Wed Nov 20 12:59:37 2024, Tyler, Update, Electronics, RIN Update
|
I went ahead and compared the noise spectrum of the ADC to those of the photodetectors with the FROSTI on and off. As discussed last meeting, it looks like
the measurements with the Red Pitaya (RP) are limited by the ADC noise floor. Another avenue to explore in this measurement could be switching to the
cymac ADCs. |
Mon Aug 12 16:24:34 2024, Tyler, Update, Cleanroom, RIN Measurement Update 1
|
[Tyler]
For some preliminary tests, I moved the IR photodetectors outside of the cleanroom and onto the other optical table. The basic goal was
to obtain a signal from both photodetectors. To achieve this, one of the heater cartridges used for early FLIR measurements months ago was hooked up to
a power supply (PS). The PS was set to supply 0.20 A with a voltage of 2.8 V; the corresponding power is thus 0.56 W. With this, I was able to measure |
Mon Jul 29 14:30:16 2024, Tyler, Update, Cleanroom, RIN Measurement Set-up
|
[Tyler]
I have begun moving parts into the cleanroom for the upcoming FROSTI RIN tests that will be conducted within the next few weeks. While waiting
for the rest of the equipment to arrive to perform the full-scale tests, I have additionally moved the FROSTI under the shelf above the optical table,
where it will stay for the meantime. As always, please use caution when in the cleanroom. Aside from the FROSTI, the IR photodetectors that will be used |
Thu Jul 11 15:53:39 2024, Luke, Update, VAC, RGA line upgrade
|
[ Luke, Jon ]
Started work at 11:00
As mentioned in my previous post the RGA was not clearing the table because of a tilt in the cross. So I removed the 90 deg elbow, loosened the |
Fri Aug 23 16:08:32 2024, Luke, Update, VAC, RGA line leak testing
|
[Luke, Luis, Jon, Tyler]
On the 22nd Dr. Richardson showed Luis, Tyler and I how to preform a leak test with the RGA. We did the initiall test and found a few leaks two
were particuarly bad highlighted in orenge below. To try and remidy this we planned on replacing the copper gaskests on the leaking flanges. We then began |
Tue Aug 27 15:01:26 2024, Luke, Update, VAC, RGA line leak testing
|
[Luke, Tyler]
On the 27th Tyler and I ran the RGA leak test again with the electron multiplier on. These were the leaks we measured. The chamber's overall pressure
was at ~6e-8 torr. |
Wed Jul 10 17:31:07 2024, Luke, Update, VAC, RGA line disassembly and upgrade
|
[ Luke, Cynthia, Michael, Xuesi, Anthony ]
Started work around 12:45
We vented the chamber first and once it reached atmospheric pressure we started taking apart the RGA line. |
Fri Nov 10 08:32:34 2023, Jon, Update, VAC, RGA experiments
|
I ran a 3-minute degas cycle of the RGA filament for the first time yesterday (in this process, the filament gets very hot in
order to "boil off" settled particulate). I was surprised to see the pressure (of not just the RGA volume, but also
the main volume) rise from 2e-8 to 5e-6 torr.
This observation, |
Tue Nov 14 17:21:40 2023, Jon, Update, VAC, RGA best practices
|
As a follow up ELOG 261, I have received advice from one of the vacuum experts at LIGO Hanford
on best practices for our RGA:
For future RGA degassing, definitely keep the main volume isolated, since it |
Wed May 10 10:49:34 2023, Aiden, Update, General, RGA Software
|
[Aiden, Cao]
Went over how to use the RGA software, how to change the graph units, scaling and mass detection. Also went over how to remove the RGA from
the vacuum system as well as procedure for turning it on. |
Mon Sep 16 13:51:23 2024, Luis Martin, Update, VAC, RGA Scans
|
[Luis, Luke}
Three RGA scans were taken. The improvement in the amount of HC in the vacuum is visible across the different measurements.
Images are attached. |
Wed Sep 25 09:06:09 2024, Luis Martin, Update, VAC, RGA Scans
|
RGA
Scan Comparison
The following images compare the RGA scans from 9/23/24, after the first bake with the new vacuum system,
with those from 3/14/24, after bake 12 with the old system. |
Wed Oct 16 13:58:59 2024, Luis Martin, Update, VAC, RGA Scan
|
The following figure displays data acquired on 10/09, and it shows that we are no longer below the cleanliness standard. Also, the system's pressure
went up to 1.9x10-8 Torr (approximately 7x10-9 Torr previously). This might be due to a leak somewhere in the system. More tests
will be performed later. |
Wed Oct 23 12:08:36 2024, Luis Martin, Update, VAC, RGA Scan
|
[Luke, Luis, Mary, Ma]
On 10/22/24 Luke, Ma, Mary and myself ran a RGA scan, the results are displayed below. The overall pressure of the vacuum was 2.0e-8 and the temperature
readings were 26C for the RGA and 25C for the main volume. |
Wed Nov 6 13:48:55 2024, Liu, Update, Interferometer Simulations, QN modeling update
|
Slides |
Mon Jul 15 13:30:49 2024, Luke , Update, VAC, Problem with 2.75" to 1.33" zero length reducer
|
Last Friday while checking the depth of the ZLR I got one of the screws stuck. Today I tried a couple things to get it out. First I tried a few different
pliers to be able to grip lower on the screw this didn't work. So I switched to the other method of drilling a small hole to see if maybe the threads would
pull away from the walls of the hole a bit. This kind of worked as seen in the picture below I was able to remove most of the screw but there is a bit |
Mon Nov 6 11:29:24 2023, Tyler, Update, Electronics, Preliminary RTD Calculations, RP Software Update
|
Preliminary RTD calculations are shown below, given an input of 10 V and desiring a few mA of current. It looks like R_ref should be at least 1 kOhm
(refer to plots/circuit below), keeping in mind we need to have
RP: The Red Pitaya Software was updated to OS 2.00. All examples on the RP website should run without issue. |
Tue Aug 1 12:48:41 2023, Aiden, Update, Cleanroom, Pre Filter Change
|
Changed the pre filter inside of the 3 stage HEPA system next to the soldering station. It was rather dirty and I have attached images with a clean
filter on the left and the used one on the right. I reset the pre filter age on the system. I tried to see if I could tell if the HEPA filter was dirty
but I could not see it. I did not reset the age of the HEPA or UV stations. They are currently 378 days old.
|
Wed Jun 28 15:58:56 2023, Shane, Cao, Infrastructure, VAC, Power trip problem remains, source of smoke is insulation
|
[Shane, Cao]
With the new change in wiring configuration described in elog 136, we tried
to power up the heaters for baking the vacuum chamber again.
Given that we were worried about the turbo pump overheats, we set the setpoints of of bother high temperature controller and PID controller to |
Tue Feb 20 08:01:30 2024, Jon, Infrastructure, General, Power and network equipment installed in 1129 rack
|
[Jon, Tyler, Pooyan, Luis, Luke, Peter]
On Thursday we installed the power conditioning/distribution equipment and networking equipment in the new 1129
rack. The hardware is identical to the setup in the 1119 rack and includes:
Tripp Lite SU5KRT3UTF - 208V, 5kVA on-line UPS with 120V transformer
CyberPower PDU20M2F12R - metered power distribution unit, |
Tue Jul 18 16:35:06 2023, Pamella, Update, FLIR, Plot-Data with the new configuration without the mask and reflector.
|
[Pamella]
I was able to plot the first graph for a result between the six different positions on the screen, for now we can see the behavior
of the heater temperature in a Gaussian graph with combination data between the six files.
To do: Tyler gave me some ideas today to improve
the plot. So I'm going to change the code to have insulation on the values for just the heater ("insulation") and I'm going to plot after this insulation |
Thu Aug 29 16:39:34 2024, Luke, Update, VAC, Photos of heater tape 6x
|
|
Tue May 9 15:49:20 2023, Jon, Infrastructure, VAC, Permanent cable routing
|
Today I brought in a fresh supply of zip ties (we now have 1500 in the tool chest) and used them to permanentize the cable routing for the gauges, pumps,
and RGA.
I also brought and installed a 3-foot 15A extension cable for powering the scroll pump. Installing the cable required shutting down the pumps, |
Mon Nov 28 18:10:23 2022, shane, Update, ELOG, Particle counts in the clean room
|
Particle count stats for the clean room Nov 28, 2022:
Took 10 sample runs in each of 5 regions in the clean room (5 runs per region with a person inside
the clean room for the measurement, and 5 runs per region without anyone in the clean room for the measurement), for a total of 50 samples taken. Sample
time was 60 seconds. Overall clean room average particle count for the size ranges are as follows:
0.3 micrometers- 3405.76 (room occupied), 974.92 (room |
Tue Apr 4 16:52:08 2023, Jon, Update, Cleanroom, Particle counter docking station
|
Due to the problems we have encountered trying to serially communicate directly with the Met One DR-528 particle counter, I went ahead and ordered the add-on
communications/charging dock. The dock "ethernetizes" the serial communications by wrapping them in TCP packets and transmitting them over the lab network.
This will allow our Python code to communicate using the standard Internet sockets package, rather than PySerial, PyNut, etc.
the docking station arrived |
Wed Apr 12 16:17:50 2023, shane, Update, General, Particle Counter moved
|
With the added height of the new docking station, the particle counter no longer fits under the Windows monitor in the electronics rack and has been moved
to the desk in the corner of the lab. |
Mon Oct 9 11:29:37 2023, Tyler, Update, Electronics, PSD/CSD Plot Updates
|
Continuing from Sophia's SURF Project this summer: Plotting the Power-Spectral Densities (PSDs) and Cross-Spectral Densities of two signals.
A continued
issue that has been observed in the plots is the random "jump" of one PSD curves. Below, a 1.4 kHz signal is driven with a magnitude of 0.7 Vpp, and connected
to the two output ports of the Red Pitaya via an SMC T-Adapter. At the moment, I anticipate that this bug might have something to do with the Real-Time |
Wed Mar 1 21:27:20 2023, Jon, Infrastructure, Cleanroom, Over-table shelf height raised
|
Jon, Cao
Today we raised the height of the shelf overhanging the cleanroom laser table by 8 inches. This was done to create more vertical clearance between
the top-loading vacuum chamber and the bottom of the shelf. The added clearance should make both removing the chamber lid and inserting large parts easier. |
Mon Jan 23 17:26:15 2023, Peter Carney, Update, General, Oven cleaning
|
Aiden and Cao
Turned on the oven to 120 deg C for 12 hours. After 12 hours, put it at 200 deg C for 48 hours. |
Thu Jan 26 18:58:25 2023, Aiden, Update, General, Oven Heating
|
Aiden cleaned the oven with methanol again and set the oven to 260 degC for 12 hours. |
Fri Feb 23 18:03:27 2024, Tyler, Update, FLIR, Optical Test Setup in Cleanroom
|
[Tyler, Xuesi]
The FLIR and test mass stand-in have been transferred into the cleanroom. A software test will be run as soon as we get an ethernet
cable long enough to reach into the cleanroom where the camera is set up. Once this is finished, the FLIR will be moved aside for construction of the FROSTI!
When completed, the camera will be placed back into position for in-air optical testing.
|
Tue Jul 26 14:10:35 2022, Cassidy, Update, Cameras, Optical Post Replacement and Realignment
|
Today I replaced the 3" optical post that the camera rests on with a 2" optical post in order for the screen to correctly fill out the camera's FOV. The
3" post is now in the glass optics cabinet next to the FLIR camera configuration box, wrapped in the protective materials from the 2" post for safekeeping.
There were no issues with the physical replacement of the post, except that the fork clamp on the post needs to be on one of the perpendicular, |
Mon Aug 12 17:09:04 2024, Cynthia , Update, Interferometer Simulations, O4 vs O5 cavity scans with ITM plume guess or ETM
|
So far the proposed solution for what to use for O5 ITM mirror for SIS simulations is either the plume guess file or using the O5 ETM mirror for ITM. I
had ran a cavity scan for both of these possibilities and it seems like the results produced are fairly different. The next step is most likely moving
on to adding the Frosti effects including both of the proposed possibilities, and before this, a few confirmations and verifications are needed using similar |
Mon Jul 1 15:19:42 2024, Cynthia , Update, Interferometer Simulations, O4 and O5 mirror cavity scans with thermal effect
|
|
Tue Apr 11 13:15:40 2023, Cao, Infrastructure, Clean & Bake, Nitrogen gas tank replaced
|
The nitrogen gas tank has been replaced with a new unit. The new tank is ultra pure nitrogen (>99.9% nitrogen).
The new tank has been placed and secured
to the rack where the old one is; cap is removed and regulator is reinstalled onto the new tank. |
Fri Feb 10 16:34:45 2023, Huy Tuong Cao, Infrastructure, Clean & Bake, Nitrogen gas tank ready to use
|
Cao,
Today I fixed the final bit related to the nitrogen gas tank, which is to apply sealing tape to M-NPT connector of the hose to prevent
leakage
(file: AirGunSealed.jpg)
After application of the tape, no audible leak can be heard from connection between the hose and the air gun. |
Fri Jul 26 17:25:42 2024, Jon, Infrastructure, Computers, New workstation ws4 installed in 1129
|
Today I installed the second desktop workstation in 1129. The new machine is an Intel NUC13ANHi5, with a 12-Core Intel i5-1340P CPU, 32GB DDR4 RAM, and
a 1TB SSD.
I loaded it with a fresh installation of Debian 12 and installed the LIGO CDS workstation (control room) tools. It is assigned the hostname ws4 |
Thu Jun 20 18:01:11 2024, Jon, Infrastructure, Computers, New workstation ws3 in 1129
|
I have repurposed a spare Intel NUC to serve as the first of two planned workstations in 1129. Today I set it up with a fresh installation of Debian 12.5,
assigned it the static IP address 192.168.1.15, and installed the LIGO CDS workstation packages. It is assigned the host name ws3.
Temporarily, the
mouse is borrowed from ws1 in 1119. We need to order another mouse as well as a 25-ft Ethernet cable for connecting the workstation to the 1129 switch, |
Wed Jun 26 15:33:41 2024, Jon, Infrastructure, Computers, New workstation ws3 in 1129
|
Set-up of the first CDS workstation for 1129, ws3, is complete and the machine is ready for use. The login credentials are the same as the other lab
machines.
All that now remains is to install a permanent cable tray for running the new Ethernet cables between the electronics rack and bench (they are |
Wed Aug 9 11:32:56 2023, Jon, Infrastructure, General, New power cables
|
I delivered new NEMA 5-15 (120V / 15 A) power cables to the lab for the following items:
WS2 (cleanroom) cart - 10ft cable
Electronics workbench overhead LED - 10ft cable
Both PI heater controller sets - (2)
6ft cables
I installed the new cables on the WS2 cart and the workbench myself, and left the two 6ft cables (as pictured below) for Aiden |
Tue Jun 27 15:18:26 2023, Pamella, Update, FLIR, New data collection
|
[Pamella]
Yesterday, I did a new data collection. I could get a better data in this time and I realized than I need use some
angle on the reflector for got a better shot. I need do that because the FLIR camera just is able to get the triangle shape for complete if I keep exactly
in same line for center point on the camera but for the data now I need move the refletor to go up and go down. So wasn't working very well if I keep the |
Tue Jun 13 21:33:46 2023, Pamella, Update, General, New cabinet for PPI
|
[Pamella and Dr.Richardson]
Dr. Richardson installed the new cabinet outside the room for the PPI equipments, and then I wiped all surfaces inside
and outside of the new cabinet.
Dr.Richardson and I have finished organizing the PPI within the new cabinet. Also we have new supplies of gloves,
and will likely have more supplies for other PPIs soon. |
Fri Jul 14 16:49:42 2023, Pamella, Update, FLIR, New bridge and calibration data
|
[Pamella]
Aiden 3D printed a new bridge for the heater and I installed the new bridge yesterday.
I started collecting data to plot
a calibration with the heater. I'm doing measurements with current and the thermocouple (thermometer) to compare with FLIR measurements and have a good
calibration. |
Mon May 13 14:48:27 2024, Aiden, Update, VAC, New Vacuum Chamber Design
|
I created a new model for the vacuum chamber based on the ideas from last week's meeting.
It should be noted that we can not have the zero length
reducer and the gate valve on the same arm as they both have blind tapped holes. We need to decide if we want the gate valve or not as if we do, we will
need to use the 3 inch long reducer.
Important Measurements:
From the back of the flange to the back of the RGA: 25.25 in
Height from |
Mon Jul 8 17:01:45 2024, Shane, Update, CDS, New CyMAC internal layout
|
[Jon, Shane]
Internal layout of CyMAC has been updated (labeled image attached) to accommodate the replacement of the two ribbon cables. Looking down
on the chassis from the front, and going from left to right, the new placement is as follows: BIO card, DAC adapter board, ADC adapter board, DAC card,
ADC card. NOTE: As part of ADC-DAC loopback testing, we're disconnecting from the FROSTI readout chassis and using the cables to connect directly from |
Tue May 30 14:51:27 2023, Pamella, Update, FLIR, New 3D mask - Bigger triangles shapes.
|
[Pamella]
Change the 3D mask
Started removing the old mask in the reflector.
Started cutting the new aluminum lid for the
new 3D mask and assembling in the 3D mask.
Started doing the new cable connections for the light.
Started testing the resistance
in the new cable connections. The multimeter show us 14.2 Ω.
Started attaching the mask with the light and the thermometer sensor.
|
Tue Jul 25 15:35:14 2023, Shane, Update, Electronics, More chassis moved
|
Finished basic assembly of binary input and output chassis today, and moved one to top shelf of work bench. The other is in corner of work bench (image
attached). They are delicate, so please do not move them or place anything on top of them. |
Wed May 3 19:03:47 2023, Julian,Pamella and Cao, Physics, VAC, Modify vacuum asssembly and install RGA
|
[Pamella, Julian, Cao]
Today we started re-configuring the vacuum chamber components.
Particle count
10:45 am : Starting
the particle count in the clean room.
11:13 am : Finished the particle count in the clean room.
Zone 3 :
0.3 u: 2535
0.5 u: 1413
1.0 u: 789
Zone 4 :
0.3 u: 457
0.5 |
Wed May 31 16:18:41 2023, Aiden, Summary, General, Mock FROSTI
|
Finished assembly on the Mock FROSTI so it is ready for the fit test at LIGO lab. |
Mon Jul 8 12:26:10 2024, Michael, Update, Interferometer Simulations, Minimizing Astigmatic Effects in the SRC of LIGO
|
This is the first look and analysis of the effects of astigmatism in the aLIGO optical layout which can lead to mode mismatch and therefore increased losses
into higher order modes. Specifically I am currently looking at measuring the effect of changing the radii of curvature of the SRC mirrors https://docs.google.com/presentation/d/1qhIehqyNukg4g8S2fqfQZz83yr9aB76tEa6fn2J-TrM/edit?usp=sharing |