Tue May 9 15:49:20 2023, Jon, Infrastructure, VAC, Permanent cable routing
|
Today I brought in a fresh supply of zip ties (we now have 1500 in the tool chest) and used them to permanentize the cable routing for the gauges, pumps,
and RGA.
I also brought and installed a 3-foot 15A extension cable for powering the scroll pump. Installing the cable required shutting down the pumps, |
Tue May 9 20:55:12 2023, Jon, Infrastructure, VAC, Calibrated Ar leak rate
|
For future reference, the calibrated Argon source has a leak rate of 7.55E-8 atm cc/s, or equivalently 5.74E-8
torr L/s. This can be used to calibrate RGA scans to units of physical leakage (outgassing) rate. |
Tue Jun 27 21:47:56 2023, Jon, Infrastructure, VAC, Vacuum chamber bake attempt 1
|
The electrical overload problem encountered in ELOG 130 has been resolved. The two heater controllers,
which draw up to 14.1 A each, overloaded the UPS and tripped one of its circuit breakers, shutting off power to both power strips mounted above the optical
table. |
Thu Jul 13 15:31:21 2023, Jon, Update, General, Ant traps placed around lab
|
In response to reports that ants have been observed in the lab, I placed five ant bait traps around the room today. Each is sitting on the floor on top
of a piece of aluminum foil, in areas unlikely to be inadvertently stepped on. They contain liquid which will spill
out if picked up, so please take care not to disturb them. |
Thu Jul 13 16:59:03 2023, Jon, Update, General, Ant traps placed around lab
|
Update: After seeing the strong response to the first set, I redistributed them to the hottest spots and added one more trap.
Quote:
In response to reports that ants have been observed in the lab, |
Mon Jul 24 14:55:53 2023, Jon, Update, VAC, Removed extension power cable
|
I removed the extension cable that was powering the leftmost heater controller, since there is no bake currently happening. It is currently powering the
LED over the electronics bench, and can be removed if needed. I will be ordering more extension cords to permanentize our setups. |
Wed Aug 9 11:32:56 2023, Jon, Infrastructure, General, New power cables
|
I delivered new NEMA 5-15 (120V / 15 A) power cables to the lab for the following items:
WS2 (cleanroom) cart - 10ft cable
Electronics workbench overhead LED - 10ft cable
Both PI heater controller sets - (2)
6ft cables
I installed the new cables on the WS2 cart and the workbench myself, and left the two 6ft cables (as pictured below) for Aiden |
Thu Aug 10 15:10:12 2023, Jon, Update, VAC, VAC System Heating Update
|
I shut down the turbo pump since this is evidently a large leak. We CANNOT turn on the RGA for leak checking with the pressure above 1E-5 Torr.
I think
we will have to manually inspect it. The most likely cause would be that the Viton seal around the lid overheated and failed.
|
Wed Oct 11 20:47:11 2023, Jon, Update, VAC, Vacuum upgrade begins
|
[Jon, Tyler, Aiden, Peter]
Upgrade of the UHV system to a larger turbo pump began today. After obtaining a final RGA scan in the old configuration (Aiden to post), we vented
all three volumes and proceeded to disassemble the 4.5"-diameter pump line. We completed installation of the new 6"-diameter pump line to the point where |
Mon Oct 30 08:42:22 2023, Jon, Update, VAC, Vacuum Leak Test
|
By 5:30 pm Friday, the pressure had reached 8.6e-8 torr and was continuing to fall. So it seems we are OK to proceed with permanentizing this configuration
(cable routing, heater tape reinstallation).
|
Wed Nov 8 17:55:49 2023, Jon, Update, General, Lab Clean-Up Day 1
|
[Jon, Tyler, Shane, Peter, Luis]
Today we completed the first phase of lab clean-up. Activities included:
CF/KF parts stored under the cleanroom table were removed and transferred to Physics 1129
Cleanroom workbench cleared, with all |
Fri Nov 10 08:32:34 2023, Jon, Update, VAC, RGA experiments
|
I ran a 3-minute degas cycle of the RGA filament for the first time yesterday (in this process, the filament gets very hot in
order to "boil off" settled particulate). I was surprised to see the pressure (of not just the RGA volume, but also
the main volume) rise from 2e-8 to 5e-6 torr.
This observation, |
Tue Nov 14 17:21:40 2023, Jon, Update, VAC, RGA best practices
|
As a follow up ELOG 261, I have received advice from one of the vacuum experts at LIGO Hanford
on best practices for our RGA:
For future RGA degassing, definitely keep the main volume isolated, since it |
Thu Nov 23 12:34:44 2023, Jon, Update, CDS, DB25 signal connections for FROSTI heaters
|
Update: I was able to put the FROSTI power controller on the lab network. It is connected to the switch in the top of the rack and is assigned
a static IP address of 192.168.1.12 and an NDS hostname of relay1.
The controller can be remotely accessed through an SSH command line interface as well as an HTML webpage, which can be opened from any web browser |
Sat Dec 9 12:34:12 2023, Jon, Update, General, Electronics workshop migrated to 1129
|
[Jon, Tyler, Shane, Luis]
On Wednesday we completed the migration of the electronics workshop from 1119 to the large new workbenches in 1129. The two workstations pictured
closest to the front of the room are for electronics assembly and testing, while the two in the rear will house LIGO CDS workstations. We moved all of |
Mon Dec 11 16:20:17 2023, Jon, Summary, TCS, FROSTI Assembly Procedure
|
Below is the procedure we will follow to assemble the FROSTI prototype.
Install SS guide rods and bottom Macor spacers in bottom reflector
Install AlN elements on top of bottom Macor spacers
Install
upper Macor spacers on top of AlN elements
Feed unterminated power and RTD leads through slots in upper reflector
Install upper reflector, |
Sun Dec 17 21:04:15 2023, Jon, Infrastructure, Clean & Bake, Clean and bake lab migrated to 1129
|
[Jon, Tyler, Aiden, Luke]
On Friday we completed assembly of the new stainless steel-topped benches in 1129. We then moved the clean and bake equipment from 1119 to its
new larger space in 1129. This included the HEPA flow bench, ultrasonic washer, deionized water drum, nitrogen tanks, and forced-convection oven. The oven |
Wed Dec 20 10:33:34 2023, Jon, Infrastructure, Clean & Bake, Clean and bake lab migrated to 1129
|
Update: I have completed permanent routing of the electrical cables. I also ran the ultrasonic washer's drain line to
the sink drain (the current hose does reach). The new clean and bake lab is now fully operational.
|
Fri Dec 29 16:02:27 2023, Jon, Configuration, Electronics, RTD Readout Chassis
|
The custom front and rear panels for the RTD readout chassis arrived last Friday. I installed them in the chassis frame to check their fit. They fit
very well, so all that now remains is to complete the internal wiring and test the connections.
The chassis panel designs are archived to LIGO-D2300452 and LIGO-D2300453. |
Mon Jan 15 22:29:34 2024, Jon, Infrastructure, General, Cabinet installation & lab clean-up completed
|
[Jon, Tyler, Aiden, Shane, Pooyan, Michael, Cynthia, Luke]
On Wednesday, we completed long list of work towards making the new lab (1129) fully operational and enabling the next phase of FROSTI testing.
Cabinet Installation
Three new VWR cabinets with sliding glass doors were installed in 1129. Each unit measures 48" |
Fri Feb 2 16:56:56 2024, Jon, Update, CDS, RTS model implemented for FROSTI RTD readouts
|
Summary
Today I finished implementing an RTS model to read out the integrated FROSTI RTDs (temperature sensors) via the CyMAC. The model is
named "MSC" and is located at cymac:/opt/rtcds/usercode/models/c1msc.mdl. We successfully tested it with the heater elements operating in vacuum at low
power (12 VDC), finding them to reach an average steady-state temperature of 160 C. |
Fri Feb 16 18:37:28 2024, Jon, Update, VAC, Bake ended 6:23 pm
|
I ended the bake of the UHV system (that began on Monday) at 6:23 pm today by switching OFF both PID controllers. The heaters elements were run at max
power (24 V DC / 200 mA per element) during this bake, and I left them powered at the same level.
At the time, the instrument readings were as follows: |
Tue Feb 20 08:01:30 2024, Jon, Infrastructure, General, Power and network equipment installed in 1129 rack
|
[Jon, Tyler, Pooyan, Luis, Luke, Peter]
On Thursday we installed the power conditioning/distribution equipment and networking equipment in the new 1129
rack. The hardware is identical to the setup in the 1119 rack and includes:
Tripp Lite SU5KRT3UTF - 208V, 5kVA on-line UPS with 120V transformer
CyberPower PDU20M2F12R - metered power distribution unit, |
Thu Feb 22 21:48:16 2024, Jon, Update, VAC, Vacuum vent for RGA testing of reflector
|
[Jon, Tyler, Luke, Aiden]
Summary
Following Wednesday's cleanroom cleaning [333],
we proceeded to vent the vacuum chamber, remove the heater elements and their mount structure, and install the FROSTI reflectors. The reflectors are the
final components to undergo RGA testing before the FROSTI prototype can be assembled. After installing the reflectors, we pumped the chamber |
Sat Feb 24 08:53:38 2024, Jon, Infrastructure, Computers, Matlab upgraded to 2023b on Chimay
|
I upgraded Matlab on chimay to the latest stable release, 2023b. From some quick tests, it appears to be in working order. Let me know of any issues. |
Mon Feb 26 21:23:27 2024, Jon, Update, TCS, FROSTI Assembly - Day 1 7x
|
[Jon, Tyler, Luis, Luke, Mohak, Cynthia, Michael, Aiden]
FROSTI assembly began today. After a final set of RGA scans were taken, the vacuum chamber
was vented and the reflectors were removed. The chamber was then resealed and pumped down again.
Today we completed the installation of the Macor hardware and heater elements between the two reflector halves. Tomorrow we will route, bundle, |
Thu Jun 20 18:01:11 2024, Jon, Infrastructure, Computers, New workstation ws3 in 1129
|
I have repurposed a spare Intel NUC to serve as the first of two planned workstations in 1129. Today I set it up with a fresh installation of Debian 12.5,
assigned it the static IP address 192.168.1.15, and installed the LIGO CDS workstation packages. It is assigned the host name ws3.
Temporarily, the
mouse is borrowed from ws1 in 1119. We need to order another mouse as well as a 25-ft Ethernet cable for connecting the workstation to the 1129 switch, |
Wed Jun 26 15:33:41 2024, Jon, Infrastructure, Computers, New workstation ws3 in 1129
|
Set-up of the first CDS workstation for 1129, ws3, is complete and the machine is ready for use. The login credentials are the same as the other lab
machines.
All that now remains is to install a permanent cable tray for running the new Ethernet cables between the electronics rack and bench (they are |
Thu Jul 11 21:01:37 2024, Jon, Infrastructure, General, Cable tray installed in 1129
|
Today I installed a 10' cable tray in 1129, for permanently routing Ethernet lines to the workstations. It is securely bolted to C-channels in the side
wall and in the center cable tray. |
Fri Jul 26 17:25:42 2024, Jon, Infrastructure, Computers, New workstation ws4 installed in 1129
|
Today I installed the second desktop workstation in 1129. The new machine is an Intel NUC13ANHi5, with a 12-Core Intel i5-1340P CPU, 32GB DDR4 RAM, and
a 1TB SSD.
I loaded it with a fresh installation of Debian 12 and installed the LIGO CDS workstation (control room) tools. It is assigned the hostname ws4 |
Tue Jul 30 07:42:47 2024, Jon, Infrastructure, General, Cable tray installed in 1119
|
Yesterday I installed another 5' cable tray in 1119, for permanently routing Ethernet lines to the L-bench. It is securely bolted to the top of the electronics
rack, on one end, and to the top of the glass-door storage cabinet, on the other. This eliminates the need for the cable ramp which previously sat behind
the rack. |
Fri Feb 10 16:34:45 2023, Huy Tuong Cao, Infrastructure, Clean & Bake, Nitrogen gas tank ready to use
|
Cao,
Today I fixed the final bit related to the nitrogen gas tank, which is to apply sealing tape to M-NPT connector of the hose to prevent
leakage
(file: AirGunSealed.jpg)
After application of the tape, no audible leak can be heard from connection between the hose and the air gun. |
Mon Apr 8 14:57:41 2024, Cynthia, Pooyan, Update, Interferometer Simulations, performed cavity scans for O4 O5, and coupled cavity
|
|
Tue Feb 27 09:06:29 2024, Cynthia , Update, Interferometer Simulations, cavity scan with higher order input laser
|
I performed a few cavity scan with the inputing laser with a different mode (not pure 00). For each laser I included a graph for just plotting the order
with highest power (for example 1st order laser input the first plot only scanned for 1st order in that cavity), and I have also included a graph scanning
for order 1-10. |
Mon Apr 22 15:06:33 2024, Cynthia , Update, Interferometer Simulations, cavity scan update
|
[Cynthia,Pooyan]
Completed some simulations injecting 0-10th order modes. Some graphs will be used for the poster after some further titles, axis, and
range adjustments. |
Mon Jun 24 14:28:51 2024, Cynthia , Update, Interferometer Simulations, SIS cavity with thermal effect
|
tried to run a cavity scan with thermal deformation and ring heater for ITM04 ETM08 (aLIGO mirrors). Not sure about the accuracy of the graph as there is
some commands that still need to verified. |
Mon Jul 1 15:19:42 2024, Cynthia , Update, Interferometer Simulations, O4 and O5 mirror cavity scans with thermal effect
|
|
Mon Jul 15 15:44:52 2024, Cynthia , Update, Interferometer Simulations, performed cavity scans with thermal effects and ring heater
|
|
Mon Aug 12 17:09:04 2024, Cynthia , Update, Interferometer Simulations, O4 vs O5 cavity scans with ITM plume guess or ETM
|
So far the proposed solution for what to use for O5 ITM mirror for SIS simulations is either the plume guess file or using the O5 ETM mirror for ITM. I
had ran a cavity scan for both of these possibilities and it seems like the results produced are fairly different. The next step is most likely moving
on to adding the Frosti effects including both of the proposed possibilities, and before this, a few confirmations and verifications are needed using similar |
Mon Aug 26 14:42:04 2024, Cynthia , Update, Interferometer Simulations, current status on cavity scan with effects of FROSTI
|
I used the code and arm cavity model used for previous O5 study on mirrors and HOM (the pdf of the study and the result can be found at https://dcc.ligo.org/LIGO-G2100878),
but it seems like the result I obtained is different from the study result. Since my cavity scans codes have a large portion of it relying on this code,
I will have to go over the study result and the code to make sure there is no issue with that code itself first. There are also some other updates or issued |
Mon Sep 16 15:18:59 2024, Cynthia , Update, Interferometer Simulations, a breakdown of FROSTI and thermal effects and the resulting cavity scan
|
|
Mon Sep 23 15:00:41 2024, Cynthia , Update, Interferometer Simulations, corrections on assumption for O5 coating
|
The document recording ETM07 and ETM08 coating (T2300093) was discussed:
the current plume files are not necessarily correct in a way that LIGO lab
have tried to add it on uncoated ETM such as ETM07 and it does not match what the coated ETM07 would look like.
the plume should be added on top of
the uncoated ETM instead of assuming an ideal ETM. According to Garilynn, the imperfection on uncoated ETM matters.
So far the possible ETM data used |
Mon Apr 15 15:25:10 2024, Cynthia, Update, Interferometer Simulations, progress on simulation so far
|
|
Mon Jun 3 14:59:44 2024, Cynthia, Update, Interferometer Simulations, Created cavity scan with LG modes
|
|
Mon Aug 19 07:11:55 2024, Cynthia, Update, Interferometer Simulations, cavity scans with FROSTI effects
|
|
Wed Oct 2 13:38:00 2024, Cynthia, Update, Interferometer Simulations, cavity scan with averaged O4 ETM coating as plume
|
|
Thu Jul 27 10:18:43 2023, Celeste, Update, TCS, Graphical Updates to HOM RH Modification
|
Attached are updated graphs of the irradiance distribution from the 1/8th ring heater units (extruded and reduced in length). |
Fri Jul 28 17:45:45 2023, Celeste, Update, TCS, Graphical Updates to HOM RH Modification, Friday 7/28
|
Updated 1/8th Heater simulation modification graphs. Slides 7, 10, 16-19 are new additions. |
Tue Aug 1 16:22:35 2023, Celeste, Update, TCS, Graphical Updates to HOM RH Modification, Tuesday 8/1
|
Slides 20-33 are newly added (data/graphs from parameter sweep feature-1/8th heater unit length varied from 10% of original to 100% of original). |
Thu Aug 10 14:13:38 2023, Celeste, Update, TCS, 8/10/23, Simulation Graphical Progress
|
|