  533   Wed Mar 5 12:16:28 2025 ShaneUpdateCDSVac system communications update

[Shane, Jon]

Update on the serial interfacing
with the vacuum system: both turbo pumps
  
  518   Wed Feb 19 13:44:48 2025 ShaneUpdateCDSVac serial interfacing update


[Jon, Shane]



Debugging update for vac system serial
communications: we were able to successfully
  
  484   Wed Dec 4 16:01:23 2024 ShaneUpdateCDSVac serial interfacing troubleshooting updateUpdate on the issue with serial interfacing
for the TV 551 turbo pump: Tried a new test
today, to see if the commands being sent
  
  293   Sun Dec 17 19:43:18 2023 AidenUpdateVACVac Heating Update[Aiden]

I measured the temperature of
the flanges where some of the electronics
will go and I found that the RGA flange was
  
  242   Mon Oct 23 07:28:57 2023 PeterUpdateVLC UpdateVLC Mode MatchingI have attached a pdf with slides of my latest
updates. 
 Carney_VLC_Update.pdf 
  256   Mon Nov 6 11:31:25 2023 PeterUpdateVLC UpdateVLC Mode MatchingSee Update Attached  VLC_Update_11_6_23.pdf 
  263   Mon Nov 13 06:15:45 2023 PeterUpdateVLC UpdateVLC Mode MatchingWeekly Updates Attached in pdf  VLC_Mode_Matching_3.pdf 
  221   Thu Sep 7 19:24:25 2023 PeterUpdateVLC UpdateVLC Launch ChainThe launch optics up to the Faraday Isolator
have been added to the breadboard. In the
first image, the optics are (from L to R)
 IMG-3404(1).jpgIMG-3408(1).jpg 
  234   Mon Oct 9 11:06:17 2023 PeterUpdateVLC UpdateVLC Launch ChainImplemented the new stage for the EOM. Took
power data at different positions in the
launch chain. Beam waist: 0.066mm (beam waist
 IMG-3540.jpgIMG-3538.jpgIMG-3533.jpgIMG-3522.jpg 
  304   Tue Jan 16 10:01:21 2024 PeterUpdateVLC UpdateVLC Faraday Isolator and Mode MatchingAttached is a PDF of my weekly updates.   VLC_Mode_Matching_Design_-_Remastered.pdf 
  288   Fri Dec 8 11:15:21 2023 PeterUpdateVLC UpdateVLC AssemblyThe optics of the visible light cavity have
been assembled. The mode matching telescope
is folded through the two stirring mirrors
 IMG_4194.jpgIMG_4195.jpgIMG_4197.jpgIMG_4196.jpg 
  360   Mon Apr 15 11:51:03 2024 PeterUpdateVLC UpdateVLCAn update on the VLC project is attached below:  VLC_Update_April_15_2024.pdf 
  368   Mon May 13 14:53:29 2024 PeterUpdateVLC UpdateVLCVLC Update WEEK 7 attached below  VLC_Update.pdf 
  301   Tue Jan 9 16:35:09 2024 AidenUpdateVACVAC System Leak and Heating[Luis, Luke, Aiden]

Leak tested each
flange and weld and only found two flanges
to have noticeable leaks with the electron
  
  150   Fri Jul 7 15:11:39 2023 AidenUpdateVACVAC System Heating Update
The temperature of the flange connecting
to the turbo pump after reaching equilibrium
is 74 degC. This means that it is safe to
  
  152   Mon Jul 10 13:23:23 2023 AidenUpdateVACVAC System Heating Update
Checked on the system today. 


The
flange on the turbo pump has reached an equilibrium
temperature of 87 degC when set at 150 degC.
  
  153   Thu Jul 13 14:56:43 2023 AidenUpdateVACVAC System Heating Update
Checked on the vacuum system today to
change the PID controls back to their default
values in order to try and get the temperature
  
  156   Fri Jul 14 14:37:25 2023 AidenUpdateVACVAC System Heating Update
Checked on the vacuum system and it looks
like it will either need to be increased
in temperature or baked for a longer time.
  
  160   Mon Jul 17 13:50:41 2023 AidenUpdateVACVAC System Heating Update
Started to cool down the chamber today.
Final temperature readings of the chamber
were 146C and 91C for the body and cross
  
  161   Mon Jul 17 14:01:41 2023 AidenUpdateVACVAC System Heating Update
The insulation on the lid of the vacuum
chamber has some discoloration and it may
be wise to place a sensor closer to this
 IMG_4535.jpg 
  188   Wed Aug 2 17:02:38 2023 AidenUpdateVACVAC System Heating Update
Moved the temperature sensor on the PID
controller to one of the switch backs on
the lid.


Also started the next
  
  189   Thu Aug 3 16:00:25 2023 AidenUpdateVACVAC System Heating UpdateCheck on the temperature of the bake today
to see the equilibrium temperatures. With
both of the PID controllers set to 150 C,
  
  192   Fri Aug 4 15:21:33 2023 AidenUpdateVACVAC System Heating UpdateChecked on Bake 3 today and the temperature
sensors read 126 C and 91 C for the chamber
barrel and turbo pump flange respectively.
  
  201   Thu Aug 10 14:36:00 2023 AidenUpdateVACVAC System Heating UpdateCame in to install one of the Full range gauges.
Checked the temperature first of the cross
and it was reading 30 C. After installing
  
  202   Thu Aug 10 15:10:12 2023 JonUpdateVACVAC System Heating UpdateI shut down the turbo pump since this is evidently
a large leak. We CANNOT turn on the RGA for
leak checking with the pressure above 1E-5
  
  203   Thu Aug 10 18:32:39 2023 AidenUpdateVACVAC System Heating Update
[Dr. Richardson, Aiden]


DO NOT TOUCH ANY VALVES ON THE
CHAMBER. THERE IS A PRESSURE DIFFERENTIAL
 IMG_4588.jpg 
  205   Fri Aug 11 18:32:00 2023 AidenUpdateVACVAC System Heating Update
[Dr. Richardson, Aiden] Large Update


Removed
most of the insulation on the chamber in
order to pull back some of the heater tape
 11x 
  219   Fri Sep 1 19:21:19 2023 AidenUpdateVACVAC System Heating UpdateStarted bake 5 today. This will hopefully
be a longer and hotter bake with it lasting
6-7 days at around 150 C. The pressure in
  
  220   Tue Sep 5 16:43:19 2023 AidenUpdateGeneralVAC System Heating UpdateChecked on bake 5 today after 3 days of equilibrium.
The RGA cross is at 106 C and the turbo pump
cross is at 74 C. This was reached while
  
  222   Fri Sep 8 16:10:43 2023 AidenUpdateVACVAC System Heating UpdateTurned off the PID controllers to let the
chamber cool down. Final temperatures for
the RGA cross and Turbo pump cross were 113
  
  223   Mon Sep 11 16:02:42 2023 AidenUpdateVACVAC System Heating UpdateThe chamber has cooled down from bake 5 and
I took the first set of data. The pressure
measured during the RGA measurements reached
 bake5_230911_ArO.pngbake5_230911_ArC.png 
  251   Tue Oct 31 19:46:35 2023 AidenUpdateVACVAC System Heating UpdateStarted bake 7 on Monday but found issues
with the heating as the cross in front of
the RGA got way too hot too quickly. This
 IMG_4745.jpgIMG_4744.jpg 
  253   Wed Nov 1 20:22:07 2023 AidenUpdateVACVAC System Heating UpdateRaised the PID controller temperature to 105C
today as at that temperature the lid and
the barrel temperature sensors were reading
  
  280   Wed Nov 29 21:13:32 2023 AidenUpdateVACVAC System Heating UpdateStarted Bake 8 today. Set the PID controllers
to 120 C and will check in the morning for
equilibrium temperatures for the lid and
  
  282   Thu Nov 30 13:58:18 2023 AidenUpdateVACVAC System Heating Update[Aiden]

Came into the lab in the morning
to check on the chamber heating. I decided
to set the PID controllers to 110C rather
  
  283   Sat Dec 2 18:10:23 2023 AidenUpdateVACVAC System Heating Update[Aiden]

Turned off the heating tape
today in anticipation to take more RGA data
on Sunday or Monday morning before the meeting.
  
  295   Mon Dec 18 15:51:49 2023 AidenUpdateVACVAC System Heating UpdateAfter letting the chamber cool down I put
the electronics back on and turned the RGA
element back on. No data has been taken yet
  
  190   Thu Aug 3 17:47:51 2023 AidenUpdateVACVAC Heating System Update
Did some further testing to determine
if it was within reason to increase the temperature
of the chamber. I used a thermometer and
  
  195   Tue Aug 8 15:31:26 2023 AidenUpdateVACVAC Heating System Update
Vacuum Chamber equilibrium temperature
for bake 3 are 126 C and 88 C for the chamber
wall and turbo pump flange respectively.
 10x 
  208   Tue Aug 15 16:04:23 2023 AidenUpdateVACVAC Heating System Update
Pulled off the rest of the heater tape
along with the aluminum tape left behind.
The aluminum tape adhesive left behind a
 6x 
  212   Thu Aug 17 15:02:44 2023 AidenUpdateVACVAC Heating System Update
Put the heating tape back on and made
sure to have 4 coils around the barrel of
the chamber. To make this happen I did not
 11x 
  213   Thu Aug 17 15:18:48 2023 AidenUpdateVACVAC Heating System UpdateRelocated the PID controllers so that the
heating tape could be plugged in. In the
picture the left one controls the top half
 IMG_4628.jpg 
  308   Thu Jan 18 15:13:37 2024 AidenUpdateVACVAC Heating System Update[Aiden]

Took more data today and the
chamber and elements are showing an even
lower HC level than we have gotten before.
 bake10_240118_Elements_ArO.pngJanuary_18_Ar_Open_Elements_Analyzed.png 
  325   Tue Feb 13 12:34:04 2024 AidenUpdateVACVAC Heating System UpdateHere is an overlay with for all the heating
steps done with the heater elements.
 bake10_240118_Elements_ArO.png 
  269   Thu Nov 16 19:32:31 2023 AidenUpdateVACVAC HC Levels UpdateTook some more RGA data today and overlaid
it with data taken from October 19. I added
a red line that symbolizes where all amu
 bake7_231116_ArO.pngNovember_15_Ar_Open_Analyzed.png 
  140   Fri Jun 30 16:43:14 2023 PamellaUpdateFLIRUpdates: Small moving the FLIR camera     [Pamella] 

Today, I was able to
make some adjustments to the FLIR camera
angle, suggested by  Dr. Richardson, and
 AcquisitionImage(Jun-30-2023_16_23)_(3).jpgAcquisitionImage(Jun-30-2023_16_23)_(1)(1).jpgAcquisitionImage(Jun-30-2023_16_24).jpgAcquisitionImage(Jun-30-2023_16_22)_(1)(1).jpgAcquisitionImage(Jun-30-2023_16_22)_(1).jpg 
  523   Tue Feb 25 01:37:00 2025 MichaelUpdateInterferometer SimulationsUpdates and Current Next Steps for Toroidal Mirrors ProjectSince the previous discussion of this project,
I've worked on building finesse models to
verify mathematical results which model the
  
  453   Wed Oct 2 12:20:43 2024 TylerUpdateTCSUpdated FROSTI Analysis 10/02/2024Attached below are updates on current FROSTI
prototype analysis.
 FROSTI_Analysis_Updates.pdf 
  414   Mon Jul 29 12:20:56 2024 LiuUpdateInterferometer SimulationsUpdate on wavefront actuation with astigmatically driven RH for CEUpdate on wavefront actuation with astigmatically
driven RH for CE is attached. 
 SURF_nonastig_merged.pdf 
  425   Fri Aug 16 12:51:46 2024 Luis MartinUpdateVACUpdate on vacuum chamber status[Luis, Luke, Tyler]

Vacuum chamber parts were finally
received and assembled. After whipping down
 IMG_1910.HEICIMG_1911.HEICIMG_1909.HEICIMG_1912.HEIC 