Entry  Tue Apr 4 09:39:58 2023, Peter, Update, VLC Electronics, 532 M2 Measurements OmegaY_M2_Fit_8.pdfOmegaX_M2_Fit_8.pdfM2_Measurements_Set_Up.svgBeam_Data_8_3lens.txt
Final M squared measurements were taken Wednesday, 3/29/23 by Peter and Ryan Hinosawa. 5 separate sets of data were taken, and upon discussion, we declared
the plots shown below in attachment 1 and 2 as the final plots of our M squared measurements.

The optical design of the M squared measurement process
is given in attachment 3. The laser and three lenses shown below are mounted on the optical table. The track is placed behind the third lens, and the camera
Entry  Fri Sep 29 11:53:54 2023, Shane, Update, Cleanroom, 5 zone particle count measurement in cleanroom  23.png23.png
Today's 5 zone measurement of cleanroom particulate concentration is attached
Entry  Fri Nov 17 14:06:01 2023, Shane, Update, Cleanroom, 5 zone particle count 23.png
Here's today's 5 zone particle count measurement for the cleanroom. Zone 5 (closest to back wall by fire cabinet) is still above the limit for the larger
size ranges; everything else is in good shape and roughly 10 times under the limit. Not sure why zone 5 is still so dirty (maybe some of the electronics
being stored in bags/bins on the upper shelf of the desk aren't clean?) but will focus cleaning efforts on this zone next time. 
Entry  Thu Nov 9 19:06:46 2023, shane, Update, Cleanroom, 5 zone cleanroom measurement 23.jpeg
Here's today's five zone measurement, taken ~5 hours after the cleaning. Zone 5 (closest to fire cabinet and back wall) is a bit over the limit in all size
ranges (about 1500 particles in 1.0u size range over), and zone 2 is slightly over the limit in the 1.0u range, but everything else is under the requirement.
Entry  Tue Jul 29 12:30:00 2025, Christina, Update, TCS, 260 hour ADC update CSD_06_28_25_270hr.png
 [Ma, Christina, Tyler] 

ADC CyMAC 260 hr, 8192Hz sampling rate channels V3 and Vref6
Entry  Fri Feb 2 19:08:20 2024, Aiden, Update, VAC, 1st Hot Element RGA Scan bake10_240202_Elements_ArC.pngbake10_240202_Elements_ArO.png
Here are the measurements for the RGA scan of the elements while on at around 160C. The pressure of the chamber during the test was 4.12 e-8 torr.
Entry  Tue Nov 21 14:47:24 2023, Tyler, Update, Lore, 1129 Workbench Assembly Update 1 IMG_7569.jpgIMG_7568.jpg

[Tyler, Shane, Mohak, Cynthia, Luke, Michael, Luis]


Started assembly of the workbench equipment today. We completed the stools, and have constructed the frames of each workbench. All that needs to
be added are the tabletops and the top shelves, which will be done on Monday.
Entry  Mon Nov 27 14:22:30 2023, Tyler, Update, Lore, 1129 Assembly Update IMG_7669.jpgIMG_7668.jpg
[Tyler, Michael, Luke, Cynthia]


The tabletops have been attached to the workbench frames. Unfortunately, one of the tabletops came out of the box
with a large scratch and small dent in the middle. One of the electric top shelves is ready to be attached to the undamaged table, but the other is yet
to be opened. Assembly will be completed Wednesday morning.
Entry  Fri Apr 21 15:21:18 2023, Pamella, Update, FLIR,  AcquisitionImage(Apr-21-2023_14_26).jpg
     FLIR project updates

    
 01:50 pm: Starting test position 34 mm distance to black wall. 
  Parameters : 0.100 A, 1.5 V and
the temperature inside the mirrors 40°C. 
 2:09 pm : Finished the test and figured out this position it is too far the black wall so now we change
for more close position. 




   2:17 pm:  Starting test in another position: 10 mm distance to the black wall( this measurement
Entry  Mon Oct 30 11:03:56 2023, Tyler, Update, Scripts/Programs,  Screenshot_2023-10-23_at_12.39.05_PM.png

FLIR: After some adjustments, the plot generated from the FLIR measurements look much more symmetric (see attachment). There are more included grid
points, which smooths out the curve as compared to last week. 


Red Pitaya: It looks like a new OS update was released for the RP, which includes
a new Python API (was previously only available in C). I'm going to try and update the one we have currently running in lab.
Entry  Mon Jan 8 20:24:53 2024, Aiden, Update, General,  IMG_4888.jpgIMG_4886.jpgIMG_4887.jpg
[Jon, Aiden]

Installed the heater elements into their fixture and prepped the cables by twisting the wires into pairs. We also installed the pins
onto the wires and placed them into the peek DB 25 connector. The installation tool we had did not fit the pin size we had so the pins needed to be installed
by hand by opening the connector and holding them in place. In the future we will need to make sure we twist the wires together, group them, and then splice
Entry  Tue Jan 16 16:11:41 2024, Aiden, Update, VAC,  bake10_240116_Elements_ArO.pngbake10_240116_Elements_ArC.png
[Aiden,Luis]

Below is the data for the most recent bake. I believe the chamber is cleaner than it is actually showing as the RGA data was still getting
lower while the data was being taken. I will take the data again tomorrow just in case. Still, the data shows that the chamber is basically as clean as
it was before bake 10 and this means further power testing can proceed.

Helium leak tested the chamber again today to check if the sealant changed
Entry  Mon Jul 1 11:45:45 2024, Sid, Update, Interferometer Simulations,  
Progress update: Most of last week was spent getting set up with SIS, and learning how to do basic simulations. The goal for this week is to begin reproducing
the methodology from T2000338. I have begun with studying perturbations to mirror curvature and position in a simple FP cavity, but thus far have been
unable to get the same results.
Entry  Tue Aug 6 13:07:07 2024, Xuejun, Update, Interferometer Simulations,  Thermal_model_image.pnggenerated_irradiance_profile.png
[Xuejun]

 The width and location of the measured in-air change in temperature profile has been determined to be 0.045m and 0.137m respectively. Subsequently,
a fake irradiance profile was able to be generated that best resembled what the actual irradiance profile could be using this information for testing in
COMSOL. The generated irradiance profile that output the most similar change in temperature profile as the measured in-air profile has been included as
Entry  Wed Nov 13 14:06:00 2024, Luke , Update, General,  
slides
Entry  Mon Jan 27 23:35:28 2025, Xuesi Ma, Update, ,  20250127_142647.jpg20250127_153454.jpg20250127_154516.jpg
[Ma]
Installed all the pins to the peek DB 25 connectors
Entry  Mon Feb 3 13:17:21 2025, Xuesi Ma, Update, ,  20250203_123153.jpg20250203_123213.jpg
[Ma]
changed all zip ties to peek zip ties, and grouped wires together. The setup is ready to go into the chamber.
Entry  Tue Feb 18 10:01:07 2025, Xuesi Ma, Update, ,  IMG_7916.jpegIMG_7915.jpegIMG_7917.jpeg
[Ma, Pooyan, Tyler]
On Friday, we connected the vacuum chamber with the Cymac.
Entry  Tue Feb 25 10:02:32 2025, Xuesi Ma, Update, ,  resistance_vs_time_all_channels_all_time.pdftemperature_vs_time_all_channels_all_time.pdfresistance_vs_time_rise_time.pdfresistance_vs_time_fall_time.pdf
1424039912.625576 2025/02/19 22:38:14 UTC Time start
24V 2.8A right after start all 8 elements
1424044804.902443 2025/02/19 23:59:46 UTC Time stop
Entry  Tue Mar 11 10:43:57 2025, Xuesi Ma, Update, ,  20250310_171936.jpg
Continue investigation in the spikes
Pulsed ADC with a function generator and find no spikes. Rules out ADC for causing the spikes
Loopback test that bypasses the FROSTI Chassis shows spikes (spikes happened on all channels at the same time)
Entry  Mon Mar 31 15:41:56 2025, Xuesi Ma, Update, ,  
The result from AI Chassis bypass test showed that the AI Chassis may be the problem. There are no spikes from DAC's direct output.
All chassis except timing chassis are turned off. Power supplies for 24V, 18V, and -18V are turned off
The AI chassis has been taken out of the rack for further inspection
Entry  Tue Apr 1 11:47:08 2025, Liu, Update, ,  Thermal_state_decoder_update.pdf
 
Entry  Mon Apr 7 13:28:49 2025, Xuesi Ma, Update, ,  20250403_151946.jpgELOG_Spike_adapter_filter_on.png20250404_143624.jpgELOG_Spike_adapter_isolate.png20250407_105846.jpg
Test 1: Adapter Board Connected to Filter Board

  Setup: AI Chassis is powered on. Signal is measured directly from
the adapter board. All other ports on the adapter board are connected to the filter board.
  Observation: Two distinct spikes
observed at the beginning of the measurement.


Test 2: Adapter Board Disconnected from Filter Board

  Setup:
Entry  Tue Apr 15 11:13:43 2025, Xuesi Ma, Update, ,  20250414_120428.jpg20250414_120423.jpg20250411_163105.jpg
Test 4: AI Chassis ground isolation

  Setup: AI Chassis isolated from the ground with readout directly connected to
adapter board
  Observation: No spike observed.


Test 5: Ribbon cable check

  Setup:
AI Chassis remains isolated from the ground. The signal is measured after the ribbon cable. (Attachment 3)
  Observation: No
Entry  Tue Apr 22 12:08:46 2025, Xuesi Ma, Update, ,  20250415_161755.jpg20250416_174640.jpg20250422_105614.jpg
Test 7: Reconnect ribbon cables

  Setup: Reconnect all the ribbon cables, and turned on the AI Chassis while isolated
rack
  Observation: No spike observed.


Test 8: Reconnect to rack

  Setup:
Reconnect the AI Chassis to the rack.
  Observation: No spike observed.


Test 9: Restore to original position.

Entry  Tue May 6 13:19:31 2025, Xuesi Ma, Update, ,  resistance_vs_time_RV_rise_time_24.pdfresistance_vs_time_all_channels_all_time_RV.pdf
 
Entry  Tue May 13 12:35:01 2025, Xuesi Ma, Update, ,  resistance_vs_voltage_all.pdfresistance_vs_voltage_overlay.pdfresistance_vs_time_all_channels_all_time_RV.pdf
 
Entry  Mon May 19 10:59:14 2025, Xuesi Ma, Infrastructure, ,  


  Status Update

  Previous Status:
  All Sorensen power supplies were turned off. The Cymac system was down (all chassis were offline).
  
    If you need more information or assistance in turning them back on, please contact Xuesi Ma.
  
Entry  Tue May 27 12:52:22 2025, Xuesi Ma, Update, ,  6x
Using the configuration in section 2.11.1 in the Sorensen installation and operation manual (attached below), I'm able to remote control the Sorensen
power supply. 
I use DAC VEXC8 as the external voltage source and a breakout board to match the configuration of connector J3.
Entry  Tue Jun 3 13:08:47 2025, Xuesi Ma, Update, ,  934.jpg933.jpg
We currently have the parts for a DB9 connector but need parts for a DB25 connector, where did we get the parts for the DB9 connector? We may be able
to use the same company for the DB25 connector.
Also need a cable for the connectors. Find a DB9 to DB9 cable in 1129, not sure if I can disassemble it and use just the cable.
Entry  Tue Jun 3 13:16:53 2025, Xuesi Ma, Infrastructure, ,  928.jpg929.jpg931.jpg930.jpg932.jpg

    Date and Time: Around 3:50 PM on June 2, 2025
    Location and Temperature:
    
        Back of the room 1119, around the working station: 86 °F
        Front of the room 1119, around the doorway: 84.1
Entry  Tue Jun 10 12:13:00 2025, Xuesi Ma, Update, ,  resistance_vs_voltage.pdfresistance_vs_voltage_element_5.pdfresistance_vs_time_all_channels_all_time_RV.pdf

  By measuring the resistance of the ladder, I obtained a graph of resistance as a function of voltage.
  All the heater elements behave consistently, showing only a small standard deviation.
  However, heater element 5 shows a significantly larger standard deviation.
Entry  Tue Jun 17 12:22:43 2025, Xuesi Ma, Update, ,  12x



    
    
    CYMAC
Remote Control Cable Documentation
    
        .connector {
            background-color: #f8f9fa;
            border-left: 4px solid
#3498db;
            padding: 10px 15px;
            margin: 15px 0;
        }
        .pin-table {
            width: 100%;
            border-collapse:
Entry  Tue Jun 24 11:50:15 2025, Xuesi Ma, Update, ,  resistance_vs_time_all_channels_channel_switch.jpgresistance_vs_time_all_channels_channel_switch_one_cycle_before.jpgresistance_vs_time_all_channels_channel_switch_one_cycle_after.jpgresistance_vs_voltage.jpg



    
    
    Heater
Element Resistance Test Results
    
        .heater-test-container {
            font-family: Arial, sans-serif;
            line-height:
1.6;
            max-width: 800px;
            margin: 20px auto;
            padding: 20px;
            color: #333;
        }
        .heater-test-container
Entry  Tue Jul 1 13:41:36 2025, Xuesi Ma, Update, ,  
[Ma, Liu]
 Slides
Entry  Thu Jul 10 16:41:18 2025, Christina, Update, TCS,  2994921113032912040.JPG4717009101108174053.JPG5782646701589802125.JPG
 [Christina, Ma, Tyler] 

 Pomona Box completed and is now on the server rack in 1119. Additionally, the photodetectors were connected to the
box and set up in front of the heater elements. 
Entry  Tue Jul 15 10:40:23 2025, Christina, Update, TCS,  rpon.png
 [Christina, Ma, Tyler] 

 Yesterday, Ma and I started taking data for the PSD/CSD measurements while the photodetectors and one of the heater
elements are on (8) and are using the Red Pitaya to compare it to the data we took for the same measurements on the CyMAC. It will be finished Wednesday
morning, and then we plan on starting to take additional recordings in order to conduct the same type of comparison for the dark noise measurements. 
Entry  Tue Jul 15 11:47:53 2025, Xuesi Ma, Infrastructure, ,  20250701_165118.jpg20250701_165200.jpg20250701_165329.jpg20250701_165246.jpg

    Date and Time: Around 4:50 PM on July 1, 2025
    Location and Temperature:
    
        Back of the room 1119, around the working station: 85.7 °F
        Front of the room 1119, around the doorway:
Entry  Tue Jul 22 12:20:29 2025, Christina, Update, TCS,  PSDch0-15.pngCSD2hz_16hz.png
 [Ma, Christina, Tyler] 
 Figure 1 shows the following PSDs for channels 0-15 from the 14 hour test. Figure 2 shows the reduced chi squared and
CSD plots for both the 2 Hz and 16 Hz resolutions.
Entry  Thu Jul 31 14:26:58 2025, Xuesi Ma, Update, ,  2025-08-07_cleanroom_chart.png
[Tyler, Ma, Christina, Maple, Cece, Mary, Pooyan, Audrey]
We started by cleaning outside of the cleanroom wiping down the cable channel and working our way down while taking the pre-cleaning measurement.
We then stated wiping down the inside of clean room and vacuumed, mopped the outside of the cleanroom. Finally, we vacuumed, mopped, and wiped down the
Entry  Wed Aug 6 16:31:37 2025, Xuesi Ma, Update, ,  941.jpg942.jpg943.jpg945.jpg946.jpg

    Date and Time: Around 4:20 PM on Auguest 6, 2025
    Location and Temperature:
    
        Back of the room 1119, around the working station: 90.2 °F
        Front of the room 1119, around the doorway:
Entry  Tue Aug 12 13:32:43 2025, Liu, Update, Interferometer Simulations,  Screenshot_2025-08-12_at_1.31.11_PM.pngScreenshot_2025-08-12_at_1.31.17_PM.png
Differences in Fused Silica parameters.
Entry  Tue Aug 12 13:46:56 2025, Christina, Update, ,  3.png3-1.png
 
Entry  Tue Sep 9 12:01:38 2025, Tyler, Ma, Update, ,  
Slides
Entry  Tue Sep 9 13:08:44 2025, Xuesi Ma, Update, ,  
Slides