Fri Aug 11 10:57:20 2023, Celeste, Update, TCS, 8/11/23 Simulation Progress
|
Tue Aug 15 16:10:06 2023, Celeste, Update, TCS, 8/15/2023 Simulation Progress
|
Tue Jun 21 18:31:49 2022, Cassidy and Phoebe, Update, Cameras, IR Absorbing Screen and FLIR Camera Setup
|
Tue Jul 26 14:10:35 2022, Cassidy, Update, Cameras, Optical Post Replacement and Realignment
|
Thu Apr 27 16:23:44 2023, Cao, Pamella and Julian, Physics, VAC, Installing vacuum system (cont.)
|
Mon Oct 3 17:21:39 2022, Cao, Update, TCS, Inspection of macor parts 7x
|
Tue Apr 11 13:15:40 2023, Cao, Infrastructure, Clean & Bake, Nitrogen gas tank replaced
|
Wed Apr 12 16:13:19 2023, Cao, Physics, VAC, Vacuum prep and installation
|
Fri Apr 28 18:16:57 2023, Cao, Physics, VAC, Grounding vacuum system
|
Fri Apr 28 19:00:13 2023, Cao, Physics, VAC, Tighten CF ports on vacuum chamber
|
Fri Apr 28 19:39:19 2023, Cao, Summary, General, Clean and Bake Leybold TTR 91 Pirani Gauge
|
Sun May 14 15:50:48 2023, Cao, Infrastructure, Computers, High resolution display of logrus machine
|
Wed Jun 21 20:25:05 2023, Cao, Infrastructure, VAC, Vacuum chamber bake attempt 1 6x
|
Mon Jul 3 14:32:24 2023, Cao, Infrastructure, VAC, Cooling down vacuum chamber
|
Mon Jul 3 16:26:21 2023, Cao, Infrastructure, DAQ, Access and control Red Pitaya remotely and run it on local machine
|
Fri May 12 20:28:34 2023, Aiden, Cao, Physics, VAC, Vacuum chamber Helium leak test
|
Wed Jul 5 15:46:47 2023, Aiden, Cao, Infrastructure, VAC, Vacuum Chamber Baking Update
|
Thu Jan 26 18:58:25 2023, Aiden, Update, General, Oven Heating
|
Tue Feb 7 17:27:30 2023, Aiden, Physics, ELOG, Clean and Bake Batch #1
|
Fri Feb 10 15:15:30 2023, Aiden, Update, General, Bagging First Batch
|
Mon Feb 13 18:57:53 2023, Aiden, Summary, General, Clean and Bake batch 2
|
Fri Feb 17 19:12:39 2023, Aiden, Update, General, Clean and Bake batch 3
|
Tue Feb 21 17:51:04 2023, Aiden, Summary, General, Clean and Bake batch 4
|
Tue Feb 28 19:37:22 2023, Aiden, Summary, General, Clean and Bake batch 5
|
Fri Mar 3 19:13:33 2023, Aiden, Summary, General, Clean and Bake Batch 6
|
Wed Mar 8 19:29:00 2023, Aiden, Summary, General, Clean and Bake batch 7
|
Tue Mar 14 18:21:41 2023, Aiden, Summary, General, Clean and Bake batch 8
|
Fri Mar 17 19:46:39 2023, Aiden, Summary, General, Clean and Bake batch 9
|
Mon Apr 3 17:04:05 2023, Aiden, Summary, General, IDP Scroll Pump Assembly
|
Wed Apr 12 10:53:02 2023, Aiden, Summary, General, Valve Cleaning
|
Mon Apr 17 17:06:49 2023, Aiden, Summary, General, Clean and Bake batch 11
|
Mon Apr 24 17:38:45 2023, Aiden, Summary, General, Clean and Bake Batch 12
|
Thu Apr 27 09:48:34 2023, Aiden, Summary, General, Batch 12 Bagging
|
Wed May 10 10:49:34 2023, Aiden, Update, General, RGA Software
|
Wed May 31 16:18:41 2023, Aiden, Summary, General, Mock FROSTI
|
Tue Jun 6 16:04:46 2023, Aiden, Update, General, Water
|
Tue Jun 13 13:25:05 2023, Aiden, Summary, Clean & Bake, Clean and Bake Batch 13
|
Fri Jun 16 17:40:28 2023, Aiden, Update, Clean & Bake, Clean and Bake Batch 14
|
Wed Jul 5 16:02:12 2023, Aiden, Update, Clean & Bake, Clean and Bake batch 14 Bagging
|
Thu Jul 6 16:16:03 2023, Aiden, Summary, VAC, Vacuum Chamber Baking Update
|
Fri Jul 7 15:11:39 2023, Aiden, Update, VAC, VAC System Heating Update
|
Mon Jul 10 13:23:23 2023, Aiden, Update, VAC, VAC System Heating Update
|
Thu Jul 13 14:56:43 2023, Aiden, Update, VAC, VAC System Heating Update
|
Fri Jul 14 14:37:25 2023, Aiden, Update, VAC, VAC System Heating Update
|
Mon Jul 17 13:50:41 2023, Aiden, Update, VAC, VAC System Heating Update
|
Mon Jul 17 14:01:41 2023, Aiden, Update, VAC, VAC System Heating Update
|
Thu Jul 20 18:03:19 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update
|
Fri Jul 28 13:46:17 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update
|
Tue Aug 1 12:10:03 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update
|
Tue Aug 1 12:48:41 2023, Aiden, Update, Cleanroom, Pre Filter Change
|
|