410
|
Tue Jul 16 18:43:07 2024 |
Shane | Update | CDS | ADC-DAC loopback testing and IOLAN installation |
UPDATE:
Follow up ADC-DAC loopback testing
now complete, matching all the ADC channels
to a single DAC channel, and then matching |
|
419
|
Fri Aug 2 13:50:22 2024 |
Shane | Update | CDS | Serial Comm. Test (Agilent Turbo Pump) | Did a brief communication test with the agilent
turbo pump today, to see if we could get
serial communications up and running for |
|
434
|
Tue Sep 3 18:24:17 2024 |
Tyler | Update | CDS | Cymac Timing Chassis Issue | [Tyler, Jon]
The timing chassis used
for the cymac has been shut off due to an
unknown issue causing its supplied current |
|
Draft
|
Tue Oct 1 19:41:23 2024 |
Shane | Update | CDS | CyMAC Timing Chassis Issue | [Shane, Luis]
Summary of the issue we've
been having with the timing chassis: when
we connect only the Valon 5015 to power, |
|
461
|
Thu Oct 17 13:24:23 2024 |
Shane | Update | CDS | Timing Chassis issue identified |
[Ma,
Luis, Shane]
Working theory for the
timing chassis issues had been that the 1A |
|
465
|
Fri Oct 25 10:56:30 2024 |
Shane | Update | CDS | Timing Chassis fixed and reinstalled |
[Ma, Shane]
We
replaced the 1A breaker in the timing chassis
today with a 4A one, and tested that all |
|
473
|
Thu Nov 14 11:58:05 2024 |
Shane | Update | CDS | Turbo pump connection troubleshooting | Attempted connection to the TV551 turbo pump
through Varian/Agilent's software on spica.
Successful connection established, and we |
|
8
|
Fri Jul 22 13:20:28 2022 |
Phoebe | Update | | Comsol | I will be using comsol until 1:30 pm today.
I will be updating the model for the heater
mount to be thicker in certain areas, so |
|
37
|
Tue Feb 28 19:33:51 2023 |
Peter | Update | | 532 M2 Measurements | Y axis of plot in units of micrometers. X
axis in units of millimeters. |
|
46
|
Wed Mar 8 18:35:52 2023 |
Pamella | Update | | Lab cleaning | Today Pamella finished cleaning of the cleanroom,
starting with the HEPA vacuuming, mopping
and clearing all floor with IPA wipes.
Also |
|
371
|
Fri May 31 19:37:47 2024 |
Luke | Update | | Vacuum chamber Disassembly | [Luke, Aiden, Jon, Michel, Tyler]
Work
done:
On Tuesday (5/28) we removed the RGA
line with minimal difficulty. On Wednesday |
|
378
|
Wed Jun 19 18:45:14 2024 |
Luke | Update | | Vacuum chamber reassembly | [Luke, Aiden, Mohak , Tyler]
On Tuesday
we had the silver screws for the spherical
cube shortened by a quarter of an inch so |
|
423
|
Mon Aug 12 16:35:30 2024 |
Luke | Update | | Ringheater modeling Update | |
|
451
|
Wed Oct 2 10:31:46 2024 |
Xuesi Ma | Configuration | | Group Meeting Slides 10/2/2024 |
Group Meeting slides for Non-deterministic
Heater Response.
|
|
452
|
Wed Oct 2 12:05:42 2024 |
Luke | Update | | Ringheater modeling Update | Power
point slides |
|
455
|
Wed Oct 2 14:49:59 2024 |
Liu | Update | | FROSTI ETM actuation | Proposed FROSTI ETM actuation on the HOM7
resonance.
Animation |
|
460
|
Wed Oct 16 14:13:31 2024 |
Liu | Update | | FROSTI with non uniform absorption scattering sources | Slides |
|
Draft
|
Wed Oct 23 12:33:54 2024 |
Luke | Update | | Zernike calculation update | PowerPoint
slides new
PowerPoint |
|