ligo-ex ligo-ds
  Richardson Lab Experimental Log, Page 11 of 14  Not logged in ELOG logo
    Reply  Tue Feb 20 08:01:30 2024, Jon, Infrastructure, General, Power and network equipment installed in 1129 rack IMG_0924.jpegIMG_0925.jpegIMG_0921.jpegIMG_0922.jpeg
[Jon, Tyler, Pooyan, Luis, Luke, Peter]
On Thursday we installed the power conditioning/distribution equipment and networking equipment in the new 1129
rack. The hardware is identical to the setup in the 1119 rack and includes:

Tripp Lite SU5KRT3UTF - 208V, 5kVA on-line UPS with 120V transformer
CyberPower PDU20M2F12R - metered power distribution unit,
Entry  Thu Feb 22 21:48:16 2024, Jon, Update, VAC, Vacuum vent for RGA testing of reflector IMG_0938.pngIMG_0939.png
[Jon, Tyler, Luke, Aiden]
Summary
Following Wednesday's cleanroom cleaning [333],
we proceeded to vent the vacuum chamber, remove the heater elements and their mount structure, and install the FROSTI reflectors. The reflectors are the
final components to undergo RGA testing before the FROSTI prototype can be assembled. After installing the reflectors, we pumped the chamber
Entry  Sat Feb 24 08:53:38 2024, Jon, Infrastructure, Computers, Matlab upgraded to 2023b on Chimay 
I upgraded Matlab on chimay to the latest stable release, 2023b. From some quick tests, it appears to be in working order. Let me know of any issues.
Entry  Mon Feb 26 21:23:27 2024, Jon, Update, TCS, FROSTI Assembly - Day 1 7x
[Jon, Tyler, Luis, Luke, Mohak, Cynthia, Michael, Aiden]
FROSTI assembly began today. After a final set of RGA scans were taken, the vacuum chamber
was vented and the reflectors were removed. The chamber was then resealed and pumped down again. 
Today we completed the installation of the Macor hardware and heater elements between the two reflector halves. Tomorrow we will route, bundle,
Entry  Thu Jun 20 18:01:11 2024, Jon, Infrastructure, Computers, New workstation ws3 in 1129 
I have repurposed a spare Intel NUC to serve as the first of two planned workstations in 1129. Today I set it up with a fresh installation of Debian 12.5,
assigned it the static IP address 192.168.1.15, and installed the LIGO CDS workstation packages. It is assigned the host name ws3.


Temporarily, the
mouse is borrowed from ws1 in 1119. We need to order another mouse as well as a 25-ft Ethernet cable for connecting the workstation to the 1129 switch,
    Reply  Wed Jun 26 15:33:41 2024, Jon, Infrastructure, Computers, New workstation ws3 in 1129 IMG_1368.jpg

Set-up of the first CDS workstation for 1129, ws3, is complete and the machine is ready for use. The login credentials are the same as the other lab
machines. 


All that now remains is to install a permanent cable tray for running the new Ethernet cables between the electronics rack and bench (they are
Entry  Thu Jul 11 21:01:37 2024, Jon, Infrastructure, General, Cable tray installed in 1129 IMG_1395.pngIMG_1396.png
Today I installed a 10' cable tray in 1129, for permanently routing Ethernet lines to the workstations. It is securely bolted to C-channels in the side
wall and in the center cable tray.
Entry  Fri Jul 26 17:25:42 2024, Jon, Infrastructure, Computers, New workstation ws4 installed in 1129 ws4.jpg
Today I installed the second desktop workstation in 1129. The new machine is an Intel NUC13ANHi5, with a 12-Core Intel i5-1340P CPU, 32GB DDR4 RAM, and
a 1TB SSD.
I loaded it with a fresh installation of Debian 12 and installed the LIGO CDS workstation (control room) tools. It is assigned the hostname ws4
    Reply  Tue Jul 30 07:42:47 2024, Jon, Infrastructure, General, Cable tray installed in 1119 cable_tray_1119.jpg
Yesterday I installed another 5' cable tray in 1119, for permanently routing Ethernet lines to the L-bench. It is securely bolted to the top of the electronics
rack, on one end, and to the top of the glass-door storage cabinet, on the other. This eliminates the need for the cable ramp which previously sat behind
the rack.
Entry  Thu Jan 22 10:10:31 2026, Jon, Infrastructure, General, Lab floor plans Pre-Feb-2026.pngPost-Feb-2026.png
Attached are the starting and final floor plans for the February 2026 expansion into the Physics 1125 lab.
    Reply  Thu Feb 5 11:42:47 2026, Jon, Infrastructure, General, Lab floor plans image.jpgimage_1.jpgimage_3.jpg
 [Audrey, Cece, Jon, Ma, Mary, Michael, Pooyan, Tyler, Shane] 
 We have completed the preliminary reorganization of our Physics 1119 lab space. This includes: 
 
 Moving all cabinets to their final positions 
 Clearing out all equipment from the cleanroom in prep for HVAC work, and storing
Entry  Fri Feb 10 16:34:45 2023, Huy Tuong Cao, Infrastructure, Clean & Bake, Nitrogen gas tank ready to use AirGunSealed.jpg
Cao,


Today I fixed the final bit related to the nitrogen gas tank, which is to apply sealing tape to M-NPT connector of the hose to prevent 
leakage
(file: AirGunSealed.jpg) 

After application of the tape, no audible leak can be heard from connection between the hose and the air gun. 
Entry  Mon Apr 8 14:57:41 2024, Cynthia, Pooyan, Update, Interferometer Simulations, performed cavity scans for O4 O5, and coupled cavity  LIGO_update_week1.pdf
 
Entry  Tue Feb 27 09:06:29 2024, Cynthia , Update, Interferometer Simulations, cavity scan with higher order input laser ligoPre_2_27.pdf
I performed a few cavity scan with the inputing laser with a different mode (not pure 00). For each laser I included a graph for just plotting the order
with highest power (for example 1st order laser input the first plot only scanned for 1st order in that cavity), and I have also included a graph scanning
for order 1-10. 
Entry  Mon Apr 22 15:06:33 2024, Cynthia , Update, Interferometer Simulations, cavity scan update LIGO_4_22.pdf
[Cynthia,Pooyan]
Completed some simulations injecting 0-10th order modes. Some graphs will be used for the poster after some further titles, axis, and
range adjustments. 
Entry  Mon Jun 24 14:28:51 2024, Cynthia , Update, Interferometer Simulations, SIS cavity with thermal effect ETM08thermal.png
tried to run a cavity scan with thermal deformation and ring heater for ITM04 ETM08 (aLIGO mirrors). Not sure about the accuracy of the graph as there is
some commands that still need to verified. 
Entry  Mon Jul 1 15:19:42 2024, Cynthia , Update, Interferometer Simulations, O4 and O5 mirror cavity scans with thermal effect cavityScan_07_01.pdf
 
Entry  Mon Jul 15 15:44:52 2024, Cynthia , Update, Interferometer Simulations, performed cavity scans with thermal effects and ring heater cavity_scan_07_15.pdf
 
Entry  Mon Aug 12 17:09:04 2024, Cynthia , Update, Interferometer Simulations, O4 vs O5 cavity scans with ITM plume guess or ETM O5_plots_and_tables.pdfO4_plots_and_tables.pdfETM12mapO5.pngScreenshot_2024-08-12_at_5.05.31_PM.png
So far the proposed solution for what to use for O5 ITM mirror for SIS simulations is either the plume guess file or using the O5 ETM mirror for ITM. I
had ran a cavity scan for both of these possibilities and it seems like the results produced are fairly different. The next step is most likely moving
on to adding the Frosti effects including both of the proposed possibilities, and before this, a few confirmations and verifications are needed using similar
Entry  Mon Aug 26 14:42:04 2024, Cynthia , Update, Interferometer Simulations, current status on cavity scan with effects of FROSTI LIGO_updates_8_26.pdf
I used the code and arm cavity model used for previous O5 study on mirrors and HOM (the pdf of the study and the result can be found at https://dcc.ligo.org/LIGO-G2100878),
but it seems like the result I obtained is different from the study result. Since my cavity scans codes have a large portion of it relying on this code,
I will have to go over the study result and the code to make sure there is no issue with that code itself first. There are also some other updates or issued
Entry  Mon Sep 16 15:18:59 2024, Cynthia , Update, Interferometer Simulations, a breakdown of FROSTI and thermal effects and the resulting cavity scan  ligo_update_9_16_(1).pdf
 
Entry  Mon Sep 23 15:00:41 2024, Cynthia , Update, Interferometer Simulations, corrections on assumption for O5 coating Uncoated_S1_ETM07-v2.pdf
The document recording ETM07 and ETM08 coating (T2300093) was discussed: 

the current plume files are not necessarily correct in a way that LIGO lab
have tried to add it on uncoated ETM such as ETM07 and it does not match what the coated ETM07 would look like. 

the plume should be added on top of
the uncoated ETM instead of assuming an ideal ETM. According to Garilynn, the imperfection on uncoated ETM matters. 

So far the possible ETM data used
Entry  Tue Jun 3 12:16:13 2025, Cynthia , Update, Interferometer Simulations, Point absorber simulation on radially averaged profile  update_6_3.pdf
 
Entry  Thu Feb 5 13:34:13 2026, Cynthia , Update, Interferometer Simulations, Point absorber + miscentering simulation  update2_5_(3).pdf
 
Entry  Mon Apr 15 15:25:10 2024, Cynthia, Update, Interferometer Simulations, progress on simulation so far LIGO_update_week3_(2).pdf
 
Entry  Mon Jun 3 14:59:44 2024, Cynthia, Update, Interferometer Simulations, Created cavity scan with LG modes  ligo_update_6_3.pdf
 
Entry  Mon Aug 19 07:11:55 2024, Cynthia, Update, Interferometer Simulations, cavity scans with FROSTI effects  LIGO_update_8_19.pdf
 
Entry  Wed Oct 2 13:38:00 2024, Cynthia, Update, Interferometer Simulations, cavity scan with averaged O4 ETM coating as plume O5plumevsCoating.pngO5CoatAvgpt5.pngO5AVgcoatingFROSTIpt5.PNG
 
Entry  Tue Feb 25 10:56:25 2025, Cynthia, Update, Interferometer Simulations, mirror coating added for simulation rerun updats_(3).pdf
I have tried to rerun the simulation on finesse after adding the mirror coating. The result has a large fluctuation in required input power vs arm power
that is concerning. I am currently working on potentially resolve this issue and get a reasonable graph before I proceed to optimizing the thermal maps.
Entry  Tue Mar 4 10:18:43 2025, Cynthia, Update, Interferometer Simulations, attempted to remove curvature and tilt for the coating  3_4_updates.pdf
 
Entry  Tue Mar 11 11:28:52 2025, Cynthia, Update, Interferometer Simulations, flattening mirror to study power discrepency updates_3_11_(1).pdf
 
Entry  Tue Apr 15 11:37:17 2025, Cynthia, Update, Interferometer Simulations, Finishing up mirror coating map step updates_4_15_2025.pdf
 
Entry  Thu Feb 19 12:34:18 2026, Cynthia, Update, Interferometer Simulations, Point absorber simulation update_2_18.pdf
 
Entry  Tue Aug 26 12:45:41 2025, Christina, Ma, Tyler, Update, CDS, RIN Update 
Slides
Entry  Fri Jun 27 15:38:22 2025, Christina, Update, TCS, FROSTI Reconstruction IMG_4009.png
 [Tyler, Ma, Christina, Luke] 

 We threaded the wiring of the heater elements through the reflective surfaces and were able to attach each piece with the Macor spacers and
connect both sides. We used the guide rails and screws to ensure proper alignment. The only necessary step left is to add the additional external screws
Entry  Tue Jul 1 11:04:00 2025, Christina, Update, TCS, FROSTI Reconstruction II IMG_4042.png
 [Ma, Tyler, Christina] 

 Finished external reconstruction of the FROSTI by installing all the pins to the 2 DB 25 connectors. To ensure everything
was operating correctly, we did electrical testing by testing continuity and by checking each of the heater elements' RTD and power resistance values and
comparing them to what was tabulated in January. Additionally, we organized the wires and added the stands. 
Entry  Mon Jul 7 16:39:18 2025, Christina, Update, TCS, Pomona Box Drawings pbdwg1.PDFpbdwg2.pdf
 Below are the drawings for the pomona box modifications 
Entry  Thu Jul 10 16:41:18 2025, Christina, Update, TCS,  2994921113032912040.JPG4717009101108174053.JPG5782646701589802125.JPG
 [Christina, Ma, Tyler] 

 Pomona Box completed and is now on the server rack in 1119. Additionally, the photodetectors were connected to the
box and set up in front of the heater elements. 
Entry  Tue Jul 15 10:40:23 2025, Christina, Update, TCS,  rpon.png
 [Christina, Ma, Tyler] 

 Yesterday, Ma and I started taking data for the PSD/CSD measurements while the photodetectors and one of the heater
elements are on (8) and are using the Red Pitaya to compare it to the data we took for the same measurements on the CyMAC. It will be finished Wednesday
morning, and then we plan on starting to take additional recordings in order to conduct the same type of comparison for the dark noise measurements. 
Entry  Tue Jul 15 13:13:48 2025, Christina, Update, TCS, Photodetector optical post assembly pdreassembly.png
 
Entry  Tue Jul 22 12:20:29 2025, Christina, Update, TCS,  PSDch0-15.pngCSD2hz_16hz.png
 [Ma, Christina, Tyler] 
 Figure 1 shows the following PSDs for channels 0-15 from the 14 hour test. Figure 2 shows the reduced chi squared and
CSD plots for both the 2 Hz and 16 Hz resolutions.
Entry  Tue Jul 29 12:30:00 2025, Christina, Update, TCS, 260 hour ADC update CSD_06_28_25_270hr.png
 [Ma, Christina, Tyler] 

ADC CyMAC 260 hr, 8192Hz sampling rate channels V3 and Vref6
Entry  Mon Aug 11 22:19:50 2025, Christina, Update, TCS, Red Pitaya Data Streaming 3.png3-1.png
 [Ma, Tyler, Christina] 

 This past week, we were able to set up the data streaming for continuous acquisition to the PCs, and can conduct the initial tests now. We were
able to do this by:


 Installing the correct OS ecosystems to each Red Pitaya 
 Installing the terminal streaming client 
Entry  Tue Aug 12 13:46:56 2025, Christina, Update, ,  3.png3-1.png
 
Entry  Tue Aug 19 12:08:40 2025, Christina, Update, TCS, RP Initial vs CyMAC Plot Comparisons 11hzCSD.png11hzstrain.png
[Tyler, Ma, Christina]


These are the frequency averaged and veto binned plots for the initial Red Pitaya and CyMAC systems.
Entry  Thu Jul 27 10:18:43 2023, Celeste, Update, TCS, Graphical Updates to HOM RH Modification HOM_RH_1_8_Unit_Modification_Graphs.pdf
Attached are updated graphs of the irradiance distribution from the 1/8th ring heater units (extruded and reduced in length). 
Entry  Fri Jul 28 17:45:45 2023, Celeste, Update, TCS, Graphical Updates to HOM RH Modification, Friday 7/28 HOM_RH_Simulation_Progress.pdf
Updated 1/8th Heater simulation modification graphs. Slides 7, 10, 16-19 are new additions.
Entry  Tue Aug 1 16:22:35 2023, Celeste, Update, TCS, Graphical Updates to HOM RH Modification, Tuesday 8/1 HOM_RH_Simulation_Progress_80123.pdf
Slides 20-33 are newly added (data/graphs from parameter sweep feature-1/8th heater unit length varied from 10% of original to 100% of original). 
Entry  Thu Aug 10 14:13:38 2023, Celeste, Update, TCS, 8/10/23, Simulation Graphical Progress Simulation_Progress__8_10_23.pdf
 
Entry  Fri Aug 11 10:57:20 2023, Celeste, Update, TCS, 8/11/23 Simulation Progress Simulation_Progress__1_32nd_Model_(1).pdf
 
ELOG V3.1.3-7933898