | Clean and Bake Batch 12 | Today I Bagged and tagged the o-rings from
batch 11 and placed them inside the clean
room. I also cleaned batch 12 parts in liquinox |
 |
|
80
|
Thu Apr 27 09:48:34 2023 |
Aiden | Summary | General | Batch 12 Bagging | I took batch 12 out of the oven and put them
in a bag and placed the bag inside the clean
room in the first large stainless steel container.
I |
 |
|
96
|
Wed May 10 10:49:34 2023 |
Aiden | Update | General | RGA Software | [Aiden, Cao]
Went over how to use the RGA
software, how to change the graph units,
scaling and mass detection. Also went over |
|
|
111
|
Wed May 31 16:18:41 2023 |
Aiden | Summary | General | Mock FROSTI | Finished assembly on the Mock FROSTI so it
is ready for the fit test at LIGO lab. |
|
|
115
|
Tue Jun 6 16:04:46 2023 |
Aiden | Update | General | Water | Aiden went and refilled the de-ionized water
to continue clean and bake batches. |
|
|
121
|
Tue Jun 13 13:25:05 2023 |
Aiden | Summary | Clean & Bake | Clean and Bake Batch 13 | Cleaned and Baked the new 1.33" and 2.75"
blanks for the vacuum system. Cleaned them
with liquinox in the ultra sonic washer for |
|
|
126
|
Fri Jun 16 17:40:28 2023 |
Aiden | Update | Clean & Bake | Clean and Bake Batch 14 | Cleaned and Baked the new and 2.75" copper
gaskets for the vacuum system. Cleaned them
with liquinox in the ultra sonic washer for |
 |
|
146
|
Wed Jul 5 16:02:12 2023 |
Aiden | Update | Clean & Bake | Clean and Bake batch 14 Bagging | Bagged and Tagged the 2.75" copper gaskets
from Batch 14 and placed them into the clean
room on the work bench. |
|
|
148
|
Thu Jul 6 16:16:03 2023 |
Aiden | Summary | VAC | Vacuum Chamber Baking Update |
Pressure Measured Before Removing Gauge
2.31 E-7 Torr.
Went in and turned
on the heating tape in increments of 30 degC |
|
|
150
|
Fri Jul 7 15:11:39 2023 |
Aiden | Update | VAC | VAC System Heating Update |
The temperature of the flange connecting
to the turbo pump after reaching equilibrium
is 74 degC. This means that it is safe to |
|
|
152
|
Mon Jul 10 13:23:23 2023 |
Aiden | Update | VAC | VAC System Heating Update |
Checked on the system today.
The
flange on the turbo pump has reached an equilibrium
temperature of 87 degC when set at 150 degC. |
|
|
153
|
Thu Jul 13 14:56:43 2023 |
Aiden | Update | VAC | VAC System Heating Update |
Checked on the vacuum system today to
change the PID controls back to their default
values in order to try and get the temperature |
|
|
156
|
Fri Jul 14 14:37:25 2023 |
Aiden | Update | VAC | VAC System Heating Update |
Checked on the vacuum system and it looks
like it will either need to be increased
in temperature or baked for a longer time. |
|
|
160
|
Mon Jul 17 13:50:41 2023 |
Aiden | Update | VAC | VAC System Heating Update |
Started to cool down the chamber today.
Final temperature readings of the chamber
were 146C and 91C for the body and cross |
|
|
161
|
Mon Jul 17 14:01:41 2023 |
Aiden | Update | VAC | VAC System Heating Update |
The insulation on the lid of the vacuum
chamber has some discoloration and it may
be wise to place a sensor closer to this |
|
|
168
|
Thu Jul 20 18:03:19 2023 |
Aiden | Update | VAC | Vacuum Chamber Baking Update |
Took another set of RGA data after the
second bake has cooled down to 27 degC.
Just
by visual comparison to the other graphs, |
|
|
179
|
Fri Jul 28 13:46:17 2023 |
Aiden | Update | VAC | Vacuum Chamber Baking Update |
Took some more data to look at the HC
count. Initial data was from leaving the
Argon leak closed and then left it open for |
   |
|
184
|
Tue Aug 1 12:10:03 2023 |
Aiden | Update | VAC | Vacuum Chamber Baking Update |
Dr. Richardson and I took off the insulation
on the lid again to add more insulation in-between
the heater tape folds in addition to what |
  |
|
185
|
Tue Aug 1 12:48:41 2023 |
Aiden | Update | Cleanroom | Pre Filter Change |
Changed the pre filter inside of the
3 stage HEPA system next to the soldering
station. It was rather dirty and I have attached |
  |
|
188
|
Wed Aug 2 17:02:38 2023 |
Aiden | Update | VAC | VAC System Heating Update |
Moved the temperature sensor on the PID
controller to one of the switch backs on
the lid.
Also started the next |
|
|
189
|
Thu Aug 3 16:00:25 2023 |
Aiden | Update | VAC | VAC System Heating Update | Check on the temperature of the bake today
to see the equilibrium temperatures. With
both of the PID controllers set to 150 C, |
|
|
190
|
Thu Aug 3 17:47:51 2023 |
Aiden | Update | VAC | VAC Heating System Update |
Did some further testing to determine
if it was within reason to increase the temperature
of the chamber. I used a thermometer and |
|
|
192
|
Fri Aug 4 15:21:33 2023 |
Aiden | Update | VAC | VAC System Heating Update | Checked on Bake 3 today and the temperature
sensors read 126 C and 91 C for the chamber
barrel and turbo pump flange respectively. |
|
|
195
|
Tue Aug 8 15:31:26 2023 |
Aiden | Update | VAC | VAC Heating System Update |
Vacuum Chamber equilibrium temperature
for bake 3 are 126 C and 88 C for the chamber
wall and turbo pump flange respectively. |
10x |
|
201
|
Thu Aug 10 14:36:00 2023 |
Aiden | Update | VAC | VAC System Heating Update | Came in to install one of the Full range gauges.
Checked the temperature first of the cross
and it was reading 30 C. After installing |
|
|
203
|
Thu Aug 10 18:32:39 2023 |
Aiden | Update | VAC | VAC System Heating Update |
[Dr. Richardson, Aiden]
DO NOT TOUCH ANY VALVES ON THE
CHAMBER. THERE IS A PRESSURE DIFFERENTIAL |
|
|
205
|
Fri Aug 11 18:32:00 2023 |
Aiden | Update | VAC | VAC System Heating Update |
[Dr. Richardson, Aiden] Large Update
Removed
most of the insulation on the chamber in
order to pull back some of the heater tape |
11x |
|
208
|
Tue Aug 15 16:04:23 2023 |
Aiden | Update | VAC | VAC Heating System Update |
Pulled off the rest of the heater tape
along with the aluminum tape left behind.
The aluminum tape adhesive left behind a |
6x |
|
212
|
Thu Aug 17 15:02:44 2023 |
Aiden | Update | VAC | VAC Heating System Update |
Put the heating tape back on and made
sure to have 4 coils around the barrel of
the chamber. To make this happen I did not |
11x |
|
213
|
Thu Aug 17 15:18:48 2023 |
Aiden | Update | VAC | VAC Heating System Update | Relocated the PID controllers so that the
heating tape could be plugged in. In the
picture the left one controls the top half |
|
|
214
|
Mon Aug 21 17:13:25 2023 |
Aiden | Update | VAC | Vacuum Chamber Baking Update |
Came in to take RGA data and found the
turbo pump drawing .38 Amps. This was much
higher than what it was on Friday. I investigated |
 |
|
215
|
Mon Aug 28 14:43:50 2023 |
Aiden | Update | VAC | Vacuum Chamber Baking Update | The PID controllers were turned off on Friday
and the chamber was left to cool over the
weekend. Just took data and it looks like |
 |
|
216
|
Tue Aug 29 19:09:21 2023 |
Aiden | Update | VAC | Vacuum Chamber Baking Update | Here are some more plots with the RGA data
take August 29. It seems that more pumping
time has led to the HC levels being dramatically |
 |
|
217
|
Tue Aug 29 22:07:38 2023 |
Aiden | Update | General | Electronic Bench | Dr Richardson is working on mounting more
power supplies in the server rack and is
using the electronics bench. Be aware to |
|
|
218
|
Thu Aug 31 12:56:29 2023 |
Aiden | Update | VAC | Vacuum Chamber Baking Update | Took some more RGA data to see if the HC levels
have further declined since bake 4 and it
seems that it has started to plateau with |
  |
|
219
|
Fri Sep 1 19:21:19 2023 |
Aiden | Update | VAC | VAC System Heating Update | Started bake 5 today. This will hopefully
be a longer and hotter bake with it lasting
6-7 days at around 150 C. The pressure in |
|
|
220
|
Tue Sep 5 16:43:19 2023 |
Aiden | Update | General | VAC System Heating Update | Checked on bake 5 today after 3 days of equilibrium.
The RGA cross is at 106 C and the turbo pump
cross is at 74 C. This was reached while |
|