ligo-ex ligo-ds
  Richardson Lab Experimental Log, Page 1 of 9  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
Entry  Wed Nov 20 12:59:37 2024, Tyler, Update, Electronics, RIN Update ASD_plots.pdf
I went ahead and compared the noise spectrum of the ADC to those of the photodetectors with the FROSTI on and off. As discussed last meeting, it looks like the measurements with the Red Pitaya (RP) are limited by the ADC noise floor. Another avenue to explore in this measurement could be switching to the cymac ADCs.
Entry  Wed Nov 20 12:31:24 2024, Luis, Update, VAC, Leak test RGA Scan after vacuum repairs 2024-11-20_PostBake1_ArO.png

[Luke, Luis]

After the gasket replacement performed on Monday (11/18/24) we let the vacuum pump down to UHV pressure for a couple days. Today (11/20/24) we measured the pressure to be 5.30*e^-9 with a temperature of 22C, and we performed a leak test and RGA Scan.

Here are the results:

Connection Leak rate (torr)
Reducing Cross - TP Left 4.5e-9 (lowish)
Reducing Cross - TP Right 6.0e-9 (lowish)

 

 

Entry  Tue Nov 19 17:10:34 2024, Luke , Update, VAC, Leak check image.pngIMG_5116.jpegIMG_5117.jpeg

Chamber temperature: 23C

Chamber Initial Pressure: ~1.8e-8 main, ~3.5e-8 rga

Did another leak test after monday's work to check how the seal was holding up initial leak was 5.5e-9. I then tried to tighten the bolts a bit more the leak rose to 1.9e-8 about a factor of 4 change.

I checked another flange to confirm that I was preforming the test properly. I measured the elbow to pressure sensor to be 2.2e-11 aproximatly what it was earlier in the month (1.9e-11). 

I ran another isolation test. It is still exponetial. Graph attached.

Thoughts:

I belive at this point that it is a knife edge issue when replacing the gasket I checked both flanges and the new gasket. The tp knife edge seemed perfectly fine, the gasket had very minor scratches, and the reducing cross had very small imperfections on its edge. 

We may want to try and use the liquid sealant or get annealed gaskets for 4.5"

Entry  Thu Nov 14 11:58:05 2024, Shane, Update, CDS, Turbo pump connection troubleshooting 
Attempted connection to the TV551 turbo pump through Varian/Agilent's software on spica. Successful connection established, and we are able to read out al the readings associated with the pump (status, temperature, etc) through the software, which is actually pretty extensive and well organized. Was able to stop and restart the pump with no issues. Serial communications seem to be working fine, and the current serial settings (baud rate 9600, serial type RS232) all match what the Iolan was expecting with the previous connection test. Also notable: the code used for the previous (failed) connection test is written using 'Letter protocol', which is the older of the two communications protocols supported by these kinds of pumps. This rules out the pump being too old to accept the newer communication format as the issue, since it's the older format being used anyway. Will continue trouble shooting to determine why previous connection test failed.
Entry  Thu Nov 14 10:46:20 2024, Luke , Summary, Cleanroom, Cleanroom cleaning partical_count_final.png

 

[Luke, Luis, Michael]

cleaning cleanroom and particle count

  • 8:30 am: started particle count
    • zone 3:
      • 0.3 u: 1195
      • 0.5 u: 177
      • 1.0 u: 132
    • zone 4:
      • 0.3 u: 619
      • 0.5 u: 0
      • 1.0 u: 0
  • 9:00 am: began surface check and wipedown, including softwalls
  • 9:35 am: started vacuuming the floor
  • 9:43 am: finished vacuuming the floor
  • 9:45 am: started mopping the floor
  • 9:55 am: finished mopping the floor
  • 9:56 am: started cleaning the buckets
  • 10:00 am: started mopping with IPA wipes
  • 10:05 am: finished mopping with IPA wipes
  • 10:20m: started particle count
    • zone 3:
      • 0.3 u: 2213
      • 0.5 u: 398
      • 1.0 u: 0
    • zone 4:
      • 0.3 u: 1150
      • 0.5 u: 177
      • 1.0 u: 44
Entry  Wed Nov 13 14:06:00 2024, Luke , Update, General,  

slides

Entry  Wed Nov 13 14:03:32 2024, Tyler, Update, Electronics, RIN Update IMG_0463.jpgCH0_CH1_ASDs.pdf
[Tyler]

We've added two low-pass filters in hopes of reducing any potential aliasing that may be introducing additional noise into the power spectra for the RIN measurements. It still looks like the noise levels are too high. Attached below are some recent measurements taken with the FROSTI powered on and off.

Entry  Wed Nov 6 13:48:55 2024, Liu, Update, Interferometer Simulations, QN modeling update 
Slides
Entry  Tue Nov 5 11:08:40 2024, Luis Martin, Update, VAC, ISO Test 

[Luis, Luke, Ma Michael]

The isolation test was conducted on the vacuum system. Every pump was turned off under vacuum, and pressure measurements were taken every minute for 15 minutes. The results are displayed in the sheet linked at the end of this report. The pressure of the main volume dropped very slowly.

The pressure of the RGA Volume dropped in an exponential manner. The test had to be paused at 11 minutes due to concerns about the pressure exceeding the lowest permitted level for the RGA filament.

After the ISO test was performed, we attempted to tighten the bolts of the small turbo pump on the RGA Volume. However, we noticed that the pressure had increased by nearly an order of magnitude, going from 3.27 × 10-9 Torr to 1.45 × 10-8 Torr when both volumes were separated. We conducted a leak test for that particular flange and found a concerning leak of 2.15 × 10-8 Torr, which had previously been 1.9 × 10-9 Torr. We believe the copper seal was damaged during the ISO test.

View the results sheet

Entry  Tue Nov 5 09:56:04 2024, Luis Martin, Update, Clean & Bake, MR Bake 

[Luke, Luis]

On Friday, 11/1/24, the MR was unpackaged and cleaned under the flow bench. We noticed an ink stain on one of the corners of the material. After wiping it down with IPA and Vector Alpha wipes, the stain was removed. However, the material showed some wear.

After cleaning, we placed it in the bake station and applied a stainless steel baking protocol. On Tuesday, 11/4/24, the material was removed from the furnace and packaged in a static shielding bag. The MR was wrapped in Vector Alpha wipes.

Entry  Tue Oct 29 16:37:35 2024, Tyler, Update, Electronics, Red Pitaya OS Update 

The Red Pitaya ecosystem has been upgraded to OS 2.00-35, with a key feature being greater freedom in adjusting the sampling frequency for signal analysis. Before, decimation factors could only be applied if they were a power of 2 (i.e 2,4,8,16,...) up to 65536. Now, the factors can be any power of two up to 16, and any whole number greater than 16 up to 65536. Further information can be found here.

Entry  Fri Oct 25 10:56:30 2024, Shane, Update, CDS, Timing Chassis fixed and reinstalled successful_timing.jpeg
[Ma, Shane]

We replaced the 1A breaker in the timing chassis today with a 4A one, and tested that all is working well. The chassis successfully outputted the correct signal (image attached). The real time models have also been restarted and the CyMAC diagnostics screen is showing all green flags. Timing chassis has been closed up and reinstalled in the server rack.

Entry  Wed Oct 23 12:33:54 2024, Luke , Update, , Zernike calculation update 

PowerPoint slides new

PowerPoint slides older

Entry  Wed Oct 23 12:08:36 2024, Luis Martin, Update, VAC, RGA Scan 2024-10-22_PostBake1_ArO.png

[Luke, Luis, Mary, Ma]

On 10/22/24 Luke, Ma, Mary and myself ran a RGA scan, the results are displayed below. The overall pressure of the vacuum was 2.0e-8 and the temperature readings were 26C for the RGA and 25C for the main volume.

As we can see, the vacuum is passing cleanliness standards again.

Entry  Wed Oct 23 11:48:06 2024, Luis Martin, Update, VAC, Leak Test Results 

[Luke, Luis, Mary, Ma]

On 10/22/24 Luke, Ma, Mary and myself ran a leak test, the results are displayed below. The overall pressure of the vacuum was 2.0e-8 and the temperature readings were 26C for the RGA and 25C for the main volume.

Connection Leak rate (torr)
Tee - RGA 9.4e-12 (very low)
Tee - Cal leak 1.58e-11 (very low)
Tee - ZLR (2.75"-4.5") 7.32e-12 (very low)
ZLR (2.75"-4.5") - Reducing Cross 6.9e-11   (low)
Cross - Elbow 2.34e-11 (very low)
Elbow - Pressure sensor 1.96e-11 (very low)
Cross - Turbo pump (small) 1.91e-9   (lowish)
Cross - Gate valve 1.66e-10 (very low)
Gate valve - Port 7.41e-10   (low)
Port - ZLR (6.0"-8") 2.93e-10   (low)
ZLR (6.0"-8") - Turbo pump (large) 6.15e-11 (very low)
Port - Pressure sensor 2.0e-11 (very low)
Port - Up to air valve 1.42e-11 (very low)
Port - Blank 1.27e-11 (very low)
Port - Feed through port 4.59e-12 (very low)
Lid - Curtain side 3.09e-11 (very low)
Lid - Wall side 4.26e-11 (very low)

 

 

Entry  Thu Oct 17 13:24:23 2024, Shane, Update, CDS, Timing Chassis issue identified IMG_6462.jpegIMG_6464.jpeg

[Ma, Luis, Shane]

Working theory for the timing chassis issues had been that the 1A breaker was tripping and causing the failure of the Valon 5015 and 3010 to output the timing signal correctly. We just tried bypassing the breaker, running 6 V on the benchtop power supply (set the current limit to 1.5A), with the 5010 generating the sine wave to pass to the 3010. All worked correctly, and there were no issues. Square wave outputted by the 3010 was exactly as desired (image attached) at the correct frequency, and this confirms the issue was the breaker, not the valon 5015. Ready to go ahead with ordering a new replacement breaker.

Entry  Wed Oct 16 14:13:31 2024, Liu, Update, , FROSTI with non uniform absorption scattering sources 
Slides
Entry  Wed Oct 16 13:58:59 2024, Luis Martin, Update, VAC, RGA Scan 2024-10-09_PostBake1_ArO.png

The following figure displays data acquired on 10/09, and it shows that we are no longer below the cleanliness standard. Also, the system's pressure went up to 1.9x10-8 Torr (approximately 7x10-9 Torr previously). This might be due to a leak somewhere in the system. More tests will be performed later.

Entry  Tue Oct 15 15:27:38 2024, Xuesi Ma, Update, ELOG, Timing Chassis Update 12x

I conducted separate tests on the '5015' and '3010a'. When powered individually, the '5015' outputs a signal at 33.55 MHz with an amplitude of 608 mV. It draws 1 A of current from the power source. The input signal for the '3010a' is 33.54 MHz with an amplitude of 670 mV (peak-to-peak) and a 15 mV DC offset. The output signal from channel 1 is a 65.5 kHz square wave with an amplitude of 3.28 V. The '3010a' draws 0.1 A of current.

Both the '5015' and '3010a' work fine when powered separately. However, when both are powered together, the power source behaves as if there is a short circuit. The current theory is that the switch or breaker is tripping, as it has a 1 A current rating. Since the combined current demand of both devices exceeds 1 A, this may be causing the issue.

Slides for 10/16/2024 Group Meeting

Entry  Wed Oct 9 13:52:31 2024, Tyler, Update, TCS, RIN Update 10/09/2024 RIN_plots_CH0.pdf

I tried adjusting the gain settings on the photodetectors to check if this would help improve the RIN spectra measurements. Overall, it doesn't look like it does, and if anything, looks worse. I assume this is so because as the gain is lowered, the amount of detectable signal from the FROSTI becomes smaller and smaller.

Entry  Thu Oct 3 19:35:04 2024, Shane, Update, Cleanroom, Cleanroom cleaning and particle count 
[Luke, Michael, Cynthia, Mary]

cleaning cleanroom and particle count

  • 12:25 pm: started particle count
    • zone 3:
      • 0.3 u: 4614
      • 0.5 u: 872
      • 1.0 u:83
    • zone 4:
      • 0.3 u: 2411
      • 0.5 u: 415
      • 1.0 u: 83
  • 12:48 pm: began surface check and wipedown, including softwalls
  • 1:20 pm: started vacuuming the floor
  • 1:30 pm: finished vacuuming the floor
  • 1:34 pm: started mopping the floor
  • 1:40 pm: finished mopping the floor
  • 1:40 pm: started cleaning the buckets
  • 1:42 pm: started mopping with IPA wipes
  • 1:50 pm: finished mopping with IPA wipes
  • 1:51 pm: changed sticky floor mats
  • 3:44 pm: started particle count
    • zone 3:
      • 0.3 u: 3207
      • 0.5 u: 624
      • 1.0 u: 83
    • zone 4:
      • 0.3 u: 916
      • 0.5 u: 83
      • 1.0 u: 0
Entry  Wed Oct 2 14:49:59 2024, Liu, Update, , FROSTI ETM actuation 
Proposed FROSTI ETM actuation on the HOM7 resonance. Animation
Entry  Wed Oct 2 13:38:00 2024, Cynthia, Update, Interferometer Simulations, cavity scan with averaged O4 ETM coating as plume O5plumevsCoating.pngO5CoatAvgpt5.pngO5AVgcoatingFROSTIpt5.PNG
 
Entry  Wed Oct 2 12:20:43 2024, Tyler, Update, TCS, Updated FROSTI Analysis 10/02/2024 FROSTI_Analysis_Updates.pdf
Attached below are updates on current FROSTI prototype analysis.
Entry  Wed Oct 2 12:05:42 2024, Luke , Update, , Ringheater modeling Update 

Power point slides

Entry  Wed Oct 2 10:31:46 2024, Xuesi Ma, Configuration, , Group Meeting Slides 10/2/2024 Group_Meeting_10_2.pdf

Group Meeting slides for Non-deterministic Heater Response.

Entry  Tue Oct 1 19:41:23 2024, Shane, Update, CDS, CyMAC Timing Chassis Issue IMG_5917.jpegIMG_5803.jpegIMG_5804.jpeg
[Shane, Luis] Summary of the issue we've been having with the timing chassis: when we connect only the Valon 5015 to power, the timing signal comes out of it sinusoidal as expected and the status lights are steady and all looks good. As soon as we connect the 3010 to power, the signal (both coming out of the 5015 and coming out of the 3010) go flat and the status lights of the 5015 start to flicker. We think what may be going on is that the 5015 is drawing just enough power to survive on its own, but when the current gets split to go to the 3010 as well, the 5015 takes more than it needs and becomes overpowered, and thus no longer outputs anything. We want to test further by powering them with two separate power supplies, but we need another one of the power connectors for the 3010 (the only one we have branches out from the connector to the 5015 and we don't want to cut any of the wires). Images of the inside of the chassis, along with two roughly sketched circuit diagrams (one showing the current setup, in which they're powered by the same source, and one showing a possible test set up, in which they're powered separately.
Entry  Wed Sep 25 09:06:09 2024, Luis Martin, Update, VAC, RGA Scans 24overlay.png24overlayNormalized.png
RGA Scan Comparison

The following images compare the RGA scans from 9/23/24, after the first bake with the new vacuum system, with those from 3/14/24, after bake 12 with the old system.

The first image shows a graph of the raw data and includes the calibrated leak for both curves. As we can see, our new system meets LIGO standards of cleanliness.

The second graph contains the plot of the normalized data.

Entry  Mon Sep 23 15:11:21 2024, Tyler, Update, Scripts/Programs, Effective Emissivity Analysis and RIN Update OPD_Plot.pngTemp_emiss_plot.pngrin_photodectors.pngRIN_setup.jpg

A quick update on the effective emissivity analysis for the CIT FROSTI testing:

I was able to (roughly) match the OPD data to a referenced COMSOL model, with an applied power of 12.6 W (as seen below). However, when changing the emissivity of the ETM in COMSOL, the dT profiles do not seem to change much. I am not sure as to why this is the case at the moment, and will continue to look further.

Additionally attached are the current RIN measurements of the FROSTI prototype. Shown is the PSDs of both channels, in reference to their individual backgrounds.

Entry  Mon Sep 23 15:00:41 2024, Cynthia , Update, Interferometer Simulations, corrections on assumption for O5 coating Uncoated_S1_ETM07-v2.pdf
The document recording ETM07 and ETM08 coating (T2300093) was discussed: the current plume files are not necessarily correct in a way that LIGO lab have tried to add it on uncoated ETM such as ETM07 and it does not match what the coated ETM07 would look like. the plume should be added on top of the uncoated ETM instead of assuming an ideal ETM. According to Garilynn, the imperfection on uncoated ETM matters. So far the possible ETM data used for O5, ETM 11,14,19, and 20 are all uncoated, and different ways could be used to predict the plume, including the plume data on LIGO dcc or subtract the uncoated data from the coated for O4 ETM and use that as another guessed plume.
Entry  Mon Sep 23 08:29:49 2024, Luke, Update, Interferometer Simulations, Ringheater update 20240923_Update.pptx

Ringheater Update

If the link does not work here is the file.

Entry  Mon Sep 16 15:18:59 2024, Cynthia , Update, Interferometer Simulations, a breakdown of FROSTI and thermal effects and the resulting cavity scan  ligo_update_9_16_(1).pdf
 
Entry  Mon Sep 16 14:59:51 2024, Tyler, Update, TCS, FLIR RIN Update 09/16 adc_noise_floor_photodectors.png

Below is the dark noise spectrum of the Red Pitaya, which was measured over the course of a weekend. Additionally, I have successfully measured a signal from the photodetectors with the FROSTI as the IR source, so it seems there shouldn't be any worry of these particular detectors not being feasible for the RIN measurement.

Entry  Mon Sep 16 13:51:23 2024, Luis Martin, Update, VAC, RGA Scans 2024-09-11_PostBake1_ArO.png2024-09-13_PostBake1_ArO.png2024-09-16_PostBake1_ArO.png

[Luis, Luke}

Three RGA scans were taken. The improvement in the amount of HC in the vacuum is visible across the different measurements. Images are attached.

Entry  Mon Sep 16 07:28:16 2024, Luke, Update, Interferometer Simulations, Ring heater update 20240916_Ringheater_updates.pptx
 
Entry  Mon Sep 9 21:02:37 2024, Luke, Update, VAC, Steadystate temperature of flanges 

I measured the temperature of the flanges and reconnected the RGA turning on its filament. I then turned off the PID controllers.

Here is a table that has the temperature of the different parts of the vacuum chamber.

Electronics Temperature (C)
Pressure gauge (Main volume) 81
Main turbo pump 67
RGA 53
Pressure gauge (RGA volume) 60
Cal leak 48
Mini tubo pump 46
Pirani gauge (1.33") 46
conical nipple (2.75") 82
Lid 112
Barrel lower 125
Barrel upper 122
RGA volume 125
Bottom of chamber 117
Entry  Mon Sep 9 14:27:36 2024, Pooyan, Infrastructure, Computers, Chimay backup attempt 

One ongoing work is to make all lab machines automatically backed-up on Scribe on a daily basis. The updates should be boatable and stored for some time (potentially a few weeks) on Scribe. Making whole disk images has already been tried for some of the machines with no problems. (e.g., Cymac and WorkStations)

The same thing can not be done with Chimay though, as it currently has one huge RAID-controlled volume that stores all the information (OS, home directories, and NDS-downloaded data). Creating daily full disk images of such a system is not practical. 

Here is the plan we came up with to overcome this issue:

  1. Create one full disk image of Chimay and store it on Scribe (it was already done)
  2. Move the nds-downloaded raw data temporarily to Scribe and remove it from Chimay
  3. Make another full disk image of Chimay
  4. Burn this image to a single disk and boot chimay with it
  5. Restore the rest of Chimay disks and move the NDS data back

     

On the weekend (Sat and Sun 9/7-8) I tried to execute these steps. There wasn't enough free space left on Scribe to move all the NDS data to it, so I stored part of this data temporarily on WS4. Then I also checked storage-consuming directories and, in one case, removed some non-important stored files. As there was no free space left on Scribe to execute step no. 3, I initiated storing the image on WS3. Unfortunately, a couple of different trials of the image-creation process failed as there was not enough free space on WS3 to accommodate Chiamy image as well. I was not able to reduce the image size such that it can be stored on WS3. 

 

These are the options left for us to get this work done. 

  1. Distribute the NDS files between different machines to make enough free space on Scribe for the image and then follow the previous plan
  2. Shrink the Chimay drive size, create the image and then follow the previous plan
  3. Temporarily transfer some services to Megatrone (Network gateway, Wiki, elog) and recreate chimay and its services from scratch
Entry  Mon Sep 9 12:36:45 2024, Michael, Update, Interferometer Simulations, Update on Analysis of Mode Mismatch Minimization in A# SRC_Mode_Mismatch_Update_9_9_24.pdf
I have taken a closer look at the solution curve in the mirror parameter space which I have searched, focusing on the "resilience" of specific points, with the plan to analyze how certain conditions of the interferometer change as we move along this solution curve.
Entry  Fri Sep 6 14:34:52 2024, Luke , Update, VAC, Heating tape work 

On the 5th I had tried to start baking the vacuum chamber however certain parts of the chamber were getting too hot and causing the controllers to shut off. So I turned them off so that the next day I could rearrange the temperature probes. I then on the 6th set them up so that instead of overshooting the temperature they would be a little low in places.

After being left over night the cooler parts of the vacuum chamber got much closer to the desired temperature of 120C.

Here is a table of the temperatures of the sections of the chamber. Note: After these measurements were taken the PID controllers were set to 125C.

Location   Temperature (C)
Lid (PID controller 1 emergency shutoff) 108
Barrel lower (PID controller 1) 120 
Barrel upper (PID controller 2 emergency shutoff) 118
RGA volume (PID controller 2) 120

Here is a table of temperature of the flanges that have electronics.

Electronics Temperature (C)
Pressure gauge (Main volume) 79
Main turbo pump 64
RGA 51
Pressure gauge (RGA volume) 55
Cal leak 47
Mini turbo pump 50
Pirani gauge 45 

Other temperatures of note:

The optical table was about 38C

The cleanroom was around 33C (~91F)

Entry  Tue Sep 3 18:24:17 2024, Tyler, Update, CDS, Cymac Timing Chassis Issue 
[Tyler, Jon]

The timing chassis used for the cymac has been shut off due to an unknown issue causing its supplied current to fluctuate. All real-time models will be suspended until a solution is found.

Entry  Tue Sep 3 15:52:56 2024, Luke, Update, VAC, Heater tape initilization  

[Luke, Tyler, Jon]

On the 3rd we set up the pid controllers for the heater tapes and after putting on the insulation we started heating them up. We first brought it to ~50C and let it stabilize, there was about a 6-7 degree difference between the RGA and the barrel temperature, with the barrel being higher. We then brought it to 60 then 70C it still maintained the slight difference between the RGA and barrel temperatures.

Here is a table of the temperatures of the flanges connected to electronics as I left it.

Electronics Temperature (C)
Pressure gauge (Main volume) 58
Main turbo pump 45
RGA 37
Pressure gauge (RGA volume) 39
Cal leak 40
Mini tubo pump 36
Pirani gauge 37

Notes: I removed the electronics from the pressure gauge (main volume) because while it was below the required threshold it was still quite high compared to the other flanges.

Entry  Sun Sep 1 16:17:40 2024, Luke, Update, VAC, Vacuum chamber leak checking and re-applying heating tape 

[Luke, Luis, Cinthia, Michal, Tyler]

On the 26th Cinthia, Michal, and I took off the insolation on the vacuum chamber and re-routed it to include the new RGA volume. 

The next day Luis and I finished up the last of the flanges to be attached. We attached the Pirani gauge with a conical reducing nipple to the 2.75" port on the vacuum chamber. We then preformed the Helium leak testing, both flanges were quite low the 2.75" flange had a leak of 1.68e-10 torr and the 1.33" flange of 5.5e-12 torr. The leak on the 1.33" flange was so low it was difficult to know how much of it was real and how much was just noise.

Entry  Thu Aug 29 16:39:34 2024, Luke, Update, VAC, Photos of heater tape 6x
 
Entry  Tue Aug 27 18:37:40 2024, Luke, Update, Interferometer Simulations, Ringheater model update Initial_1W.pngIncreased_rays_100W.pngIncreased_rays_more_100W.pngInitial_100W.png
Updated the model to produce a more circular deformation in the HR surface. The first three attachments are from irradiance patterns gotten from ray tracing. The last is from a pre-defined irradiance pattern.
Entry  Tue Aug 27 15:01:26 2024, Luke, Update, VAC, RGA line leak testing 

[Luke, Tyler]

On the 27th Tyler and I ran the RGA leak test again with the electron multiplier on. These were the leaks we measured. The chamber's overall pressure was at ~6e-8 torr. 

Connection Leak rate (torr)
Tee - RGA 3.92e-11 (very low)
Tee - Cal leak 4.77e-11 (very low)
Tee - ZLR (2.75"-4.5") 4.97e-11 (very low)
ZLR (2.75"-4.5") - Reducing Cross 2.45e-9   (low)
Cross - Elbow 7.36e-11 (very low)
Elbow - Pressure sensor 2.36e-11 (very low)
Cross - Turbo pump (small) 8.07e-9   (lowish)
Cross - Gate valve 4.02e-11 (very low)
Gate valve - Port 2.27e-9   (low)
Port - ZLR (6.0"-8") 1.11e-9   (low)
ZLR (6.0"-8") - Turbo pump (large) 1.00e-10 (very low)
Port - Pressure sensor 1.05e-10 (very low)
Port - Up to air valve 1.08e-11 (very low)
Port - Blank 5.58e-10 (very low)
Port - Feed though port 1.21e-11 (very low)
Lid 1.11e-11 (very low)

 

 

Entry  Mon Aug 26 14:42:04 2024, Cynthia , Update, Interferometer Simulations, current status on cavity scan with effects of FROSTI LIGO_updates_8_26.pdf
I used the code and arm cavity model used for previous O5 study on mirrors and HOM (the pdf of the study and the result can be found at https://dcc.ligo.org/LIGO-G2100878), but it seems like the result I obtained is different from the study result. Since my cavity scans codes have a large portion of it relying on this code, I will have to go over the study result and the code to make sure there is no issue with that code itself first. There are also some other updates or issued encountered when I tried to plot the mirror maps with effects of FROSTI.
Entry  Fri Aug 23 16:08:32 2024, Luke, Update, VAC, RGA line leak testing 

[Luke, Luis, Jon, Tyler]

On the 22nd Dr. Richardson showed Luis, Tyler and I how to preform a leak test with the RGA. We did the initiall test and found a few leaks two were particuarly bad highlighted in orenge below. To try and remidy this we planned on replacing the copper gaskests on the leaking flanges. We then began taking the two problem flanges off, but seven of the eight bolts holding on the turbo pump were over tightened and had seized. So after we got them off we postponed the rest of the work to the next day.

On the 23nd Luis and I reattached the badly leaking flanges with new copper gaskets. We then preformed the Helium leak test with the RGA. As seen in the table below we weren't able to majorly changed the leaks in the two flanges.

 

Connection Initial  After disassembly
Tee - RGA 3.1e-9 -> 2.4e-9 9.2e-9
Tee - Cal leak Low Low
Tee - ZLR (2.75"-4.5") Low 9.2e-9
ZLR (2.75"-4.5") - Reducing Cross 2.1e-8 -> 1.9e-8 3.6e-8 -> 9.3e-9
Cross - Elbow Low 1.2e-9
Elbow - Pressure sensor Low 2.9e-9
Cross - Turbo pump (small) 2.1e-8 -> 3.1e-8 6.9e-8 -> 2.2e-8
Cross - Gate valve Low Low
Gate valve - Port 2.4e-9 -> 2.2e-9 1.2e-9
Port - ZLR (6.0"-8") 1.1e-9 N/A
ZLR (6.0"-8") - Turbo pump (large) Low N/A
Port - Pressure sensor Low N/A
Port - Up to air valve Low N/A
Port - Blank Low N/A
Port - Feed though  port Low N/A
Lid Low N/A

 

Entry  Mon Aug 19 07:11:55 2024, Cynthia, Update, Interferometer Simulations, cavity scans with FROSTI effects  LIGO_update_8_19.pdf
 
Entry  Fri Aug 16 12:51:46 2024, Luis Martin, Update, VAC, Update on vacuum chamber status IMG_1910.HEICIMG_1911.HEICIMG_1909.HEICIMG_1912.HEIC

[Luis, Luke, Tyler]

Vacuum chamber parts were finally received and assembled. After whipping down the parts, the blank was removed from the reducing cross. Then, the zero-length reducer was attached. Lastly, we installed the T that had the argon leak and RGA. The final pump down showed signs of an improved seal since the pressure dropped quite fast. This pressure is well bellow the limit required to use the RGA, argon test leak could be performed some time next week.

Entry  Mon Aug 12 17:09:04 2024, Cynthia , Update, Interferometer Simulations, O4 vs O5 cavity scans with ITM plume guess or ETM O5_plots_and_tables.pdfO4_plots_and_tables.pdfETM12mapO5.pngScreenshot_2024-08-12_at_5.05.31_PM.png
So far the proposed solution for what to use for O5 ITM mirror for SIS simulations is either the plume guess file or using the O5 ETM mirror for ITM. I had ran a cavity scan for both of these possibilities and it seems like the results produced are fairly different. The next step is most likely moving on to adding the Frosti effects including both of the proposed possibilities, and before this, a few confirmations and verifications are needed using similar previous studies to make sure my code produce the right result.
Entry  Mon Aug 12 16:35:30 2024, Luke , Update, , Ringheater modeling Update HR_surface_deformation.pngIrradiation_pattern_input.pngHR_surface_deformation_other.png
 
Entry  Mon Jul 29 14:30:16 2024, Tyler, Update, Cleanroom, RIN Measurement Set-up RIN_FROSTI.jpg
[Tyler]

I have begun moving parts into the cleanroom for the upcoming FROSTI RIN tests that will be conducted within the next few weeks. While waiting for the rest of the equipment to arrive to perform the full-scale tests, I have additionally moved the FROSTI under the shelf above the optical table, where it will stay for the meantime. As always, please use caution when in the cleanroom. Aside from the FROSTI, the IR photodetectors that will be used for the test are delicate and costly to replace.

    Reply  Mon Aug 12 16:24:34 2024, Tyler, Update, Cleanroom, RIN Measurement Update 1 Basic_setup.jpgRP.jpg
[Tyler]

For some preliminary tests, I moved the IR photodetectors outside of the cleanroom and onto the other optical table. The basic goal was to obtain a signal from both photodetectors. To achieve this, one of the heater cartridges used for early FLIR measurements months ago was hooked up to a power supply (PS). The PS was set to supply 0.20 A with a voltage of 2.8 V; the corresponding power is thus 0.56 W. With this, I was able to measure a signal using the Red Pitaya, the device that will be used for following RIN measurements.

Quote:
[Tyler]

I have begun moving parts into the cleanroom for the upcoming FROSTI RIN tests that will be conducted within the next few weeks. While waiting for the rest of the equipment to arrive to perform the full-scale tests, I have additionally moved the FROSTI under the shelf above the optical table, where it will stay for the meantime. As always, please use caution when in the cleanroom. Aside from the FROSTI, the IR photodetectors that will be used for the test are delicate and costly to replace.

 

Entry  Tue Aug 6 13:07:07 2024, Xuejun, Update, Interferometer Simulations,  Thermal_model_image.pnggenerated_irradiance_profile.png
[Xuejun]

The width and location of the measured in-air change in temperature profile has been determined to be 0.045m and 0.137m respectively. Subsequently, a fake irradiance profile was able to be generated that best resembled what the actual irradiance profile could be using this information for testing in COMSOL. The generated irradiance profile that output the most similar change in temperature profile as the measured in-air profile has been included as well as the change in temperature profile it produced on the blackbody screen "test mass" model in COMSOL.

Entry  Sun Aug 4 09:01:01 2024, Michael, Update, Interferometer Simulations, Update on SRC Mode Mismatch Analysis SRC_Mode_Mismatch_Update_8_2_24.pdfSRC_Mode_Mismatch_Update_8-12-24.pdf
An update on my analysis to minimize mode mismatch/scattering by introducing toroidal mirrors to the SRC.
Entry  Fri Aug 2 13:50:22 2024, Shane, Update, CDS, Serial Comm. Test (Agilent Turbo Pump) pinouts.jpeg
Did a brief communication test with the agilent turbo pump today, to see if we could get serial communications up and running for it. Used a simplified python script with sockets package to establish a connection and send a simple command to query the pump's operational status. The connection was successful, and had no issues establishing. The command also sent successfully, and received a response. The response didn't make sense, though, as all the possible statuses correspond to integers 0-7, and this test returned the integer 15. Need to troubleshoot some more to figure out why it's returning nonsense values. Possible match-up issue with the way the information is being encoded on each end? At the very least, connection and command sending are both working fine, and this showed that the pin-out connections we were assuming (image attached) are correct for basic connection to work.
Entry  Thu Jul 11 21:01:37 2024, Jon, Infrastructure, General, Cable tray installed in 1129 IMG_1395.pngIMG_1396.png
Today I installed a 10' cable tray in 1129, for permanently routing Ethernet lines to the workstations. It is securely bolted to C-channels in the side wall and in the center cable tray.
    Reply  Tue Jul 30 07:42:47 2024, Jon, Infrastructure, General, Cable tray installed in 1119 cable_tray_1119.jpg
Yesterday I installed another 5' cable tray in 1119, for permanently routing Ethernet lines to the L-bench. It is securely bolted to the top of the electronics rack, on one end, and to the top of the glass-door storage cabinet, on the other. This eliminates the need for the cable ramp which previously sat behind the rack.
Entry  Thu Mar 21 16:56:42 2024, Tyler, Update, DAQ, RTD Parameter Calibration RTD_Calib-2.pngIMG_8569.jpg
[Jon,Tyler]

We noticed that the RTD temperature readings given on the Cymac were off, and traced the issue to miscalibration in the relationship between the resistance and temperature of each RTD (Callendar-Van Dusen eqn). Below is the table of values inferred from independent measurements of temperature and resistance to rectify this problem. This data was then fitted to better determine the coefficients present in the temperature-resistance relation:

       R_0 (ohm)   Alpha    Beta

RTD 0   80.8674   0.001315   4.273e-6

RTD 1   79.5704   0.001887   3.7873e-6

RTD 2   81.7334   0.002014   2.1724e-6

RTD 3   74.3060   0.003677   3.6022e-8

RTD 4   81.1350   0.001761   2.3598e-6

RTD 5   77.9610   0.002423   -7.5192e-7

RTD 6   78.7980   0.001373   6.2909e-6

RTD 7   83.8616   0.001890   3.3529e-6

    Reply  Mon Mar 25 10:55:33 2024, Tyler, Update, DAQ, RTD Parameter Calibration RTD_Calib_nobeta.png
Refitted RTD calibration, neglecting quadratic term:

       R_0 (ohm)   Alpha (1/C)

RTD 0   79.3962   0.002031

RTD 1   78.2874   0.002530

RTD 2   80.9775   0.002381

RTD 3   74.2947   0.003684

RTD 4   80.3199   0.002157

RTD 5   78.2106   0.002297

RTD 6   76.6825   0.002438

RTD 7   82.6645   0.002458


Measurements taken can be found here. An uncertainty of 1 C was assumed for temperature.

Quote:
[Jon,Tyler]

We noticed that the RTD temperature readings given on the Cymac were off, and traced the issue to miscalibration in the relationship between the resistance and temperature of each RTD (Callendar-Van Dusen eqn). Below is the table of values inferred from independent measurements of temperature and resistance to rectify this problem. This data was then fitted to better determine the coefficients present in the temperature-resistance relation:

       R_0 (ohm)   Alpha    Beta

RTD 0   80.8674   0.001315   4.273e-6

RTD 1   79.5704   0.001887   3.7873e-6

RTD 2   81.7334   0.002014   2.1724e-6

RTD 3   74.3060   0.003677   3.6022e-8

RTD 4   81.1350   0.001761   2.3598e-6

RTD 5   77.9610   0.002423   -7.5192e-7

RTD 6   78.7980   0.001373   6.2909e-6

RTD 7   83.8616   0.001890   3.3529e-6

 

       Reply  Tue Mar 26 13:51:56 2024, Tyler, Update, DAQ, RTD Parameter Calibration Screenshot_2024-03-26_at_1.23.27_PM.png

Another re-fit, but this time the quadratic coefficient (beta) is set to 1.003e-6:

       R_0 (ohm)   Alpha (1/C)

RTD 0   79.7386   0.001863

RTD 1   78.6248   0.002359

RTD 2   81.3254   0.002211

RTD 3   74.6127   0.003509

RTD 4   80.6652   0.001988

RTD 5   78.5450   0.002127

RTD 6   77.0144   0.002268

RTD 7   83.0204   0.002288

Quote:
Refitted RTD calibration, neglecting quadratic term:

       R_0 (ohm)   Alpha (1/C)

RTD 0   79.3962   0.002031

RTD 1   78.2874   0.002530

RTD 2   80.9775   0.002381

RTD 3   74.2947   0.003684

RTD 4   80.3199   0.002157

RTD 5   78.2106   0.002297

RTD 6   76.6825   0.002438

RTD 7   82.6645   0.002458


Measurements taken can be found here. An uncertainty of 1 C was assumed for temperature.

Quote:
[Jon,Tyler]

We noticed that the RTD temperature readings given on the Cymac were off, and traced the issue to miscalibration in the relationship between the resistance and temperature of each RTD (Callendar-Van Dusen eqn). Below is the table of values inferred from independent measurements of temperature and resistance to rectify this problem. This data was then fitted to better determine the coefficients present in the temperature-resistance relation:

       R_0 (ohm)   Alpha    Beta

RTD 0   80.8674   0.001315   4.273e-6

RTD 1   79.5704   0.001887   3.7873e-6

RTD 2   81.7334   0.002014   2.1724e-6

RTD 3   74.3060   0.003677   3.6022e-8

RTD 4   81.1350   0.001761   2.3598e-6

RTD 5   77.9610   0.002423   -7.5192e-7

RTD 6   78.7980   0.001373   6.2909e-6

RTD 7   83.8616   0.001890   3.3529e-6

 

 

       Reply  Mon Jul 29 13:39:16 2024, Tyler, Update, DAQ, RTD Parameter Calibration RTD_Recal_params.pngRTD_recal_plots_fin.png
[Tyler]

Using the data taken during the FROSTI testing at Caltech, I attempted to find a better calibration of the RTD sensors, given our past issues with inaccurate readings. The fit parameters, alpha and beta, are still all different from the initial values given to us by Fralock (alpha = .003, beta = 1.003e-6, R_0 was not given), but the true values will differ based on factors such as part geometry.

Quote:
Refitted RTD calibration, neglecting quadratic term:

       R_0 (ohm)   Alpha (1/C)

RTD 0   79.3962   0.002031

RTD 1   78.2874   0.002530

RTD 2   80.9775   0.002381

RTD 3   74.2947   0.003684

RTD 4   80.3199   0.002157

RTD 5   78.2106   0.002297

RTD 6   76.6825   0.002438

RTD 7   82.6645   0.002458


Measurements taken can be found here. An uncertainty of 1 C was assumed for temperature.

Quote:
[Jon,Tyler]

We noticed that the RTD temperature readings given on the Cymac were off, and traced the issue to miscalibration in the relationship between the resistance and temperature of each RTD (Callendar-Van Dusen eqn). Below is the table of values inferred from independent measurements of temperature and resistance to rectify this problem. This data was then fitted to better determine the coefficients present in the temperature-resistance relation:

       R_0 (ohm)   Alpha    Beta

RTD 0   80.8674   0.001315   4.273e-6

RTD 1   79.5704   0.001887   3.7873e-6

RTD 2   81.7334   0.002014   2.1724e-6

RTD 3   74.3060   0.003677   3.6022e-8

RTD 4   81.1350   0.001761   2.3598e-6

RTD 5   77.9610   0.002423   -7.5192e-7

RTD 6   78.7980   0.001373   6.2909e-6

RTD 7   83.8616   0.001890   3.3529e-6

 

 

Entry  Mon Jul 29 12:23:10 2024, Liu, Update, Interferometer Simulations, Update on mechanical resonances of CE BS with stiffener ring eigen_freqs_merged.pdf
Update on mechanical resonances of CE BS with stiffener ring is attached.
Entry  Mon Jul 29 12:20:56 2024, Liu, Update, Interferometer Simulations, Update on wavefront actuation with astigmatically driven RH for CE SURF_nonastig_merged.pdf
Update on wavefront actuation with astigmatically driven RH for CE is attached.
Entry  Mon Jul 29 12:18:52 2024, Liu, Update, Interferometer Simulations, Update on FROSTI O5 ETM profile optimization pdf_merged.pdf
Update on FROSTI O5 ETM profile optimization is attached.
Entry  Fri Jul 26 17:25:42 2024, Jon, Infrastructure, Computers, New workstation ws4 installed in 1129 ws4.jpg

Today I installed the second desktop workstation in 1129. The new machine is an Intel NUC13ANHi5, with a 12-Core Intel i5-1340P CPU, 32GB DDR4 RAM, and a 1TB SSD.

I loaded it with a fresh installation of Debian 12 and installed the LIGO CDS workstation (control room) tools. It is assigned the hostname ws4 and and the static IP address 192.168.1.19 on the local lab network. Like the other CDS workstations, there is just one user account accessible with the usual credentials.

The machine is fully set up and ready for use.

Entry  Mon Jul 22 18:19:34 2024, Luke, Update, VAC, Zero length reducer stuck bolts image_2024-07-22_181607501.pngimage_2024-07-22_181632965.png

Today, I borrowed a bolt extractor drill bit from the machine shop to remove some stuck bolts from the zlr. Before starting, I laid down a sheet of aluminum foil on the work table and wiped down all the tools I was going to use. I began by drilling a small pilot hole and then enlarged it with a 5/32 drill bit. However, when I attempted to use the bolt extractor, it didn't grip the bolt effectively. Our bolts were too seized, causing the extractor bit to repeatedly slip instead of gaining traction.

Entry  Tue Jul 9 18:19:50 2024, Shane, Update, CDS, ADC-DAC loopback testing and IOLAN installation iolanServerTerminal.jpegADC-DAC_Loopback_Testing.xlsxupdatedc1msc.jpeg
[Shane, Jon]

Finished ADC-DAC loopback testing today (see attached xlsx file or access directly here). All looks well with the first 8 channels, with the gain hovering just under 2. Also edited c1msc model in simulink to add channels 7-15 (the last 8 channels), and changed the rate back to 64K. See image 1 for the updated c1msc model. The last 8 channels are also looking good and show no problems, with slightly more scattering for the gain, but all values very close to 2.

We also installed the new eight-channel Perle IOLAN SDS8 terminal server today. Image attached.

NOTE: When we were installing it, we noticed an energized wire dangling from the 24V power supply. Has since been fixed and put back into place.

    Reply  Tue Jul 16 18:43:07 2024, Shane, Update, CDS, ADC-DAC loopback testing and IOLAN installation Follow-up_ADC-DAC_Loopback_Testing.xlsx
UPDATE: Follow up ADC-DAC loopback testing now complete, matching all the ADC channels to a single DAC channel, and then matching all the DAC channels to a single ADC channel (see attached xlsx file or access directly here). Also note c1msc model file has been updated to include the second set of 16 ADC channels. The newly added channels also have their own filter modules, but those are not needed for anything other than the loop-back testing and can now be deleted if we don't want to keep them.

Quote:
[Shane, Jon]

Finished ADC-DAC loopback testing today (see attached xlsx file or access directly here). All looks well with the first 8 channels, with the gain hovering just under 2. Also edited c1msc model in simulink to add channels 7-15 (the last 8 channels), and changed the rate back to 64K. See image 1 for the updated c1msc model. The last 8 channels are also looking good and show no problems, with slightly more scattering for the gain, but all values very close to 2.

We also installed the new eight-channel Perle IOLAN SDS8 terminal server today. Image attached.

NOTE: When we were installing it, we noticed an energized wire dangling from the 24V power supply. Has since been fixed and put back into place.

 

Entry  Mon Jul 15 15:52:40 2024, Michael, Update, Interferometer Simulations, aLIGO locking with varying SRC mirrors and measuring mode mismatch SRC_Astigmatism_Analysis_7_15_24.pdf
 
Entry  Mon Jul 15 15:44:52 2024, Cynthia , Update, Interferometer Simulations, performed cavity scans with thermal effects and ring heater cavity_scan_07_15.pdf
 
Entry  Mon Jul 15 14:49:06 2024, Pooyan, Update, Computers, Synology NAS server setup 

Installed a Synology NAS server (Synology RackStation RS1221) in lab room 1129, with host name “scribe” and ip “192.168.1.17”. It is mounted on the rack and each of its 8 storage bays has a 2TB SSD disk. It will be used to set up automated backups of all the lab machines (e.g., chimay, logrus, megatron).

One shared storage is set on it with SHR-2 as its RAID type. It can tolerate the failure of two disks and has 10.4TB of total capacity. 

We can use both rsync and dd to create backups of the system. A suggested backup schedule could be daily rsync backups and bi-weekly disk snapshots using dd. 

 

Entry  Mon Jul 15 14:28:32 2024, Pooyan, Update, Interferometer Simulations, aLIGO test mass surface profiles  

Created a Google Slides presentation to summarize all the mirror surface map information that we use for simulating interferometers. 

A+ expected maps are based on correspondence with G. Billingsley. The estimate for the A+ ITMs will be to take the “as polished” data and add coating non-uniformity to it. (T2000398) Neither of these are scaled for the precise thickness of the Ti:Ge coatings.

Google Slides link: https://docs.google.com/presentation/d/1ge-ciAiEdNyyTvSShYdZz2JpACFRY2W3JDpxHRqMnOQ/edit?usp=sharing

 

 

 

Entry  Mon Jul 15 13:30:49 2024, Luke , Update, VAC, Problem with 2.75" to 1.33" zero length reducer  IMG_1882.jpg
Last Friday while checking the depth of the ZLR I got one of the screws stuck. Today I tried a couple things to get it out. First I tried a few different pliers to be able to grip lower on the screw this didn't work. So I switched to the other method of drilling a small hole to see if maybe the threads would pull away from the walls of the hole a bit. This kind of worked as seen in the picture below I was able to remove most of the screw but there is a bit still stuck which I was not able to remove and I didn't want to use a larger bit for fear of damaging the tapped hole.
Entry  Mon Jul 15 09:36:44 2024, Liu, Update, Interferometer Simulations, ETM Profile Optimization for FROSTI pdf_merged.pdf

This is to optimize the FROSTI heating profile for ETM, by minimizing the residual RMSE of the HR surface deformation after the beam size weighted curvature is removed by the current RH. The parameters of the profile being explored are the location, width, and total power for the Gaussian Annulus. As shown in the attached series of plots, the optimal location is 9.9 cm, with a width of 7.7 cm, and a total FROSTI power of 12.7 W (for 1 W of Gaussian beam absorption). The residual RMSE is 1.2 nm. About 0.5% of the FROSTI power is lost at the edges of the TM.

For comparison, without FROSTI, the residual RMSE after the beam size weighted curvature removed by the current RH is 44.5 nm. When the width of the Annulus is set to be 3 cm however, the residual RMS is 3.1 nm, with much smaller FROSTI power needed at 4.7 W, and less power loss at 0.02%.

Entry  Sat Jul 13 15:09:04 2024, Luke, Update, General, Ring heater COMSL model update image_2024-07-13_150654436.pngimage_2024-07-13_150704735.pngimage_2024-07-13_150716079.pngimage_2024-07-13_150726593.png

After the feedback from last meeting and Liu's help narrowing down what I should do to improve the model. I made some changes: First with Liu's help I made the proportions of the test mass and ring heater much more reasonable and parametrized by constants. Second from Cao's paper "FROSTI Nonimaging Reflector Design" Liu showed me what I should do to define the elliptical mirrors. Third during Friday's modeling/programming meeting walked me through getting the different irradiance plots to work. 

Entry  Thu Jul 11 15:53:39 2024, Luke, Update, VAC, RGA line upgrade  image_2024-07-11_154630323.pngimage_2024-07-11_154818191.pngimage_2024-07-11_154902840.png

[ Luke, Jon ]

Started work at 11:00

As mentioned in my previous post the RGA was not clearing the table because of a tilt in the cross. So I removed the 90 deg elbow, loosened the bolt securing the Tee to the ZLR, and removed the cross from the gate valve. I then spun around the Tee on the bottom so that the cal leak would be pointing in the right direction and connected the rotating 2.75" flange of the cross to the gate valve. I then added the small turbo pump to the top of the cross. 

Then with the help of Dr. Richardson, we made some adjustments to how the Tee was oriented with respect to the cross and how the cross was with respect to the table. So that the cal leak and RGA would fit on the table. After that we made some changes to the bolting of the ZLR to reducing cross replacing the 2.00" bolts and nuts with 1.75" bolts and nut plates. We did face some difficulty with half of the 2.00" bolts which required a bit of torque to get them out. 

Finished work at 2:20 

 

Things to do:

Before we start pumping down the system again Dr. Richardson wanted two other changes to be made. To replace the 2.75" to 1.33" conical reducer with a zero length reducer. He also wants the bolts that hold the main turbo pump to be replaced with nut plates. 

I plan on starting this work on Friday (7/12) before pumping down over the weekend

Entry  Wed Jul 10 17:31:07 2024, Luke, Update, VAC, RGA line disassembly and upgrade  image_2024-07-10_172112210.pngimage_2024-07-10_172431863.pngimage_2024-07-10_172603090.pngimage_2024-07-10_172823966.png

[ Luke, Cynthia, Michael, Xuesi, Anthony ]

Started work around 12:45

We vented the chamber first and once it reached atmospheric pressure we started taking apart the RGA line.

We removed the parts in this order: Calibrated leak, RGA, Pressure gauge, 2.75" Blank on Tee, 2.75" Tee, all 1.33" Blanks on the cube, 4.5" feed through port, and finally the cube. Everything went smoothly after every part was taken off we covered the ends in Aluminum foil to maintain cleanliness. 

We then started the assembly of the new line. The parts were added in this order: Reducing cross, ZLR, Tee, Cal leak, RGA, 90 deg Elbow, and Pressure sensor.

We left off the Turbo pump as of now because we weren't able to find a 1" post not in use and we didn't want to put too much weight on the cross. We also noticed that the RGA might not fit on its probes because of a slight tilt to the cross and by extension the Tee. If this ends up being a problem we might need to remove all the parts connected to the cross so that we can reposition it so that the 2.75" rotating flange is connected to the gate valve.

Ended work around 4:00

Entry  Mon Jul 8 17:01:45 2024, Shane, Update, CDS, New CyMAC internal layout updated_cymac.jpeg
[Jon, Shane] Internal layout of CyMAC has been updated (labeled image attached) to accommodate the replacement of the two ribbon cables. Looking down on the chassis from the front, and going from left to right, the new placement is as follows: BIO card, DAC adapter board, ADC adapter board, DAC card, ADC card. NOTE: As part of ADC-DAC loopback testing, we're disconnecting from the FROSTI readout chassis and using the cables to connect directly from ADC input channels to DAC output channels . Initial testing confirmed functionalility of all 32 ADC input channels and the first 8 DAC output channels.
Entry  Mon Jul 8 12:26:10 2024, Michael, Update, Interferometer Simulations, Minimizing Astigmatic Effects in the SRC of LIGO 
This is the first look and analysis of the effects of astigmatism in the aLIGO optical layout which can lead to mode mismatch and therefore increased losses into higher order modes. Specifically I am currently looking at measuring the effect of changing the radii of curvature of the SRC mirrors https://docs.google.com/presentation/d/1qhIehqyNukg4g8S2fqfQZz83yr9aB76tEa6fn2J-TrM/edit?usp=sharing
Entry  Mon Jul 8 10:39:14 2024, Xuejun, Update, FLIR, Average Temperature Profile Average-Temperature-Profile.pdf

After taking data for each of the individual heater elements, I imported them into python and overlayed them to produce an average temperature profile. I rotated the 7 of the elements to align with element 1's profile and averaged them out. By setting the range to 28C - 33C (this gave the best visibility of the heating pattern) it gave the profile attached.

Entry  Fri Jul 5 14:23:13 2024, Liu, Update, Interferometer Simulations, Engineering drawings for straight edge heater element designs for FROSTI 
Step files and engineering drawings for the straight edge heater element designs have been created in COMSOL and SolidWorks. They are available in the group Git Repo. With those, we will initiate a discussion with the ceramics supplier for an estimate of the feasibility and benefits of the straight edge element over the curved element in terms of manufacturing cost and time.
Entry  Fri Jul 5 14:12:32 2024, Liu, Update, Interferometer Simulations, CE BS Mechanical Resonances butterfly.pngdrumhead.png
The butterfly and drumhead mechanical modes for the aLIGO BS were calculated in COMSOL. The resonant frequencies for the two acoustic modes are 2.45 kHz and 3.61 kHz, matching the results in reference for instance.

For a quick projection for the resonant frequencies going from aLIGO to CE, the height and width of the BS are increased assuming the mass is increased from 14 kg to 70 kg, while keeping the aspect ratio fixed. The resonant frequencies for the two mechanical modes as a result becomes smaller, to 1.43 kHz and 2.11 kHz respectively, risking getting in the detection band.

Next step is to implement a mechanical ring with high stiffness outside the BS barrel to combat the decrement of the resonant frequencies of the relevant mechanical modes.

Entry  Fri Jul 5 13:17:44 2024, Liu, Update, Interferometer Simulations, Four-quadrant FROSTI-like RH for astigmatic thermal actuation for CE optics 7x
In the CE corner layout design and down selection study, interferometer layouts with large incidence angles on some of the curved optics are being considered, such as the folding mirrors in the "long crab". This however generates astigmatic beams upon reflection and results in mode mismatches in coupled cavities that need to be mitigated. Astigmatic thermal actuation for the optics involved is thus essential. One way we are considering is to implement a FROSTI-like barrel RH that delivers different irradiance for the four quadrants. This post summarizes primitive results on the astigmatic thermal actuation for the HR surface by powering the heater elements from one diagonal differently compared to the other.

For this study, we looked at a simple case with an aLIGO-like test mass geometry (R=0.17m, H=0.2m) plus a barrel RH with 0.02m width at 0.03m from the AR surface with FEniCSx. The irradiance profiles are constant inside the width along the longitudinal direction, and zero outside the width. For the baseline non-astigmatic actuation with constant irradiance azimuthally. We have obtained roughly equal quadratic actuations along the x and y directions, as shown in figure. The total delivered power on the entire barrel is normalized to 1 W. The actuation on the curvature per power Delta S/Delta P in this non-astigmatic case thus is 0.835 uD/W.

For the astigmatic case however, the irradiance for the regions from one diagonal is increased by a given amount, compared to the non-astigmatic case, whereas for the other diagonal regions is decreased by the same amount (thus the total power is unchanged at 1 W). The HR deformation when the power is changed by 50%, for instance, is shown in picture, where the deformation along the x direction is larger than the y direction. The deformation in each direction however remains quadratic, with different curvature per powers for the x and y components, as shown in plot. The actuation on the curvature per power for an increasing amount of astigmatism is shown in plot. In terms of Zernike polynomials, the maximum amount of Z22 (astigmatism) for 1 W of total power is 2um while the remaining curvature content (Z20) is 6nm. This is shown in plot.

Entry  Mon Jul 1 15:19:42 2024, Cynthia , Update, Interferometer Simulations, O4 and O5 mirror cavity scans with thermal effect cavityScan_07_01.pdf
 
Entry  Mon Jul 1 11:45:45 2024, Sid, Update, Interferometer Simulations,  
Progress update: Most of last week was spent getting set up with SIS, and learning how to do basic simulations. The goal for this week is to begin reproducing the methodology from T2000338. I have begun with studying perturbations to mirror curvature and position in a simple FP cavity, but thus far have been unable to get the same results.
Entry  Fri Jun 28 18:15:16 2024, Luke, Update, VAC, Vacuum chamber  

We will be configuring the RGA line to remove the spherical cube from the system. Currently our plan for the new design is to connect a 4.5" to 2.75" Reducing Cross to the gate valve on the vacuum system. It will be orientated vertically with the turbo pump on top coming off the end will be a 90 deg elbow. On the bottom there will be a 4.5" to 2.75" Zero length reducer attached to that will be a Tee on one side the pressure sensor and the other the RGA. Connected to the elbow will be the calibrated leak. 

The only parts not readily available are the ZLR and the 2.75" gaskets

Part name Count needed Status/comment
2.75" Tee 1 In use in current RGA line
4.5" to 2.75" Reducing Cross 1 Needs to be clean and baked
4.5" to 2.75" Zero length reducer 1 To be purchased  
2.75" 90 deg elbow 1 Clean needs to be removed from another part
5/16 - 24 X 2.00" Bolts and nuts 16

8 in clean room and plenty in storage they will need to be clean and baked. Plenty of nuts in clean room.

1/4 - 28 X 1.25" Bolts and nutplates 24 12 in use in RGA line and 12 in storage that will need to be clean and baked. Sufficient nutplates in clean room
1/4 - 28 X 7/8" Bolts  12 Plenty of bolts in clean room
2.75" Copper Gasket   6 5 gaskets in clean room and none in storage. So some will need to be purchased
4.5" Copper Gasket 2 About 10 in clean room 
Entry  Fri Jun 28 10:43:13 2024, Xuejun, Update, Cleanroom, Frosti frosti.jpgchassis.jpg
[Xuejun, Tyler]

We moved Frosti into the cleanroom and debugged it to make sure everything was working. One of the DB25 pins broke off at the connector for element 1 so it needed to be recrimped. Element 6 short circuited but fixed with adjustment to the heater power pin position. We connected the power and sensor connectors to the power box and recalibrated the RTD sensors.

Entry  Thu Jun 27 13:42:02 2024, Shane, Update, Cleanroom, cleanroom 5 zone particle count measurement 24.png
Here's today's 5 zone measurement of the cleanroom. We're above the limit by a bit in zone three (all three size ranges), likely as a result of the recent work installing FROSTI, so it could probably use another focused cleaning. Everything else is below the limit.
Entry  Thu Jun 27 11:09:14 2024, Liu, Update, Scripts/Programs, Straight edge STEP files and ray loss analysis edge_CAD_8x2_step.PNGedge_CAD_step.PNGIrradiance_frontheater.pngIrradiance_profile.pdf

Drawings and CAD models of the straight-edge designs are exported, and are visualized in SOLIDWORKS. Two are attached. One is a single edge of the evenly spaced polygon design with 16 edges, and the other is the 8x2 design, with two neighboring edges grouped together to replace the original single curved heater.

For the straight edge design in COMSOL, ray power detectors were placed at the heater's front surface. The irradiance is shown in figure. The amount of light rays deposited back to the heater is small when close to the center, where it is closer to the original ring. The ray power increases as we move further away from the center toward the edges. In addition, the total power integrated at the heater's front surfaces is about 21% of the original heater's emitted power. This could account for the power efficiency difference between the straight edge design and the ring design, as shown in plot for instance.

Entry  Wed Jun 26 16:39:34 2024, Luke, Update, VAC, Vacuum chamber leak checking  image_2024-06-26_162539705.pngimage_2024-06-26_162601616.png
On Tuesday I had isolated the main volume and let it pump down over-night. Today, Wednesday, I checked it and it had only gone down by a small amount compared to when I left it on Tuesday. I then proceeded to tighten down the bolts attaching the tubo-pump to the zero-length reducer while it was under vacuum. This caused the pressure to drop down a few orders of magnitude.
Entry  Thu Jun 20 18:01:11 2024, Jon, Infrastructure, Computers, New workstation ws3 in 1129 
I have repurposed a spare Intel NUC to serve as the first of two planned workstations in 1129. Today I set it up with a fresh installation of Debian 12.5, assigned it the static IP address 192.168.1.15, and installed the LIGO CDS workstation packages. It is assigned the host name ws3. Temporarily, the mouse is borrowed from ws1 in 1119. We need to order another mouse as well as a 25-ft Ethernet cable for connecting the workstation to the 1129 switch, via the ceiling.
    Reply  Wed Jun 26 15:33:41 2024, Jon, Infrastructure, Computers, New workstation ws3 in 1129 IMG_1368.jpg

Set-up of the first CDS workstation for 1129, ws3, is complete and the machine is ready for use. The login credentials are the same as the other lab machines.

All that now remains is to install a permanent cable tray for running the new Ethernet cables between the electronics rack and bench (they are currently dangling from the suspended lights).

Quote:
I have repurposed a spare Intel NUC to serve as the first of two planned workstations in 1129. Today I set it up with a fresh installation of Debian 12.5, assigned it the static IP address 192.168.1.15, and installed the LIGO CDS workstation packages. It is assigned the host name ws3. Temporarily, the mouse is borrowed from ws1 in 1119. We need to order another mouse as well as a 25-ft Ethernet cable for connecting the workstation to the 1129 switch, via the ceiling.

Entry  Tue Jun 25 17:19:42 2024, Luke, Update, VAC, Vacuum chamber leak checking  image_2024-06-25_170036021.pngimage_2024-06-25_170057738.pngimage_2024-06-25_170120030.pngimage_2024-06-25_171238788.png
Currently our main leak is in the RGA line. We found this by closing the gate valve from the main volume to see if which side was leaking more. After identifying this we are pumping down the main volume to see how low it can go the third attachment was taken at 4:16 6/25/24. Pumping started around 3:15. We have not been able to find exactly which flange is leaking, but our guess is on the small blanks and where the cube attaches to the gate valve as seen in the second attachment. We will try a few more things and if the leak is not found/fixed we are planning on changing the configuration of the RGA line to remove the spherical cube, which we believe to be the problem. See fourth attachment for rough sketch of initial idea. We have all of the parts required and they are clean and double bagged in 1129. I have not yet made all the measurements to confirm that this design is feasible.
Entry  Tue Jun 25 12:34:18 2024, Shane, Update, Cleanroom, cleanroom cleaning and particle count 
[Luke, Shane, Xuejun, Mohak, Michael, Tyler, Cynthia]

cleaning cleanroom and particle count

  • 10:45 am: ran zero count test on particle counter
  • 11:02 am: started particle count
    • zone 3:
      • 0.3 u: 3284
      • 0.5 u: 1247
      • 1.0 u:332
    • zone 4:
      • 0.3 u: 1829
      • 0.5 u: 581
      • 1.0 u: 207
  • 11:15 am: began hepavac of rest of lab
  • 11:19 am: began surface check and wipedown, including softwalls
  • 11:32 am: finished hepavac of rest of lab
  • 11:35 am: started vacuuming the cleanroom floor
  • 11:45 am: finished vacuuming the floor
  • 11:47 am: started mopping the floor
  • 11:55 am: finished mopping the floor
  • 11:56 am: started cleaning the buckets
  • 11:57 am: started mopping with IPA wipes
  • 12:02 pm: finished mopping with IPA wipes
  • 12:03 pm: changed sticky floor mats
  • 12:04 pm: started particle count
    • zone 3:
      • 0.3 u: 3117
      • 0.5 u: 374
      • 1.0 u: 124
    • zone 4:
      • 0.3 u: 4531
      • 0.5 u: 540
      • 1.0 u: 0
Entry  Mon Jun 24 21:38:25 2024, Pooyan, Infrastructure, Computers, Computer server changes in 1119 and 1129 IMG_6889.jpgIMG_6890.jpg

[Jon, Pooyan, Tyler]

 

A few computer machine changes have been made. 

 

  • Logrus moved from 1119 to 1129. It is up and running with the same IP address as before. 
  • A new Windows machine (host name: spica, IP:192.168.1.14) is installed in the 1119 server rack. It is connected to the RGA scanner with the serial port and is specifically used for that purpose. 
    • Update: The machine was off on 6/25, although it was left on 6/24. We think that it might have been because of Windows' default setting to suspend/hibernate the machine after idleness. To resolve this, I used  "powercfg /change" command to set all the following parameters equal to zero. The machine is still running on 6/26. 

    monitor-timeout-ac
    monitor-timeout-dc
    disk-timeout-ac
    disk-timeout-dc
    standby-timeout-ac
    standby-timeout-dc
    hibernate-timeout-ac
    hibernate-timeout-dc
  • A new Debian machine (hostname: megatron, IP:192.168.1.16) is installed in the 1129 server rack. This machine is intended to be used for FEA/simulation work. A new 2TB WD Green SSD is used as its main disk drive. 

     At the moment, “controls” is the only user, and there are no apps/libraries installed on the machine.

    • Update: Jon installed LIGO cds-workstation tools and MiniConda on 6/26. 
    • Update: Pooyan and Liu set the following conda environments:
      • Env named “finesse” with Python 3.12.3 and Finesse version 3.0a24 installed. Finesse was installed via the source code. The subdirectory “/home/controls/packages” is used to store the package sourcecodes.
      • Env named “fenicsx” with the same version of Python and Finesse as the previous env, with the latest version of FEniCSx (0.8) and the test-mass-thermal-state installed.  
Entry  Mon Jun 24 14:28:51 2024, Cynthia , Update, Interferometer Simulations, SIS cavity with thermal effect ETM08thermal.png
tried to run a cavity scan with thermal deformation and ring heater for ITM04 ETM08 (aLIGO mirrors). Not sure about the accuracy of the graph as there is some commands that still need to verified.
Entry  Fri Jun 21 11:47:30 2024, Liu, Update, Scripts/Programs, COMSOL simulation on alternative straightened heater elements design 6x

In the previous post, we saw that for the heater element design with straight edges in replacement of the current eight-element ring-like design, it provides the similar Gaussian-like irradiance profiles, but with smaller power delivery efficiencies, as shown in the plot. This turned out to result in similar but less prominent thermal effects.

They only differ from the original baseline design by a source power rescaling, however, as shown in the plot, where we see the power-rescaled irradiance profiles for the straight edge designs are close to that for the ring design. The resulting temperature profiles and thermal distortions are shown in plot and plot. The thermal effects for the 16 straight-edge design with renormalized source power for instance are strikingly similar to that for the original ring design.

An alternative straightened heater element design has also been investigated with COMSOL FEA simulation. As shown in the attached, in this new design each heater element component is cut with multiple straight edges but remains connected, shown in the same colors (green and red). In the example, four straight edges are cut from each of the four heater components (4x4=16 edges in total). There is no spacing between the neighboring edges from the same element component, but the edges from different components are separated by 2mm, as can be seen in the attached. This new N-in-one straight edge design offers similar irradiance compared to that for the evenly-spaced N-sided regular polygon straight edge design with the same number of edges, as shown in the plot. It however has fewer heater components, four in this case, which makes it easier to implement in assembly and wiring, and less vulnerable to electrical and thermal shorts with their fewer heater element pins.

Entry  Wed Jun 19 18:45:14 2024, Luke, Update, , Vacuum chamber reassembly  image_2024-06-19_182556383.pngimage_2024-06-19_182631737.pngIMG_1710.jpg
[Luke, Aiden, Mohak , Tyler] On Tuesday we had the silver screws for the spherical cube shortened by a quarter of an inch so that they would fit into the gate valve. We then attached the spherical cube to the vacuum chamber. On Wednesday we finished assembling the RGA line and the main turbo pump.
Entry  Mon Jun 17 11:47:46 2024, Liu, Infrastructure, General, Temporary cooling units for the labs 1119.jpg1129.jpg
Below are the temporary cooling units installed last week in labs 1119 and 1129. They are the temp. replacement for the building AC system, which will be shut down during the Physics roof replacement.
Entry  Fri Jun 14 13:32:13 2024, Liu, Update, Scripts/Programs, COMSOL simulation on rectangular heater elements design 6x

I have been looking at the feasibility of an alternative heater element design for FROSTI that replaces the original ring-like heater elements with n rectangular elements with straight edges. They form an n-sided regular polygon that could well approximate the original annular ring if n is large enough. This eliminates curved surfaces requirement for the heater elements, which was the source of the many month production delay for the prototype parts.

This design was implemented in COMSOL, shown in the attached. From the face on view, each element has a trapezoid shape with straight edges. The edges between neighboring elements are parallel, with a space of 2 mm in between them.

The ray tracing and thermal analysis obtained from COMSOL are shown in the attached pdf.

In particular, the 2D irradiance profiles were obtained from the ray tracing (so far from the front heating surfaces only). The 1D radial profiles were integrated and shown in the attached. The power delivery efficiency for the original ring-like heater element design is integrated to be roughly 65%, for comparison. The plot also shows the radial irradiance profiles for three different straight-edge designs, which correspond to 16 edges, 18 edges, and 24 edges. We see that with the straight-edge designs, the irradiance profiles stay in a good Gaussian shape. In addition, with a larger number of edges, the power efficiency increases, but is always less than the case for the optimized ring-like design.

The thermal distortions for the TM were also obtained from COMSOL, using the irradiance profiles at the TM HR. As shown in the attached, with the straight-edge design, the effects on the thermal lens OPD and the HR surface deformation are similar to the ring design, but with less severe edge roll-off for instance.

Entry  Mon Jun 3 14:14:39 2024, Tyler, Update, FLIR, Initial CIT FROSTI Analysis  CIT_FROSTI_Analysis_Group_Meeting-2.pdf
[Tyler]

Attached below are the initial results of the CIT FROSTI testing analysis.

    Reply  Mon Jun 10 14:52:38 2024, Tyler, Update, FLIR, CIT FROSTI Analysis Update FROSTI_HR_Temperature_Difference-7.png
[Tyler]

Upon further inspection, one adjustment was made to the FROSTI profile analysis: changing the transmission value of the ZnSe viewport. It was initially assumed that the viewport possessed an AR coating, which would bring the transmission into the 90% range. Without the coating, it drops to roughly 70%. Assuming no coating, the estimated delivered power was calculated to be 11.7 W. This is consistent with the estimated power given from the Hartmann sensor analysis, thus it is believed that the viewport indeed had no coating.

Quote:
[Tyler]

Attached below are the initial results of the CIT FROSTI testing analysis.

 

Entry  Mon Jun 3 14:59:44 2024, Cynthia, Update, Interferometer Simulations, Created cavity scan with LG modes  ligo_update_6_3.pdf
 
Entry  Mon Jun 3 09:24:48 2024, Aiden, Update, VAC, Vacuum Chamber Rendering VaccumChamberAssembly__Redesign_with_tee.jpgVaccumChamberAssembly__Redesign_with_tee_top.png
Here is a new render of the vacuum chamber that includes the 2.75 tee to place the Argon leak right next to the RGA. The conical reducer under the spherical cube was also replaced with a 4.5 blank. The height from the bottom of the blank to the bottom face of the chamber is 5.45". With the chamber now on 1" standoffs, we will need a support with a height of 6.45".
Entry  Fri May 31 19:37:47 2024, Luke, Update, , Vacuum chamber Disassembly  IMG_1681.jpgIMG_1680.jpgIMG_1680.jpgIMG_1681.jpg
[Luke, Aiden, Jon, Michel, Tyler] Work done: On Tuesday (5/28) we removed the RGA line with minimal difficulty. On Wednesday (5/29) we removed the turbo pump, which had a few bolts that we needed to cut. We borrowed a dremel with ceramic blades from the machine shop to help remove some of the bolts. On Thursday we moved the vacuum chamber onto the floor to check and resecure the heating band on the bottom of the vacuum chamber. We then relocated the posts the vacuum chamber rests on closer to the end of the table and reinstalled the chamber. The post’s height was also reduced from 2in to 1in. Current state of vacuum chamber: The vacuum chamber is currently reinstalled in its new position. Some of the parts on the table will be used in the assembly of the turbo pump and RGA lines with the others being able to be moved to storage.
Entry  Thu May 16 15:23:14 2024, Shane, Update, Cleanroom, Cleanroom cleaning and particle count 
[Luis, Michael, Luke, Shane]

cleaning cleanroom and particle count

  • 1:45 pm: ran zero count test on particle counter
  • 1:50 pm: started particle count
    • zone 3:
      • 0.3 u: 2660
      • 0.5 u: 332
      • 1.0 u: 41
    • zone 4:
      • 0.3 u: 8106
      • 0.5 u: 2494
      • 1.0 u: 831
  • 2:08 pm: began surface check and wipedown, including softwalls
  • 2:22 pm: started vacuuming the floor
  • 2:39 pm: finished vacuuming the floor
  • 2:43 pm: started mopping the floor
  • 2:53 pm: finished mopping the floor
  • 2:54 pm: started cleaning the buckets
  • 2:59 pm: started mopping with IPA wipes
  • 3:06 pm: finished mopping with IPA wipes
  • 3:10 pm: changed sticky floor mats
  • 3:06 pm: started particle count
    • zone 3:
      • 0.3 u: 1496
      • 0.5 u: 83
      • 1.0 u: 0
    • zone 4:
      • 0.3 u: 789
      • 0.5 u: 83
      • 1.0 u: 41
Entry  Mon May 13 14:53:29 2024, Peter, Update, VLC Update, VLC VLC_Update.pdf
VLC Update WEEK 7 attached below
Entry  Mon May 13 14:48:27 2024, Aiden, Update, VAC, New Vacuum Chamber Design VaccumChamberAssembly__Redesign_v5.jpg
I created a new model for the vacuum chamber based on the ideas from last week's meeting.

It should be noted that we can not have the zero length reducer and the gate valve on the same arm as they both have blind tapped holes. We need to decide if we want the gate valve or not as if we do, we will need to use the 3 inch long reducer.

Important Measurements:

From the back of the flange to the back of the RGA: 25.25 in

Height from bottom of the blank to the bottom of the chamber: 2.75 in

Entry  Mon May 13 13:03:41 2024, Tyler, Update, FLIR, Readout Code Updates AcquisitionImage(Jul-18-2023_15_24).jpg.png
[Tyler]

Some changes have been made to the FLIR readout code to help improve its functionality:

  • More accurate temperature readings than before due to updates in the calculation procedure. A bug was causing one of the parameters to not update correctly; this is now fixed.
  • Saved data now stored in HDF5 files rather than CSV.
  • User can now enable automatic data storage by specifying a collection interval (in minutes). The choice of manually saving data is still present if desired.
Below is an image of the graphical interface. This is an old screenshot. Visually, there is no difference between the older and newer version. The differences come from the list above, which help the user more reliably measure and store data for later analysis.

Entry  Tue May 7 20:34:31 2024, shane, Update, CDS, frosti MEDM screen update FROSTIMEDMMay7.2024.png
[Luis, Shane] Here is the updated MEDM screen, with new orientation and updated labeling to reflect the actual positions of the heater elements. Note that indices start at T0 to be consistent with simulink model, though in the previous elog for the FROSTI layout the heater elements are labeled 1-8. Also, we finally learned how to take a screenshot on debian.
Entry  Thu May 2 22:43:36 2024, Tyler, Update, Electronics, RTD Readout Chassis Redesign IMG_9013.jpg
[Tyler, Jon]

Today the FROSTI RTD readout chassis underwent a redesign:

Instead of the original ratiometric method, which involved wiring the FROSTI RTDs in series, each element is individually powered by separate excitations. Each element additionally possesses its own reference resistor of 100 Ohm. Now, if an RTD experiences an electrical short, it should not affect the measurements of the others in sequence, as it had with the original design.

Entry  Mon Apr 22 15:06:33 2024, Cynthia , Update, Interferometer Simulations, cavity scan update LIGO_4_22.pdf
[Cynthia,Pooyan] Completed some simulations injecting 0-10th order modes. Some graphs will be used for the poster after some further titles, axis, and range adjustments.
Entry  Wed Apr 17 15:07:04 2024, Shane, Update, Cleanroom, Cleanroom cleaning and particle count 
[Mohak, Luke, Luis, Shane, Cynthia, Michael, Xuesi]

cleaning cleanroom and particle count

    NOTE: particle counter was found dead, with the charging dock unplugged. For future reference, if you need to unplug the dock, please either plug it back in when you're done, or make a note in an elog so someone else can come down and charge it.

  • 1:07 pm: ran zero count test on particle counter
  • 1:26 pm: started particle count
    • zone 3:
      • 0.3 u:1787
      • 0.5 u:457
      • 1.0 u:41
    • zone 4: We were only able to charge the particle counter a small amount before starting the cleaning, so it died again halfway through this measurement, and we didn't get results for zone 4. In interest of time, we just put it on the charger and started the cleaning.
    • 1:49 pm: began surface check and wipedown, including softwalls
    • 2:16 pm: started vacuuming the floor
    • 2:24 pm: finished vacuuming the floor
    • 2:26 pm: started mopping the floor
    • 2:32 pm: finished mopping the floor
    • 2:32 pm: started cleaning the buckets
    • 2:35 pm: started mopping with IPA wipes
    • 2:43 pm: finished mopping with IPA wipes
    • 2:43 pm: changed sticky floor mats
    • 2:45 pm: started particle count
      • zone 3:
        • 0.3 u: 1288
        • 0.5 u: 124
        • 1.0 u: 0
      • zone 4:
        • 0.3 u: 415
        • 0.5 u: 290
        • 1.0 u: 0
Entry  Mon Apr 15 15:25:10 2024, Cynthia, Update, Interferometer Simulations, progress on simulation so far LIGO_update_week3_(2).pdf
 
Entry  Mon Apr 15 11:51:03 2024, Peter, Update, VLC Update, VLC VLC_Update_April_15_2024.pdf
An update on the VLC project is attached below:
Entry  Mon Apr 8 14:57:41 2024, Cynthia, Pooyan, Update, Interferometer Simulations, performed cavity scans for O4 O5, and coupled cavity  LIGO_update_week1.pdf
 
Entry  Mon Apr 8 14:43:29 2024, Pooyan, Update, Interferometer Simulations, SIS update single and coupled cavities IFOSim_SIS__update_4_8_24.pdfScreen_Recording_2024-03-31_at_2.46.29_AM.mov
[Pooyan, Cynthia]

Attached is a brief recap PDF file. A video file showing separate HOMs plots for the cavity scan with ETM08 surface map is also attached.

The codes are available at https://git.ligo.org/uc_riverside/hom-rh/-/tree/main/SIS

Entry  Sun Apr 7 13:42:51 2024, Michael, Update, Interferometer Simulations, Update on status of gtrace project Sequential_beam_trace_crab1.pngangle_of_incidence_yaml_example.png
[Pooyan, Michael]

After meeting and discussing the current state of our work with Prof. Fulda a few weeks ago, we have decided that the best next step for the gtrace project is its integration into finesse work. Our first step towards this integration involved creating a sequential beam trace in contrast to the previous non sequential gtrace simulations. A sequential beam trace not only allows for faster runtimes of the simulation (<1 second) but also allows for more direct reading of certain beam parameters (beam size, gouy phase, and angle of incidence). The sequential model was created alongside a yaml output which provides values of parameters, now including the angle of incidence on a mirror.

Last Monday, Pooyan gave a report to the Cosmic Explorer optical design team on the current state of our project and the ultimate goal of our work. During the same meeting another group working in the optical design team presented their own work with gtrace and optical design, focusing more on optimization of parameters based on desired beam sizes at each mirror. It might be a good idea to begin attempting to bring our individual projects together to allow for collaboration and further developments.

Currently, only the crab1 layout has a sequential trace model. Pooyan is currently working on creating a finesse model for crab1 to serve as a proof of concept for how gtrace could be integrated with finesse by providing useful values such as angles of incidence.

Entry  Wed Mar 27 00:03:57 2024, Pooyan, Update, Computers, Chimay relocation to Physics 1129 Chima_front.jpgChimay_back.jpg

[Jon, Pooyan]

Moved Chimay from the server rack in Physics 1119 to a new rack in Physics 1129. It is connected to the switch in that rack and has the same ip address as before.

All services are up and running.

It appears that JupyterHub creates some processes whenever a user connects to an instance of it, but in some cases does not stop those processes after the user is not using that instance. This results in having lots of running idle processes, each using a small bit of the resources. Those processes are killed now as a result of rebooting. It might be a good idea to manually restart JupyterHub (or the whole machine) every few months to avoid this.

Entry  Sun Mar 24 11:50:37 2024, Aiden, Update, Clean &amp; Bake, Cal Tech FROSTI Parts 
Bagged the FROSTI legs and feet after the conclusion of the clean and bake. They are double bagged and sitting in the flow bench.
Entry  Sun Mar 24 11:49:27 2024, Aiden, Update, General, FROSTI RGA Scan bake13_240324_FROSTI_ArC.pngbake13_240324_FROSTI_ArO.png
Took RGA data 1 day after the conclusion of Bake 13. Bake 13 ended on Saturday March 23, the RGA data shown was taken on Sunday March 24. The scan shows that the FROSTI is very clean with no outgassing. The HC levels are at 25 e-10. The pressure in the chamber was also a 1.64 e-8 Torr.
Entry  Tue Mar 19 15:22:27 2024, Aiden, Update, Clean &amp; Bake, FROSTI Legs Clean and Bake 
[Aiden, Luke]

Cleaned and baked the Cal Tech FROSTI legs and showed Luke the procedure on how to clean parts.

Entry  Tue Mar 19 10:55:30 2024, Tyler, Update, FLIR, In-Air Optical Test FroSTI_Thermal_Profile.png
Below is an image I took using the FLIR just before leaving for the LVK meeting. The profile is roughly what we would expect (annular). Any distortions seen are likely from the screen not being completely parallel to the plane of the FroSTI (i.e. the screen slightly bends in various locations). Next step: In-vacuum test at CIT.
Entry  Fri Mar 15 16:58:55 2024, Aiden, Update, VAC, Vacuum Chamber Frosti Testing bake12_240314_Empty_ArC.pngbake12_240314_Empty_ArO.png
[Luke, Luis, Aiden] On Thursday, March 14 - Took preliminary RGA scans of the empty chamber to compare later on. Vented the chamber and placed the FROSTI into the chamber. Plugged in the DB-25 connectors into the feed through port and checked the connection to make sure there were no shorts before closing the chamber and starting the pumps again. On Friday, March 15 - The pressure in the chamber has come down to 7 e-6 torr. It seems to be coming down much slower despite the little time the chamber was left open for. This may be due to the FROSTI being out on the table for so long and a bake may be needed to bring the pressure down to near UHV.
Entry  Wed Mar 6 09:57:52 2024, Tyler, Update, TCS, FROSTI Wiring 

Upon finishing the FROSTI assembly last week, we ran into some electrical issues. An electrical short was found between two of the d-sub pins (2 and 8). It appears that the pins were somehow coming into contact with the aluminum surrounding them. This was causing the power supply to trip. The issue was seemingly fixed by adjusting the positioning of the cabling leading out of the reflector. When handling the device in the future, please make sure to keep the wiring as undisturbed as possible. The setup is rather fragile, and moving the cabling around could potentially reintroduce a short like this.

Entry  Thu Feb 29 17:16:48 2024, Shane, Update, CDS, MEDM screen for FROSTI T/P readouts IMG_6259.jpeg
Here's the latest draft of the MEDM screen for the FROSTI temp and power readouts, now with a button linking to the c1msc file display. Size/color/label are all changeable, if adjustment is needed. Checked in execute mode as well, and it's working correctly. Also noticed that the MEDM file name has been changed to FROSTI.adl, which I'm noting here for future reference. Still in medm_sandbox directory.
Entry  Mon Feb 26 21:23:27 2024, Jon, Update, TCS, FROSTI Assembly - Day 1 7x
[Jon, Tyler, Luis, Luke, Mohak, Cynthia, Michael, Aiden]

FROSTI assembly began today. After a final set of RGA scans were taken, the vacuum chamber was vented and the reflectors were removed. The chamber was then resealed and pumped down again. 

Today we completed the installation of the Macor hardware and heater elements between the two reflector halves. Tomorrow we will route, bundle, and terminate the power and sensor cables. 

    Reply  Wed Feb 28 17:49:18 2024, Tyler, Update, TCS, FROSTI Assembly - Days 2-3 IMG_0947.pngIMG_0956.pngIMG_0957.pngIMG_0959.png
[Aiden, Jon, Luis, Luke, Michael, Tyler]

FROSTI assembly was completed today. The RTD and power wires were terminated at the DB-25 connectors and the legs were put on. It is currently placed in front of the stand-in test mass (~5 cm away). The FLIR has also been moved back to it's nominal position. As of now, it appears there are some shorts within the power cabling. This will be a focus of tomorrow's work.

Quote:
[Jon, Tyler, Luis, Luke, Mohak, Cynthia, Michael, Aiden]

FROSTI assembly began today. After a final set of RGA scans were taken, the vacuum chamber was vented and the reflectors were removed. The chamber was then resealed and pumped down again. 

Today we completed the installation of the Macor hardware and heater elements between the two reflector halves. Tomorrow we will route, bundle, and terminate the power and sensor cables. 

 

Entry  Wed Jan 17 15:47:49 2024, Aiden, Update, General, Resistors for Heater Elements 
Power Res (Ohm) RTD Res (Ohm)

Heater 1= 73.6; 81.8

Heater 2= 70.4; 82.1

Heater 3= 71; 84.5

Heater 4= 71.5; 80

Heater 5= 70.5; 81.7

Heater 6= 72; 79.4

Heater 7= 69.2; 78.2

Heater 8= 71.1; 84.2

    Reply  Wed Feb 28 12:02:08 2024, Tyler, Update, General, Resistors for Heater Elements Update 
Power Res (Ohm) RTD Res (Ohm)

Heater 1= 72.8; 80.6

Heater 2= 69.5; 80.8

Heater 3= 70; 83.2

Heater 4= 70.6; 78.7

Heater 5= 69.9; 80.6

Heater 6= 71.1; 78.2

Heater 7= 68.5; 76.8

Heater 8= 70.1; 82.8

Quote:
Power Res (Ohm) RTD Res (Ohm)

Heater 1= 73.6; 81.8

Heater 2= 70.4; 82.1

Heater 3= 71; 84.5

Heater 4= 71.5; 80

Heater 5= 70.5; 81.7

Heater 6= 72; 79.4

Heater 7= 69.2; 78.2

Heater 8= 71.1; 84.2

 

Entry  Tue Feb 27 09:06:29 2024, Cynthia , Update, Interferometer Simulations, cavity scan with higher order input laser ligoPre_2_27.pdf
I performed a few cavity scan with the inputing laser with a different mode (not pure 00). For each laser I included a graph for just plotting the order with highest power (for example 1st order laser input the first plot only scanned for 1st order in that cavity), and I have also included a graph scanning for order 1-10.
Entry  Tue Feb 27 03:26:28 2024, Michael, Update, Interferometer Simulations, Reverse aLIGO Layout Created in Gtrace reverse_aligo_desmos.JPGreverse_aligo_dxf.JPG
I've created the simulation for reverse aLIGO layout in gtrace. Attached are the desmos model and the output dxf file. From here Pooyan and I plan to create a brief report of our progress to the CE optical design group.
Entry  Mon Feb 26 15:15:39 2024, Aiden, Update, General, Vacuum Chamber Baking Update 
Started Bake 12 on Wednesday Feb. 21 and turned the bake off on Saturday Feb. 24. This was a normal low temp bake with the PID controllers set to 110 degC.
Entry  Sat Feb 24 08:53:38 2024, Jon, Infrastructure, Computers, Matlab upgraded to 2023b on Chimay 
I upgraded Matlab on chimay to the latest stable release, 2023b. From some quick tests, it appears to be in working order. Let me know of any issues.
Entry  Fri Feb 23 18:03:27 2024, Tyler, Update, FLIR, Optical Test Setup in Cleanroom IMG_0941.png
[Tyler, Xuesi]

The FLIR and test mass stand-in have been transferred into the cleanroom. A software test will be run as soon as we get an ethernet cable long enough to reach into the cleanroom where the camera is set up. Once this is finished, the FLIR will be moved aside for construction of the FROSTI! When completed, the camera will be placed back into position for in-air optical testing.

Entry  Fri Feb 23 15:01:48 2024, Shane, Update, CDS, Latest draft of MEDM screen for FROSTI readouts IMG_6128.jpg23.jpg
Here's the latest draft of the MEDM screen for the FrOSTI temp and power readouts. Also, debugged the text readout boxes so they're now correctly reading out the live temperature and power values.
Entry  Thu Feb 22 21:48:16 2024, Jon, Update, VAC, Vacuum vent for RGA testing of reflector IMG_0938.pngIMG_0939.png
[Jon, Tyler, Luke, Aiden]

Summary

Following Wednesday's cleanroom cleaning [333], we proceeded to vent the vacuum chamber, remove the heater elements and their mount structure, and install the FROSTI reflectors. The reflectors are the final components to undergo RGA testing before the FROSTI prototype can be assembled. After installing the reflectors, we pumped the chamber back down and initiated a 48-hour 125 C bake.

Vacuum Vent

At ~1:00 pm, we shut off power to all eight of the FROSTI heater elements. Prior to shutoff, all were operating in vacuum at roughly 300 C. We then waited approximately 30 minutes for the elements' temperatures to fall below 50 C.

At this point, we isolated the RGA volume from the main volume by closing both gate valves, leaving the RGA volume to continue to be pumped through the bypass line. We then backfilled the main volume via the needle valve connected to one of the 2.75" ports. Once the pressures had equalized, we removed the chamber lid via our usual procedure (requiring only a small amount of flathead-screwdriver prying) and extracted the heater element assembly.

Reflector Assembly

We then removed the FROSTI reflectors from their protective packaging (for the very first time) on the cleanroom tabletop. We tested the fit of the Macor and stainless steel hardware in the reflectors' tapped holes. The Macor standoffs and bolts appear to fit perfectly. However, the 1/4-20 tapped holes for joining the two reflector halves are too shallow by ~1/4". As a temporary fix, we used some on-hand stainless steel washers (which had already been cleaned and baked) to securely fasten the two halves together. In the final assembly we will replace these with slightly shorter 1/4-20 vented bolts.

Pumpdown and Bake

The two fastened reflector halves were placed inside the chamber, sitting on top of the two mounting legs (see attached photos). We then reinstalled the lid. In order to rough the main volume, we isolated the RGA volume from the pumpline (by closing the bypass line valve), shut down the pumps, and then backfilled the pumpline via the manual vent valve on the turbo pump.

Once the pressures had equalized, we opened the 6" gate valve separating the pumpline from the main volume and powered on the roughing pump. Once the main volume pressure fell below 0.5 Torr, we powered on the turbo pump as well. The main volume pressure reached 5e-6 Torr within ~30 minutes, consistent with previous experience, and was continuing to slowly fall.

Lastly, we initiated a 125 C bake-out of the entire system following our usual procedure. We plan to run this bake for 48 hours (i.e., through the end of the day Friday).

Entry  Wed Feb 21 23:15:07 2024, Michael, Update, Interferometer Simulations, Long Shoelaces 1 Layout Created in Gtrace and Fixed Ghosting in Beamsplitter long_shoelaces1_desmos.JPGAR_side_with_reflection.PNGAR_side_without_reflection.PNG
I have created the long shoelaces 1 layout for cosmic explorer using gtrace, a slight modification from the shoelaces 1 layout design. I also modified the simulation code slightly to remove ghosting effects in the beamsplitter. Originally the python code specified that the HR and AR sides of the beamsplitter both have the same transmission/reflection. I modified this to the ideal case of: Refl_AR = 0, Trans_AR = 1. I have attached two images below to show the before and after effect of this modification.
Entry  Wed Feb 21 11:58:30 2024, Shane, Update, Cleanroom, cleanroom cleaning and particle count 
[Luke, Shane, Tyler]

cleaning cleanroom and particle count

  • 11:50 am: ran zero count test on particle counter
  • 11:55 am: started particle count
    • zone 3:
      • 0.3 u: 1787
      • 0.5 u: 581
      • 1.0 u: 166
    • zone 4:
      • 0.3 u: 623
      • 0.5 u: 290
      • 1.0 u: 124
  • 12:17 pm: began surface check and wipedown, including softwalls
  • 12:25 pm: started vacuuming the floor
  • 12:36 pm: finished vacuuming the floor
  • 12:44 pm: started mopping the floor
  • 12:57 pm: finished mopping the floor
  • 12:58 pm: started cleaning the buckets
  • 12:59 pm: started mopping with IPA wipes
  • 1:05 pm: finished mopping with IPA wipes
  • 1:06 pm: changed sticky floor mats
  • 1:08 pm: started particle count
    • zone 3:
      • 0.3 u: 1621
      • 0.5 u: 581
      • 1.0 u: 332
    • zone 4:
      • 0.3 u: 1080
      • 0.5 u: 457
      • 1.0 u: 249
Entry  Tue Feb 20 18:08:24 2024, Aiden, Update, General, Degassing the RGA bake11_240220_Elements_postdegas_ArO.pngbake11_240220_Elements_predegas_ArO.png
I took an RGA measurement before and after degassing the RGA. Both data was taken with the Argon open. The pressure before taking data was 2.39 e-8 torr in the main volume. Note that the main chamber was fully valved off for the degas and the main chamber pressure quickly rose to e-6 torr. Further investigation of this rise should be done as this might be the main culprit for the leaking.
Entry  Tue Feb 20 11:31:49 2024, Tyler, Update, Cleanroom, Garment Cabinet Door Replacement image_67190529.JPGimage_67177473.JPG
[Luis, Luke, Pooyan, Tyler]

The replacement door for the HEPA garment cabinet arrived last week, and was installed on Thursday. However, it looks like there's a small gap between the door and where the hinge is attached to the cabinet frame. No screws were provided with the replacement door. If we want to perform any adjustments, we have to be very careful; the screws break very easily.

Entry  Mon Jan 15 22:29:34 2024, Jon, Infrastructure, General, Cabinet installation & lab clean-up completed 1129.png1119.png

[Jon, Tyler, Aiden, Shane, Pooyan, Michael, Cynthia, Luke]

On Wednesday, we completed long list of work towards making the new lab (1129) fully operational and enabling the next phase of FROSTI testing. 

Cabinet Installation

Three new VWR cabinets with sliding glass doors were installed in 1129. Each unit measures 48" (W) x 22" (D) x 84" (H) and sits along the back wall (see attachment 1). The 350-lb. cabinets were laid in place by Facilities on Monday and permanentized on Wednesday. Work included:

  • Earthquake anchoring to the masonry wall
  • Sliding glass doors leveled
  • Shelving installed
  • Wiping down of interior and exterior surfaces with IPA wipes

Server Rack Installation

A new Tripp Lite 42U open-frame rack was laid in place in 1129 and anchored to the floor (see attachment 1). This rack will house all of our general-purpose and simulation computers, which will be relocated from the 1119 rack at a later time.

Lab Clean-Up

Following installation of the new cabinets and rack, we proceeded to organize and clean both labs. Work included:

  • Moved parts and equipment into permanent storage in 1129 cabinets
  • Wiped down surfaces in 1119 and 1129 with polypropylene IPA wipes
  • HEPA-vacuumed floors of 1119 and 1129
  • Mopped floor in 1119 with Liquinox solution
  • Installed new sticky mats in 1119 and 1129
  • Regular cleanroom cleaning and particle counts (see 302)
  • Positioned new stainless steel gowning bench outside the cleanroom (see attachment 2)

At this point, the only piece of lab equipment still to be delivered is a HEPA garment cabinet for reusing our (semi-disposable) bunny suits. It is schedule to arrive in mid-February and will sit outside the cleanroom in 1119, in the former location of the HEPA flow bench.

    Reply  Tue Feb 20 08:01:30 2024, Jon, Infrastructure, General, Power and network equipment installed in 1129 rack IMG_0924.jpegIMG_0925.jpegIMG_0921.jpegIMG_0922.jpeg
[Jon, Tyler, Pooyan, Luis, Luke, Peter]

On Thursday we installed the power conditioning/distribution equipment and networking equipment in the new 1129 rack. The hardware is identical to the setup in the 1119 rack and includes:

  • Tripp Lite SU5KRT3UTF - 208V, 5kVA on-line UPS with 120V transformer
  • CyberPower PDU20M2F12R - metered power distribution unit, (14) NEMA 5-20R
  • Ubiquiti USW-Pro-48 - 48 port 10Gbps network switch

The UPS is connected to a 208V NEMA 6-30R outlet in the overhead cable tray, which is on the building's "standby" (backup power) circuit. An 8-ft L6-30 extension cord has been ordered to permanently run the power cable through the cable tray.

The network switch will be connected to a Cat6 cable that was recently run by ITS from the 1119 rack, allowing the lab's LAN to be extended into 1129. This Ethernet link remains to be tested.

Quote:

Server Rack Installation

A new Tripp Lite 42U open-frame rack was laid in place in 1129 and anchored to the floor (see attachment 1). This rack will house all of our general-purpose and simulation computers, which will be relocated from the 1119 rack at a later time.

Entry  Mon Feb 19 14:40:21 2024, Shane, Update, CDS, MEDM screen for FROSTI temp readouts IMG_6094.jpegIMG_6092.jpeg
Here's the latest draft of the MEDM screen for the FROSTI heating elements' temperature readouts. Note that the MEDM screen isn't actually this grainy, this just happens to be a photo of the lab monitor's screen off a phone.
Entry  Mon Feb 19 14:17:50 2024, Aiden, Update, VAC, Heater Element RGA Scan bake11_240219_Elements_ArO.png
Three days after the completion of Bake 11, the Heater elements RGA scan looks much cleaner. The HC level is back down to 33 e-10 torrl/s with the pressure at 2.13 e-8 torr. I could not take a= scan with the Argon closed as it was left open during the bake and not closed since then.
Entry  Fri Feb 16 18:37:28 2024, Jon, Update, VAC, Bake ended 6:23 pm 

I ended the bake of the UHV system (that began on Monday) at 6:23 pm today by switching OFF both PID controllers. The heaters elements were run at max power (24 V DC / 200 mA per element) during this bake, and I left them powered at the same level.

At the time, the instrument readings were as follows:

  • Left high-limit controller: 138 C
  • Right high-limit controller: 128 C
  • Left PID controller: 100 C
  • Right PID controller: 100 C
  • Main volume pressure: 8.17e-7 Torr
  • RGA volume pressure: 4.63e-7 Torr
Entry  Tue Feb 13 13:02:41 2024, Pooyan, Update, Interferometer Simulations, Cacity sacn of Fabry-Perot  IFOSim_update_2_13_24.pdf
Created a simple model of Fabry-Perot cavity in SIS, and did a cavity scan. Total power in the cavity, 00 mode, and HOMs is measured.
Entry  Tue Feb 13 12:34:04 2024, Aiden, Update, VAC, VAC Heating System Update bake10_240118_Elements_ArO.png
Here is an overlay with for all the heating steps done with the heater elements.
Entry  Tue Feb 13 12:26:23 2024, Tyler, Update, Interferometer Simulations, BS Code Update thickness1.pdfbs_opd_homloss_h6cm_w2cm.pdf

I reproduced Cao's CE beamsplitter code (see below for example plots). I received the current info on the beamsplitter parameters for A+ and A# from GariLynn also. The next steps are to perform a similar power loss analysis on the anticipated A# beamsplitter.

Entry  Tue Feb 13 11:54:45 2024, Tyler, Configuration, FLIR, In-Air Optical Test Configuration In-air_optical_test_sketch.png

Below is the proposed schematic for FROSTI optical testing, chosen so enough space is allotted for prototype assembly.

Steps to be taken include:

  1. Reconstruct FLIR staging apparatus
  2. Move test mass stand-in to cleanroom
  3. Mark FLIR camera position on cleanroom optical table at correct distance
  4. Run ethernet cable into cleanroom
  5. Move FLIR aside to allow for more assembly space
  6. Upon assembly completion, reposition FLIR onto optical table again

Tentative plan is to begin setup early next week.

Entry  Tue Feb 13 04:05:32 2024, Michael, Update, Interferometer Simulations, Shoelaces 1 Layout Simulated in GTrace shoelaces1_dxf.JPGshoelaces1_desmos.JPG
I've worked on and have completed a first simulation of Cosmic Explorer's Shoelaces 1 layout. This is based off of Pooyan's original work with Gtrace much like the Long Crab 1 layout I worked on last week. This layout will allow me to quickly created the alternate shoelaces layouts. I've included an image of the dxf, and a desmos model for reference.
Entry  Tue Feb 13 01:26:30 2024, Peter, Update, Interferometer Simulations, CARM Power Simulations Scenario_3_CARM.pdfScenario_3_CARM_Gouy.pdf
Cao's simulations of the circulating power and gouy phase through a single arm cavity of the interferometer have been reproduced. Images of the plots can be shown in the pdfs attached. There are approx. 400 lines in this code (scenario_3_carm) that produces these plots. This code also calls on a separate code source file (thermal_models) that defines many of the functions used in this main simulation. The thermal_models file consists of over 1000 lines. More work needs to be done to fully understand and document the scripts.
Entry  Mon Feb 12 17:35:47 2024, Aiden, Update, VAC, Heater Element RGA Scan bake10_240212_Elements_ArO.pngbake10_240212_Elements_ArC.pngbake10_240212_Elements_300C_ArC.png
Took more RGA data before and after increasing the heater elements to 300 degC and before heating them up.

Started Bake 11 as well to hopefully prevent any hydrocarbons from getting captured by the room temperature walls of the chamber. The PID controllers were set to 100C.
Entry  Thu Feb 8 17:37:48 2024, Aiden, Update, VAC, Heater Element RGA Scan bake10_240208_Elements_ArO.pngbake10_240208_Elements_ArC.png
Took more RGA data now that the heaters are powered by 18V. The pressure of the system during the data taking was 3.8 e-8 torr. The RGA scans seem to have gotten worse as well with this power increase.
Entry  Wed Feb 7 12:43:22 2024, shane, Update, Cleanroom, cleanroom particle counts (full 5 zone measurement) 24.png
Here's today's full 5 zone measurement of the cleanroom. Everything is back under the requirement.
Entry  Tue Feb 6 22:40:25 2024, Michael, Update, Scripts/Programs, Long Crab 1 Design Created In Gtrace Long_Crab1.pnglong_crab_1_desmos.PNG
Worked on and completed the python code for the simulation of the Long Crab 1 layout for Cosmic Explorer basing off of Pooyan's original work with the Crab 1 layout. From here I'll look into creating the shoelaces layouts.
Entry  Mon Feb 5 14:17:52 2024, Aiden, Update, VAC, Heater Element RGA Scan bake10_240205_Elements_ArO.pngbake10_240205_Elements_ArC.png
Here are the new RGA scans for the powered Heater elements. The pressure at the time of taking data was 2.88 e-8 torr. The HC levels are at 40 e-10 torrl/s which is not bad but still higher than the lowest we have recorded.
Entry  Fri Feb 2 19:18:24 2024, shane, Update, Cleanroom, cleanroom cleaning and particle count 
[Aiden, Shane, Luis, Luke]

cleaning cleanroom and particle count

  • 5:10 pm: ran zero count test on particle counter
  • 5:14 pm: started particle count

    NOTE: initial counts are significantly above allowed limit. ~10 times larger than ISO class 5 standard in the smallest size range. Realized partway through ceiling tile changes that the power/lights for some of the hepa fans in the ceiling frame had been turned off. May explain this high number. Have since turned fans back back on.

    • zone 3:
      • 0.3 u: 109208
      • 0.5 u: 16337
      • 1.0 u: 581
    • zone 4:
      • 0.3 u: 51340
      • 0.5 u: 9228
      • 1.0 u: 581
  • 5:33 pm: started replacing ceiling tiles
  • 6:25 pm: began surface check and wipedown, including softwalls
  • 6:33 pm: started vacuuming the floor
  • 6:45 pm: finished vacuuming the floor
  • 6:45 pm: started mopping the floor
  • 6:50 pm: finished mopping the floor
  • 6:52 pm: started cleaning the buckets
  • 6:53 pm: started mopping with IPA wipes
  • 6:58 pm: finished mopping with IPA wipes
  • 6:59 pm: changed sticky floor mats
  • 7:00 pm: started particle count
    • zone 3:
      • 0.3 u: 5404
      • 0.5 u: 1413
      • 1.0 u: 41
    • zone 4:
      • 0.3 u: 1704
      • 0.5 u: 332
      • 1.0 u: 166
Entry  Fri Feb 2 19:08:20 2024, Aiden, Update, VAC, 1st Hot Element RGA Scan bake10_240202_Elements_ArC.pngbake10_240202_Elements_ArO.png
Here are the measurements for the RGA scan of the elements while on at around 160C. The pressure of the chamber during the test was 4.12 e-8 torr.
Entry  Fri Feb 2 16:56:56 2024, Jon, Update, CDS, RTS model implemented for FROSTI RTD readouts sitemap_screen.png

Summary

Today I finished implementing an RTS model to read out the integrated FROSTI RTDs (temperature sensors) via the CyMAC. The model is named "MSC" and is located at cymac:/opt/rtcds/usercode/models/c1msc.mdl. We successfully tested it with the heater elements operating in vacuum at low power (12 VDC), finding them to reach an average steady-state temperature of 160 C.

From the cymac host, the MEDM control screen can be accessed with the terminal command "sitemap" (from any directory).

Measurement Technique

Each FROSTI heater element [299] contains an internal two-wire RTD placed near the front emitting surface, which enables the temperature of the blackbody emitter to be directly monitored. From the measured temperature and the emissivity of the uncoated aluminum nitride surface (known to be ~1 in the IR), the radiated source-plane power can also be estimated.

The resistance of each RTD is measured via a ratiometric technique. The RTDs are powered in series with a 1 kΩ reference resistor located inside the readout chassis [305], whose temperature is not changing. The signal is obtained by taking the ratio of the voltage difference across each individual RTD to the voltage difference across the reference resisitor. The advantage of this technique is that the ratio of  the voltage differences is insensitive to changes in the current through the resistors (since they are all in series; see [271] for wiring diagram).

Implementation Detail

The signal flow is shown in Attachment 1. The eight RTD signals enter through ADC channels 0-7, along with the reference resistor signal on channel 8. The first set of filter modules apply a calibration gain to convert the signals from raw ADU counts to units of input-referred voltage. The ratio of each RTD signal to the reference resistor signal is then taken. The second set of filter modules multiply the voltage-difference ratios by the resistance of the reference resistor, 1 kΩ ± 0.01%, to obtain the RTD resistances in physical units of ohms.

Finally, a freeform math module is used to invert the quadratic relation between each RTD's resistance and temperature. The final signals passed to the third set of filter modules are the RTD temperatures in physical units of degrees C. The temperatures of the tungsten RTDs are estimated assuming TCR coefficients of A=0.0030 C-1 (±10%) and B=1.003E-6 C-2, which were provided by the manufacturer.

One DAC channel is used to provide the excitation voltage for the RTD measurement, which is visible on the far right of the control screen. At its maximum output voltage of +10 V, the DAC can drive a maximum current of 10 mA.

Entry  Wed Jan 31 14:37:26 2024, Shane, Summary, CDS, path directions for CyMAC model and parts library 
Path to cds parts library in Matlab simulink: /usr/share/advligorts/src/src/epics/simLink. File name CDS_PARTS.mdl Path to user models: /opt/rtcds/usercode/models, using file name c1msc.mdl
Entry  Tue Jan 23 12:17:41 2024, Tyler, Update, Electronics, RTD Chassis rtd_updated_circuitry.jpg

After updating the wiring in the RTD Chassis, a signal is now seen at each ADC input. However, there seems to be a discrepancy between the voltages I measured out with the multimeter (see below). Next steps include:

  • Finish final debugging
  • Calibrate ADC inputs with known voltage source (likely to use DAC).

Voltage Readings:

RTD 1: 0.576 V

RTD 2: 0.578 V

RTD 3: 0.598 V

RTD 4: 0.563 V

RTD 5: 0.477 V

RTD 6: 0.463 V

RTD 7: 0.456 V

RTD 8: 0.491 V

Reference Resistor: 5.463 V

Total Voltage: 9.665 V

    Reply  Tue Jan 30 11:36:19 2024, Tyler, Update, Electronics, RTD Chassis 

Quote:

After updating the wiring in the RTD Chassis, a signal is now seen at each ADC input. However, there seems to be a discrepancy between the voltages I measured out with the multimeter (see below). Next steps include:

  • Finish final debugging
  • Calibrate ADC inputs with known voltage source (likely to use DAC).

Voltage Readings:

RTD 1: 0.576 V

RTD 2: 0.578 V

RTD 3: 0.598 V

RTD 4: 0.563 V

RTD 5: 0.477 V

RTD 6: 0.463 V

RTD 7: 0.456 V

RTD 8: 0.491 V

Reference Resistor: 5.463 V

Total Voltage: 9.665 V

 

After further modification of the RTD readout chassis (i.e. adding resistors, placing reference resistor in front of RTDs), here are the following direct measurements:

RTD 1: 0.484 V

RTD 2: 0.486 V

RTD 3: 0.503 V

RTD 4: 0.474 V

RTD 5: 0.495 V

RTD 6: 0.483 V

RTD 7: 0.476 V

RTD 8: 0.510 V

Reference: 5.847 V


Here are the Cymac signal readings:

RTD 1: 74

RTD 2: 67

RTD 3: 73

RTD 4: 45

RTD 5: 82

RTD 6: 75

RTD 7: 70

RTD 8: 71

Reference: 884


The one (possible) discrepancy here is the readout for RTD 4 via Cymac, since it's signal reading is ~30 counts lower than the others. I do not believe this is a wiring issue due to the direct measurements taken.

Entry  Thu Jan 18 18:06:49 2024, shane, Update, Cleanroom, cleanroom 5 zone particle count measurement 24.png
Here's today's full five zone measurement of the cleanroom
Entry  Thu Jan 18 15:13:37 2024, Aiden, Update, VAC, VAC Heating System Update bake10_240118_Elements_ArO.pngJanuary_18_Ar_Open_Elements_Analyzed.png
[Aiden]

Took more data today and the chamber and elements are showing an even lower HC level than we have gotten before. It is safe to say that the elements are not contaminated and out gassing HC into the chamber.

Entry  Tue Jan 16 16:11:41 2024, Aiden, Update, VAC,  bake10_240116_Elements_ArO.pngbake10_240116_Elements_ArC.png
[Aiden,Luis]

Below is the data for the most recent bake. I believe the chamber is cleaner than it is actually showing as the RGA data was still getting lower while the data was being taken. I will take the data again tomorrow just in case. Still, the data shows that the chamber is basically as clean as it was before bake 10 and this means further power testing can proceed.

Helium leak tested the chamber again today to check if the sealant changed anything. The two primary target flanges from last time have improved significantly with the flange from the RGA on the cross now being below 2e-14. While the turbo pump flange was leaking at a rate of 4e-13. Much better than what it has been before.

Entry  Mon Nov 20 10:10:50 2023, Tyler, Configuration, Electronics, RTD Logic/Schematic Diagrams FIN_RTD_circuit.pngSample_Circuit_Schematic.png

Below are a basic diagram of what the RTD measurement circuit logically looks like and an example schematic of the actual wiring. The schematic wiring will be placed internally into a chassis, connected to the RTDs via DB25 cable.

Note: The DB25 Breakout Board connector is Female, not Male.
    Reply  Fri Dec 29 16:02:27 2023, Jon, Configuration, Electronics, RTD Readout Chassis front.jpegrear.jpegoverhead.jpeg

The custom front and rear panels for the RTD readout chassis arrived last Friday. I installed them in the chassis frame to check their fit. They fit very well, so all that now remains is to complete the internal wiring and test the connections.

The chassis panel designs are archived to LIGO-D2300452 and LIGO-D2300453.

Quote:

Below are a basic diagram of what the RTD measurement circuit logically looks like and an example schematic of the actual wiring. The schematic wiring will be placed internally into a chassis, connected to the RTDs via DB25 cable.

Note: The DB25 Breakout Board connector is Female, not Male.
       Reply  Tue Jan 9 12:08:59 2024, Tyler, Configuration, Electronics, RTD Readout Chassis Update IMG_8105.jpg

Below is the current state of the RTD readout chassis wiring. Initial continuity tests seem good, will run through one more time to confirm.

Quote:

The custom front and rear panels for the RTD readout chassis arrived last Friday. I installed them in the chassis frame to check their fit. They fit very well, so all that now remains is to complete the internal wiring and test the connections.

The chassis panel designs are archived to LIGO-D2300452 and LIGO-D2300453.

Quote:

Below are a basic diagram of what the RTD measurement circuit logically looks like and an example schematic of the actual wiring. The schematic wiring will be placed internally into a chassis, connected to the RTDs via DB25 cable.

Note: The DB25 Breakout Board connector is Female, not Male.

 

          Reply  Tue Jan 16 12:20:21 2024, Tyler, Configuration, Electronics, RTD Readout Chassis Update 2 IMG_8146.jpgIMG_8147.jpg

I performed another continuity test on the RTD chassis wiring, and everything seems to be set up correctly. The chassis should be ready for installation.

Quote:

Below is the current state of the RTD readout chassis wiring. Initial continuity tests seem good, will run through one more time to confirm.

Quote:

The custom front and rear panels for the RTD readout chassis arrived last Friday. I installed them in the chassis frame to check their fit. They fit very well, so all that now remains is to complete the internal wiring and test the connections.

The chassis panel designs are archived to LIGO-D2300452 and LIGO-D2300453.

Quote:

Below are a basic diagram of what the RTD measurement circuit logically looks like and an example schematic of the actual wiring. The schematic wiring will be placed internally into a chassis, connected to the RTDs via DB25 cable.

Note: The DB25 Breakout Board connector is Female, not Male.

 

 

Entry  Tue Jan 16 10:01:21 2024, Peter, Update, VLC Update, VLC Faraday Isolator and Mode Matching VLC_Mode_Matching_Design_-_Remastered.pdf
Attached is a PDF of my weekly updates.
Entry  Wed Jan 10 15:27:18 2024, Shane, Update, Cleanroom, cleanroom cleaning and particle count 
[Aiden, Shane]

cleaning cleanroom and particle count

  • 2:03 pm: changed sticky floor mats
  • 2:05 pm: started particle count
    • zone 3:
      • 0.3 u: 4863
      • 0.5 u: 1205
      • 1.0 u: 872
    • zone 4:
      • 0.3 u: 1953
      • 0.5 u: 789
      • 1.0 u: 457
  • 2:35 pm: began surface check and wipedown, including softwalls and ceiling tiles
  • 2:45 pm: started vacuuming the floor
  • 2:56 pm: finished vacuuming the floor
  • 2:57 pm: started mopping the floor
  • 3:01 pm: finished mopping the floor
  • 3:02 pm: started cleaning the buckets
  • 3:05 pm: started mopping with IPA wipes
  • 3:08 pm: finished mopping with IPA wipes
  • 3:09 pm: started particle count
    • zone 3:
      • 0.3 u: 5528
      • 0.5 u: 2203
      • 1.0 u: 1662
    • zone 4:
      • 0.3 u: 1080
      • 0.5 u: 415
      • 1.0 u: 332
Entry  Tue Jan 9 16:35:09 2024, Aiden, Update, VAC, VAC System Leak and Heating 
[Luis, Luke, Aiden]

Leak tested each flange and weld and only found two flanges to have noticeable leaks with the electron multiplier on. These were the turbo pump flange and the RGA flange that connects to the cross. The RGA one is rather new as it has not had a measurable leak before and it was around 2 e-8. We then applied the new sealant to these two flanges as directed by the instructions on the packaging.

Then after waiting a few minutes for the sealant to dry we started the bake. We got the PID controllers set to 120 after many steps and we checked the temperature of the flanges throughout this increase. The flanges never reached 70C with the electronics still left on it. The RGA was left on as well.

Entry  Mon Jan 8 20:24:53 2024, Aiden, Update, General,  IMG_4888.jpgIMG_4886.jpgIMG_4887.jpg
[Jon, Aiden]

Installed the heater elements into their fixture and prepped the cables by twisting the wires into pairs. We also installed the pins onto the wires and placed them into the peek DB 25 connector. The installation tool we had did not fit the pin size we had so the pins needed to be installed by hand by opening the connector and holding them in place. In the future we will need to make sure we twist the wires together, group them, and then splice them all to the same size for easier installation. We then grouped all the twisted pairs into a bundle and zipped them together. On the left with two peek zip ties is the power and on the right is the RTD with one peek zip tie. This orientation remains true when looking at the feed through flange from the outside with the power port on closest to the wall.

We also installed the heater elements numbered 1-8 starting from the left in image 3. These elements have numbers as resistance data was taken before as to identify the heaters after they are in the chamber. After installing the DB 25 connectors we tested that the pins were in the right orientation by using a volt meter and testing the resistance where the cable runs into the the actual power supply. It seems that all the pins were properly installed and the resistance values all match with each one gaining about 2 Ohms from the cable itself.

Then the pump down was started. The pump was very slow and we suspected a leak but after changing the o-ring pump down was not any faster and we decided to leave it over break as it seemed to just be water outgassing from the aluminum. The chamber is now able to be RGA scanned and leak tested before the next bake as it is low enough pressure.

Entry  Sun Dec 17 21:04:15 2023, Jon, Infrastructure, Clean &amp; Bake, Clean and bake lab migrated to 1129 IMG_0781.pngIMG_0782.png

[Jon, Tyler, Aiden, Luke]

On Friday we completed assembly of the new stainless steel-topped benches in 1129. We then moved the clean and bake equipment from 1119 to its new larger space in 1129. This included the HEPA flow bench, ultrasonic washer, deionized water drum, nitrogen tanks, and forced-convection oven. The oven was re-anchored to the wall with earthquake restraints in its new location.

The power cords still need to be permanently routed, but the new clean and bake lab is otherwise ready for use.

    Reply  Wed Dec 20 10:33:34 2023, Jon, Infrastructure, Clean &amp; Bake, Clean and bake lab migrated to 1129 

Update: I have completed permanent routing of the electrical cables. I also ran the ultrasonic washer's drain line to the sink drain (the current hose does reach). The new clean and bake lab is now fully operational.

Quote:

[Jon, Tyler, Aiden, Luke]

On Friday we completed assembly of the new stainless steel-topped benches in 1129. We then moved the clean and bake equipment from 1119 to its new larger space in 1129. This included the HEPA flow bench, ultrasonic washer, deionized water drum, nitrogen tanks, and forced-convection oven. The oven was re-anchored to the wall with earthquake restraints in its new location.

The power cords still need to be permanently routed, but the new clean and bake lab is otherwise ready for use.

 

Entry  Tue Dec 19 15:45:05 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update bake9_231219_Macor_ArO.pngbake9_231219_Macor_ArC.png
Took RGA data for the macor parts inside of the chamber. With the Ar open the HC levels read 30 torrl/s which is around where it was before the bake.
Entry  Mon Dec 18 15:51:49 2023, Aiden, Update, VAC, VAC System Heating Update 
After letting the chamber cool down I put the electronics back on and turned the RGA element back on. No data has been taken yet as to let the pressure continue to fall as the RGA is powered.
Entry  Sun Dec 17 19:43:18 2023, Aiden, Update, VAC, Vac Heating Update 
[Aiden]

I measured the temperature of the flanges where some of the electronics will go and I found that the RGA flange was at 55C and the two full range gauges were at 65C. I also stopped bake 9 to cool down for measurement.

Entry  Fri Dec 15 14:03:02 2023, Aiden, HowTo, VAC, Vacuum Chamber Opening 
[Aiden]

1. Turn off the RGA filament and disconnect it.

2. Record the pressure and then close the angle valve and gate valve on the RGA line to isolate it from the system.

3. Turn off the backing and turbo pump and let the turbo pump spin to a stop by slowly leaking the chamber. The slower the safer.

4.Slowly open the vents on the chamber and the turbo pump. Making sure not to raise the pressure too fast.

5. Once done venting the chamber, open the lid by removing the bolts and prying the lid open with a long flat head screw driver.

6. Removed previous parts and placed them into clean bags. Place new parts inside of the chamber and group them together close to the center.

7. Place the lid back onto the chamber and tighten the bolts in a circular pattern until tightened all the way with the wrench.

8. Make sure all vents are closed and turn the backing pump back on.

9. The turbo pump can be turned back on when the pressure reaches e-1 torr.

10. Wait until the chamber reaches a pressure of e-6 torr before opening the angle and gate valve on the RGA line. After the RGA line is open and the pressure is still below e-6 torr, the RGA filament can be turned on and a leak test of the lid should be performed.

11. After the leak test shows no leaks, proceed with starting the low temp bake.

Entry  Mon Dec 11 16:20:17 2023, Jon, Summary, TCS, FROSTI Assembly Procedure 

Below is the procedure we will follow to assemble the FROSTI prototype.

  1. Install SS guide rods and bottom Macor spacers in bottom reflector
  2. Install AlN elements on top of bottom Macor spacers
  3. Install upper Macor spacers on top of AlN elements
  4. Feed unterminated power and RTD leads through slots in upper reflector
  5. Install upper reflector, using guide rods to slowly lower into position
  6. Install vented SS bolts for reflectors; Macor bolts for heater elements
  7. Remove SS guide rods
  8. Bundle power and sensing cable with PEEK cable ties and SS cable mounts
  9. Terminate power and sensing cable bundles with PEEK DB25M connectors
Entry  Mon Dec 11 12:58:57 2023, Shane, Luis, Update, CDS, DAC-ADC loopback test debugging 
[Luis, Shane] Working on debugging last week's weird results for the ADC-DAC loopback test for channels 14 and 15. With DAC output channels 12-15 connected to ADC input channels 12-15: tried setting matrix coefficients for channels 12-15 to 1, and as with last week's results, DAC is outputting as expected for all three channels and ADC is not reading in the signal (hovering around -4,-5) for channels 14 and 15. Channels 12 and 13 still reading in correctly. Tried switching DAC output plug into channels 0-3, with ADC input plugged into channels 12-15, and all input/output signals were reading correctly. Then switched to plugging in DAC output to channels 12-15 and ADC input to channels 0-3, and saw that channels 0-3 were only able to receive the first two ADC input values. This shows that channels 12-15 are capable of receiving the correct inputs from other channels, but are failing to produce outputs for channels 14 and 15.
Entry  Thu Nov 30 13:50:32 2023, Tyler, Update, Lore, Workbench Assembly Completed IMG_7686.jpg
[Tyler, Luke, Aiden]

The workbenches are now completely assembled and put into their final places. Additionally, the tool chest has been moved.

    Reply  Sat Dec 9 12:34:12 2023, Jon, Update, General, Electronics workshop migrated to 1129 IMG_0765.jpgIMG_0767.jpeg

[Jon, Tyler, Shane, Luis]

On Wednesday we completed the migration of the electronics workshop from 1119 to the large new workbenches in 1129. The two workstations pictured closest to the front of the room are for electronics assembly and testing, while the two in the rear will house LIGO CDS workstations. We moved all of the tools, cabling, and soldering and test equipment from 1119 to this new location. We also moved the large tool chest to 1129, as pictured, and moved the smaller tool chest to 1119 in its place.

The electronics workbench is ready for use. 

Entry  Fri Dec 8 11:15:21 2023, Peter, Update, VLC Update, VLC Assembly IMG_4194.jpgIMG_4195.jpgIMG_4197.jpgIMG_4196.jpg
The optics of the visible light cavity have been assembled. The mode matching telescope is folded through the two stirring mirrors at the corners shown in the image below, with the first lens (f=0.2m) before the first stirring mirror, and the second lens (f=0.5m) between the two stirring mirrors. The distance from the cavity to the edge of the table is 14cm. There is still some work to be done on the alignment of the cavity, as the beam does not seem to be completely centered on the two mirrors.
Entry  Thu Dec 7 14:13:15 2023, Shane, Update, Cleanroom, cleanroom cleaning and particle count 
[Aiden, Shane, Michael, Luke, Cynthia]

cleaning cleanroom and particle count

  • 12:30 pm: ran zero count test on particle counter
  • 12:32 pm: started particle count.
    • zone 3:
      • 0.3 u: 59,488
      • 0.5 u: 9561
      • 1.0 u: 706
    • zone 4:
      • 0.3 u: 7732
      • 0.5 u: 1912
      • 1.0 u: 290

    NOTE: Frame ceiling tile collapsed in cleanroom, explaining insanely high 0.3 u particle count in zone 3 (nearly 6 times above limit). Wiped down tile and put it back in ceiling frame.

  • 12:56 pm: began surface check and wipedown, including softwalls
  • 1:16 pm: started vacuuming the floor
  • 1:32 pm: finished vacuuming the floor
  • 1:33 pm: started mopping the floor
  • 1:47 pm: finished mopping the floor
  • 1:48 pm: started cleaning the buckets
  • 1:53 pm: started mopping with IPA wipes
  • 2:05 pm: finished mopping with IPA wipes
  • 2:06 pm: changed sticky floor mats
  • 1:53 pm: started particle count
    • zone 3:
      • 0.3 u: 6401
      • 0.5 u: 3450
      • 1.0 u: 1787
    • zone 4:
      • 0.3 u: 4073
      • 0.5 u: 2452
      • 1.0 u: 1039
Entry  Thu Dec 7 12:42:42 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update December_06_Ar_Open_Stainless_Steel_Fasteners_Analyzed.pngbake8_231206_SSFasteners_ArO.png
After leaving the RGA on for a few days the chamber has settled at 2.01 e-8 torr. I also have good news that the chamber looks to be even cleaner as the HC levels are now the lowest they have been being at 26 e-10 Torr l/s.
Entry  Mon Dec 4 21:27:53 2023, Shane, Update, CDS, ADC-DAC loopback test results adc-dac_loopback_testing_results.pdf
Here are the test results from today's ADC-DAC loopback tests. Channels 14 and 15 were the only ones behaving abnormally. Not sure what the issue is, but needs further debugging. The DAC output was as expected for both of them, but the corresponding ADC inputs were the same regardless of what offset was used (hovering around values of -4 and -5). NOTE: all measurements listed in the attached table are 'averages' in the sense that the ADC inputs and DAC outputs hovered around the listed values, changing by +1 or -1.
Entry  Mon Dec 4 11:19:50 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update bake8_231204_SSFasteners_ArO.pngbake8_231204_SSFasteners_ArC.pngDecember_04_Ar_Open_Stainless_Steel_Fasteners_Analyzed.pngbake8_231204_SSFasteners_ArO.png
[Aiden]

Took some RGA data of the chamber after it has been cooling down. I do not believe that this data accurately shows the HC levels in the chamber as the pressure is still above where it was at before the bake and was still falling. I believe more time is needed to let the pressure fall and for the RGA filament to remain on to return to a point where the data can be trusted.

Entry  Sat Dec 2 18:10:23 2023, Aiden, Update, VAC, VAC System Heating Update 
[Aiden]

Turned off the heating tape today in anticipation to take more RGA data on Sunday or Monday morning before the meeting.

Entry  Thu Nov 30 13:58:18 2023, Aiden, Update, VAC, VAC System Heating Update 
[Aiden]

Came into the lab in the morning to check on the chamber heating. I decided to set the PID controllers to 110C rather than 120C as the chamber lid and wall were reading near 140C. With the PID controllers at 110C the chamber lid and wall now read 126C and 132C. Currently the PID controllers are placed on the cross in front of the RGA and the reducing nipple in front of the turbo pump. I believe this is a good equilibrium and will leave the tape on until Saturday when it will be turned off to cool down.

Entry  Wed Nov 29 21:13:32 2023, Aiden, Update, VAC, VAC System Heating Update 
Started Bake 8 today. Set the PID controllers to 120 C and will check in the morning for equilibrium temperatures for the lid and chamber wall. The chamber pressure was 2.13 e-8 torr before taking off the full range gauges.

After the bake is done on Saturday it will be cooled down and RGA data will be taken to measure the out gassing rate of the stainless steel fasteners inside the chamber. Then on Tuesday we will plan to vent and open the chamber again to put the macor inside and repeat the another low temp bake and then test the macor early in week 11. Then the next material will be the aluminum mounting hardware for mounting the heaters and that should hopefully be done before the end of week 11 so the heaters can be tested afterwards after being cleaned with vector alpha wipes.

Entry  Mon Nov 27 19:34:50 2023, Aiden, Update, Clean &amp; Bake, Clean and Bake Batch 20 Bagging 
Bagged and tagged bath 20 which included the macor hardware and place it inside the clean room on the table.
Entry  Mon Nov 27 14:22:30 2023, Tyler, Update, Lore, 1129 Assembly Update IMG_7669.jpgIMG_7668.jpg
[Tyler, Michael, Luke, Cynthia]

The tabletops have been attached to the workbench frames. Unfortunately, one of the tabletops came out of the box with a large scratch and small dent in the middle. One of the electric top shelves is ready to be attached to the undamaged table, but the other is yet to be opened. Assembly will be completed Wednesday morning.

Entry  Wed Nov 22 15:46:50 2023, Shane, Update, CDS, DB25 signal connections for FROSTI heaters DB25input_signals.pdfIMG_3137.jpegdc_smart_switch_signal_connections.jpeg
[Shane, Jon]

Installed new DC smart switch in electronics rack, configured power connections. Images attached. Attached is a diagram of the male DB25 signal connections to be used for FROSTI heaters. Also included below is table detailing pin and signal configuration.

Pin Signal
1 V+ Heater 1
2 V+ Heater 2
3 V+ Heater 3
4 V+ Heater 4
5 V+ Heater 5
6 V+ Heater 6
7 V+ Heater 7
8 V+ Heater 8
9 N/C
10 N/C
11 N/C
12 N/C
13 N/C
14 RTN heater 1
15 RTN heater 2
16 RTN heater 3
17 RTN heater 4
18 RTN heater 5
19 RTN heater 6
20 RTN heater 7
21 RTN heater 8
22 N/C
23 N/C
24 N/C
25 N/C
    Reply  Thu Nov 23 12:34:44 2023, Jon, Update, CDS, DB25 signal connections for FROSTI heaters 

Update: I was able to put the FROSTI power controller on the lab network. It is connected to the switch in the top of the rack and is assigned a static IP address of 192.168.1.12 and an NDS hostname of relay1.

The controller can be remotely accessed through an SSH command line interface as well as an HTML webpage, which can be opened from any web browser on the lab network by navigating to the above IP address (the login credentials are the same as for the workstation computers).

There is also an unofficial Python package for interfacing with the controller: dlipower. We will investigate using this package to interface the controller with soft EPICS channels hosted on the CyMAC. This will allow us to create a custom MEDM screen for controlling the FROSTI heater elements.

Edit: The login credentials were set up to be the same as for the CDS workstations.

Entry  Tue Nov 21 22:09:44 2023, Aiden, Update, General, Testing Parts 8x
[Aiden, Luis]

Luis and Aiden vented the chamber today. We closed off the RGA section and then proceeded to open the the vent on the main body after turning off the turbo and backing pump. We then opened the lid and placed in all the stainless steel hardware that will be used in evaluating the FROSTI optics and heater elements. We also inspected the weldments before closing it up. Check the clean and bake data base where there is now a new section outlining the parts in each test. We then closed the lid, tightened the bolts, turned the backing pump back on and let the pressure drop until it was below 1e-1 torr. Then turned the turbo pump back on and after a few hours the pressure was back down to 4.16e-7 torr. The RGA was turned off during all of this and was turned back on when done even though we closed both valves to keep the RGA volume under vacuum.

Entry  Tue Nov 21 14:47:24 2023, Tyler, Update, Lore, 1129 Workbench Assembly Update 1 IMG_7569.jpgIMG_7568.jpg

[Tyler, Shane, Mohak, Cynthia, Luke, Michael, Luis]

Started assembly of the workbench equipment today. We completed the stools, and have constructed the frames of each workbench. All that needs to be added are the tabletops and the top shelves, which will be done on Monday.
Entry  Mon Nov 20 20:45:16 2023, Aiden, Update, VAC, Leak Test 

[Aiden, Luis]

Tested every weld and flange to find leaks. Only found that the flange on the turbo pump and reducing nipple was still at 2e-9 torr on the leak. The chamber still rose in pressure when the two gate valves were closed but no noticeable leak could be found on the lid or welds.

Entry  Mon Nov 20 20:37:45 2023, Aiden, Update, VAC, Clean and Bake Batch 20 
[Aiden, Luis] Started to clean and bake the macor parts for the FROSTI reflector. Per LIGO documentation cleaned the macor in liquinox for 10 minutes and put them in the oven at 200 degC for 24 hours.
Entry  Fri Nov 17 14:06:01 2023, Shane, Update, Cleanroom, 5 zone particle count 23.png
Here's today's 5 zone particle count measurement for the cleanroom. Zone 5 (closest to back wall by fire cabinet) is still above the limit for the larger size ranges; everything else is in good shape and roughly 10 times under the limit. Not sure why zone 5 is still so dirty (maybe some of the electronics being stored in bags/bins on the upper shelf of the desk aren't clean?) but will focus cleaning efforts on this zone next time.
Entry  Thu Nov 16 19:32:31 2023, Aiden, Update, VAC, VAC HC Levels Update bake7_231116_ArO.pngNovember_15_Ar_Open_Analyzed.png
Took some more RGA data today and overlaid it with data taken from October 19. I added a red line that symbolizes where all amu peaks above 44 need to be bellow as well as a black square around the 44th amu peak. The chamber is very close to being meeting LIGO's vacuum chamber standards.
Entry  Thu Nov 16 17:12:42 2023, Luis, Shane, Mohak, Update, Cleanroom, Cleanroom cleaning and particle count 
[Shane, Luis, Mohak]

cleaning cleanroom and particle count

  • 3:37 pm: started particle count
    • zone 3:
      • 0.3 u: 1205
      • 0.5 u: 748
      • 1.0 u: 249
    • zone 4:
      • 0.3 u: 1496
      • 0.5 u: 748
      • 1.0 u: 290
  • 3:57 pm: began surface check and wipedown, including softwalls. NOTE: vacuum chamber insulation crumbling at edges, dropping loose flakes. Scatters residue whenever jostled, so wiping it down just releases more. Not enough flakes are being released for it to be a major issue, but definitely something to keep an eye on.
  • 4:18 pm: started vacuuming the floor
  • 4:29 pm: finished vacuuming the floor
  • 4:30 pm: started mopping the floor
  • 4:35 pm: finished mopping the floor
  • 4:36 pm: started cleaning the buckets
  • 4:41 pm: started mopping with IPA wipes
  • 4:52 pm: finished mopping with IPA wipes
  • 4:52 pm: changed sticky floor mats
  • 4:53 pm: started particle count
    • zone 3:
      • 0.3 u: 3367
      • 0.5 u: 1787
      • 1.0 u: 914
    • zone 4:
      • 0.3 u: 1039
      • 0.5 u: 498
      • 1.0 u: 249
Entry  Wed Nov 15 21:52:33 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update bake7_231115_ArC.pngbake7_231115_ArO.png
Took RGA data before running the degas mode. Made sure to close off the main volume before running the degas. And left the filament on.
Entry  Thu Nov 9 13:48:47 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update bake7_231109_ArC.pngbake7_231109_ArO.png
After bake 7 was stopped on Wednesday morning (11,8,2023), I took RGA data of the chamber to compare to a later scan that will be done on Monday to make sure the chamber has reached its lowest pressure. Below are the graphs.
    Reply  Fri Nov 10 08:32:34 2023, Jon, Update, VAC, RGA experiments 
I ran a 3-minute degas cycle of the RGA filament for the first time yesterday (in this process, the filament gets very hot in order to "boil off" settled particulate). I was surprised to see the pressure (of not just the RGA volume, but also the main volume) rise from 2e-8 to 5e-6 torr.
 
This observation, plus the rise in pressure seen every time the filament is activated for an RGA scan, indicates we have significant particulate settling on the RGA filament. This may be systematically biasing RGA scans taken within a short time (~15 minutes) of turning on the filament.
 
I have two ideas to reduce particulate on the RGA. However, before implementing these, I first want to consult with the vacuum experts at LIGO Lab.
  1. Run a second RGA degas cycle, but next time with the main volume valved off with only the RGA volume being pumped (through the bypass line). This will prevent "boiled off" particulate from entering the main chamber and will also increase the pumping rate for the RGA volume, reducing the amount of particulate that resettles on the RGA filament.

  2. I also noticed that the SRS manual states that the filament is designed to be long-lived and it is recommended to leave it on any time the RGA is on. By leaving the filament on all the time (i.e., hot), we could reduce the amount of particulate that is evidently settling on it between scans. I am checking whether LIGO Lab does this in their own chambers.
       Reply  Tue Nov 14 17:21:40 2023, Jon, Update, VAC, RGA best practices 

As a follow up ELOG 261, I have received advice from one of the vacuum experts at LIGO Hanford on best practices for our RGA:

  1. For future RGA degassing, definitely keep the main volume isolated, since it could contaminate the main volume with everything that just got cooked off of the filament. So the procedure should be to (i) close both gate valves, (ii) ensure the angle valve on the bypass line is open, (iii) initiate the degas cycle on the RGA, (iv) pump the RGA volume through the bypass line, until its pressure returns to its pre-degas level.

  2. Repeated degassing of the filament will definitely wear it down much faster, so do this operation sparingly.

  3. As long as the pressure of the RGA volume is in the UHV range (~1e-9 torr), best practice is to leave the filament on. This keeps it hot which helps prevent particulate from settling on it. However the electron multiplier should stay off when not actively taking scans, as it will wear down if left on all the time.

Entry  Thu Nov 2 17:14:36 2023, Shane, Jon , Update, CDS, CyMAC set up permanentized  cymac_chassis_back.jpegcymac_chassis_back2.jpegcymac_chassis_front.jpegfinal_connections_back_of_power_supply.jpegpower_supply_back.jpeg
CyMAC connections have been finalized and made permanent. Also tested voltages, which are all looking good.

Warning: power is on. Do not touch power supply terminals or screws connected to grounding cables (see attached images 4 and 5; green wires on back of power supply with black and yellow covers, and exposed positive and negative terminals on back of power supply).

Also established connections from Anti-Aliasing chassis to ADC adapter board, Anti-Imaging chassis to DAC adapter board, and binary in/out chassis to BIO card, all mounted within Cymac host computer. Turned on CyMAC and ran test model, received error message likely pointing to timing signal not being successfully passed to the adapter boards. Next steps are checking to make sure correct timing signal is actually being output, and then checking internal ribbon cable in host chassis, which is another potential cause of the error.
    Reply  Mon Nov 13 11:23:54 2023, Jon , Update, CDS, CyMAC testing Cymac_GDS_Diagnostics.png

[Jon, Shane, Luis]

My repair of the internal ribbon connecting the ADC to the adapter board resolved the timing signal problem. After this repair, we were able to start the front-end IOP model and checked out the RTS diagnostic screens (pictured below). All indicator lights were green except for the DK flag (indicating the DAC outputs are not enabled) and the DAQ flag (indicating that the system is recording data to disk). Those were both as expected, because the DAQD data acquisition service was not set up yet and the DAC outputs are not enabled until at least one user model (which outputs signals to the DAC) is started. I created and installed a simple user model (C1MSC) and confirmed that the DK flag clears once this model starts.

I later attempted to set up the DAQD service, which is needed to save data, but am yet to successfully debug it. I have received some guidance from one of LIGO's CDS experts and will try it at my next opportunity for lab work.

Entry  Mon Nov 13 11:07:50 2023, Tyler, Update, VAC, RTD Analysis Screenshot_2023-11-13_at_11.05.45_AM.pngScreenshot_2023-11-13_at_11.06.04_AM.png

After initial analysis from last week on a single RTD, I then extended to looking at all 8 in series with R_ref (set to 1 kOhm). Shown below are the edge cases for the setup:

  • RTDs are all at ambient lab temperature. This would correspond to a minimum resistance value.
  • RTDs all read out 400 C. This gives the maximum resistance value.

The results show that indeed only a few mA of current is drawn even at room temperature (a little above 5.5 mA), and this will continue to decrease with increasing temperature. The voltage across a single terminal, at a maximum, is only about 5.4 V.

Entry  Mon Nov 13 06:15:45 2023, Peter, Update, VLC Update, VLC Mode Matching VLC_Mode_Matching_3.pdf
Weekly Updates Attached in pdf
Entry  Fri Nov 10 14:16:04 2023, shane, Update, Cleanroom, new cleanroom zone diagram cleanroom_zones_nov2023.jpg
since the vac system has been moved and made permanent, here's a new diagram of the cleanroom zones. The zones themselves haven't moved, but the diagram has been updated to reflect the new set up of the cleanroom.
Entry  Thu Nov 9 19:06:46 2023, shane, Update, Cleanroom, 5 zone cleanroom measurement 23.jpeg
Here's today's five zone measurement, taken ~5 hours after the cleaning. Zone 5 (closest to fire cabinet and back wall) is a bit over the limit in all size ranges (about 1500 particles in 1.0u size range over), and zone 2 is slightly over the limit in the 1.0u range, but everything else is under the requirement.
Entry  Thu Nov 9 13:57:58 2023, Shane, Luis, Aiden, Tyler, Update, Cleanroom, cleanroom cleaning and particle count 
[Aiden, Shane, Luis, Tyler]

cleaning cleanroom and particle count

  • 12:30 pm: Tyler and Aiden started organizing cables in cleanroom
  • 12:35 pm: started particle count in flow bench
    • 0.3 u: 11681
    • 0.5 u: 3284
    • 1.0 u: 1039
  • 12:50 pm: started cleanroom particle count
    • zone 3:
      • 0.3 u: 14549
      • 0.5 u: 10351
      • 1.0 u: 6194
    • zone 4:
      • 0.3 u: 10808
      • 0.5 u: 4655
      • 1.0 u: 1953
  • 1:07 pm: began surface check and wipedown, including softwalls
  • 1:19 pm: started vacuuming the floor
  • 1:28 pm: finished vacuuming the floor
  • 1:29 pm: started mopping the floor
  • 1:33 pm: finished mopping the floor
  • 1:34 pm: started cleaning the buckets
  • 1:37 pm: started mopping with IPA wipes
  • 1:39 pm: finished mopping with IPA wipes
  • 1:40 pm: changed sticky floor mats
  • 1:41 pm: started particle count
    • zone 3:
      • 0.3 u: 8397
      • 0.5 u: 5071
      • 1.0 u: 2618
    • zone 4:
      • 0.3 u: 6651
      • 0.5 u: 4323
      • 1.0 u: 2120
Entry  Wed Nov 8 17:55:49 2023, Jon, Update, General, Lab Clean-Up Day 1 

[Jon, Tyler, Shane, Peter, Luis]

Today we completed the first phase of lab clean-up. Activities included:

  • CF/KF parts stored under the cleanroom table were removed and transferred to Physics 1129
  • Cleanroom workbench cleared, with all FROSTI hardware collected into one of the large SS bins
  • High surfaces outside the cleanroom (lights, table enclosure frames, rack, cabinets) wiped down with IPA wipes
  • Floor HEPA-vacuumed outside the cleanroom
  • Sticky mats changed throughout the lab

Tomorrow, we will complete turn-over of the cleanroom (HEPA vacuuming of floors, mopping of floors, IPA wiping of softwalls and work surfaces). Shane will post a forthcoming measurement of the cleanroom particulate levels, post-turnover.

Entry  Mon Nov 6 11:31:25 2023, Peter, Update, VLC Update, VLC Mode Matching VLC_Update_11_6_23.pdf
See Update Attached
Entry  Mon Nov 6 11:29:24 2023, Tyler, Update, Electronics, Preliminary RTD Calculations, RP Software Update cvt.pngVvC.pngIMG_7471.jpg

Preliminary RTD calculations are shown below, given an input of 10 V and desiring a few mA of current. It looks like R_ref should be at least 1 kOhm (refer to plots/circuit below), keeping in mind we need to have <10 V input for the ADC.

RP: The Red Pitaya Software was updated to OS 2.00. All examples on the RP website should run without issue.

Entry  Wed Nov 1 20:22:07 2023, Aiden, Update, VAC, VAC System Heating Update 
Raised the PID controller temperature to 105C today as at that temperature the lid and the barrel temperature sensors were reading around 120C. I will check again tomorrow to see if there is any room for increase after equilibrium.
Entry  Wed Nov 1 18:24:01 2023, Shane, Update, CDS, CyMAC Power connections made cymac_power_connected.jpegcymac_power_connections_back.jpeg
Finished power connections today for the CyMAC chassis. Images attached. Had to switch the shrink fork terminals on the power supply cables to shrink ring terminals, but was able to get everything connected and secured. Upcoming work: turning on power supply and testing voltages/checking everything is turning on and lighting up correctly. Configuration is as follows:
  • Topmost Sorensen: +24V (reserved for FROSTI)
    • Positive terminal:
      • unconnected for now
    • Negative terminal: [negative terminal is grounded]
      • jumper to Sorensen ground screw
  • Sorensen 2nd from the top: +18V
    • Positive terminal:
      • white power cable wire for AA chassis
      • white power cable wire for AI chassis
      • white power cable wire for BI chassis
      • white power cable wire for BO chassis
    • Negative terminal: [negative terminal is grounded]
      • jumper to Sorensen ground screw
      • black power cable wire for AA chassis
      • black power cable wire for AI chassis
      • black power cable wire for BI chassis
      • black power cable wire for BO chassis
  • Sorensen 3rd from the top: -18V
    • Positive terminal:[positive terminal is grounded]
      • jumper to Sorensen ground screw
      • green power cable wire for BI chassis
      • green power cable wire for BO chassis
    • Negative terminal:
      • green power cable wire for AA chassis
      • green power cable wire for AI chassis
  • Bottommost Sorensen: +6V
    • Positive terminal:
      • white power cabe wire for timing chassis
    • Negative terminal: [negative terminal is grounded]
      • jumper to Sorensen ground screw
      • green power cable wire for timing chassis
      • black power cable wire for timing chassis
Entry  Tue Oct 31 19:46:35 2023, Aiden, Update, VAC, VAC System Heating Update IMG_4745.jpgIMG_4744.jpg
Started bake 7 on Monday but found issues with the heating as the cross in front of the RGA got way too hot too quickly. This resulted in shutdowns of the heater tape while I could still only set the main PID controller for the lid to 75C. Tuesday I moved the PID controller sensors to be on the cross in front of the RGA and on the Reducing nipple. I then placed the alarm sensors onto the lid of the chamber and the barrel. This should hopefully prevent excessive heating on then smaller components. I also started the bake again Tuesday, but only set the temperature to 85C for now and will increase it further tomorrow when I get a good idea of the equilibrium point of the chamber.
Entry  Mon Oct 30 18:15:13 2023, Shane, Update, CDS, CyMAC chassis mounted and progress on power connections electronics_rack_back.jpegelectronics_rack_front.jpegmounted_chassis.jpegpower_supply.jpeg
All CyMAC chassis mounted in electronics rack today, and shelf for monitor also mounted. Images attached. Assembled grounding cables for power connections, and attached the timing chassis to power & gnd. Powered on successfully with correct voltages in expected places. After power test, everything was turned off and unplugged. Next steps: attach grounding cables to other four power supply chassis. Also attach anti-aliasing, anti-imaging, binary input and binary output chassis to power supply.
Entry  Mon Oct 30 11:03:56 2023, Tyler, Update, Scripts/Programs,  Screenshot_2023-10-23_at_12.39.05_PM.png

FLIR: After some adjustments, the plot generated from the FLIR measurements look much more symmetric (see attachment). There are more included grid points, which smooths out the curve as compared to last week.

Red Pitaya: It looks like a new OS update was released for the RP, which includes a new Python API (was previously only available in C). I'm going to try and update the one we have currently running in lab.

Entry  Fri Oct 27 15:16:31 2023, Aiden, Update, VAC, Vacuum Leak Test 
Leak tested the worst flanges on the chamber after moving it and after bake 6. The 6 inch flange connected to the 8 inch reducing nipple is now leaking at 1.5 e-9, previously at 4 e-9. The 8 inch flange connected to the turbo pump is now leaking at 1.9 e-9, previously at 3 e-9. This means that the baking most likely improved the seals on these flanges and a hotter bake might fix the leaks for good.
    Reply  Mon Oct 30 08:42:22 2023, Jon, Update, VAC, Vacuum Leak Test IMG_0659.pngIMG_0660.png

By 5:30 pm Friday, the pressure had reached 8.6e-8 torr and was continuing to fall. So it seems we are OK to proceed with permanentizing this configuration (cable routing, heater tape reinstallation).

Quote:
Leak tested the worst flanges on the chamber after moving it and after bake 6. The 6 inch flange connected to the 8 inch reducing nipple is now leaking at 1.5 e-9, previously at 4 e-9. The 8 inch flange connected to the turbo pump is now leaking at 1.9 e-9, previously at 3 e-9. This means that the baking most likely improved the seals on these flanges and a hotter bake might fix the leaks for good.

 

Entry  Fri Oct 27 15:28:30 2023, Shane, Update, CDS, AA and AI chassis for CyMAC powered on and functional AI_chassis_lights_on.jpegAA_chassis_lights_on.jpeg
CyMAC updates: Switched out the faulty power regulator boards in the Anti-Aliasing and Anti-Imaging chassis. Both chassis are now powering up correctly with lights on and the correct voltages in/out of the power regulator board. Images attached. All chassis for the CyMAC now functional, so next step is mounting everything in the rack.
Entry  Thu Oct 26 13:00:45 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update bake6_231026_ArC.pngbake6_231026_ArO.png
Bake 6 was turned off on Monday. Tooke RGA data today and have posted the data below. The pressure of the chamber after taking data was 3.22 e-8 Torr. The chamber HC levels are still not low enough but I feel with more pumping it will go down as the RGA scan was still slowly going down during the data taking.
Entry  Mon Oct 23 18:02:23 2023, Shane, Jon, Update, CDS, Timing chassis assembly complete timing_chassis_complete.jpegtiming_chassis_output_1.jpegtiming_chassis_output_2.jpeg
Concluded assembly of timing chassis for CyMAC today; see attachment 1 for interior set up of chassis. Installed front and rear panels, wired on/off switch and LED assembly, and tested to confirm everything is powering on correctly. Also tested the outputted timing reference that will go to DAC and ADC adapter boards (see attachment 2 for output 1 and attachment 3 for output 2).
Entry  Mon Oct 23 11:28:05 2023, Tyler, Update, Cameras, FLIR Camera Code Updates Screenshot_2023-10-23_at_11.06.04_AM.png
The past week I've been spending time going through the FLIR code on gitlab. Initially, it had appeared that our measurements with the camera had differed about 2 degrees C from what the thermocouple was giving (Ref ELOG 181). Upon inspection of the FLIR streaming code, I noticed a few issues: 1. The emissivity value wasn't set correctly (was 0.999 originally, should be about 0.95). 2. The ambient temperature was set to about 21.6 C (71 F). 3. The distance given before was about an inch off from what I measured. These three parameters all must be manually specified to calculate the temperature values, and are what I assume caused the larger temperature difference seen before. I've attached a new set of measurements that I took below, where 6 images were taken by the camera, looking at a heating source with a current of 0.15 A being driven. The difference between the camera and the thermocouple were much smaller, as seen below. I'd still like to take a few more measurements to solidify that this has rectified the issue, but at the moment it seems this is working much better. Images at: https://drive.google.com/drive/folders/1VDvZ1rfEGWsHq1AgG-chde3Cd8Do_piD?usp=sharing
Entry  Mon Oct 23 07:28:57 2023, Peter, Update, VLC Update, VLC Mode Matching Carney_VLC_Update.pdf
I have attached a pdf with slides of my latest updates.
Entry  Fri Oct 20 16:38:02 2023, Shane, Aiden, Update, Cleanroom, Cleanrooom cleaning and particle count 
[Aiden, Shane]

cleaning cleanroom and particle count

  • 3:16 pm: started particle count.

    NOTE: we are not within the ISO class 5 standard for any size ranges in zone 3. ~6000 above limit in 0.3 u, ~2000 above in 0.5, ~200 above in 1.0

    • zone 3:
      • 0.3 u: 16,711
      • 0.5 u: 5612
      • 1.0 u: 1039
    • zone 4:
      • 0.3 u: 6817
      • 0.5 u: 2369
      • 1.0 u: 249
  • 3:35 pm: began surface check and wipedown, including softwalls
  • 3:50 pm: started vacuuming the floor
  • 4:00 pm: finished vacuuming the floor
  • 4:01 pm: started mopping the floor
  • 4:06 pm: finished mopping the floor
  • 4:07 pm: started cleaning the buckets
  • 4:08 pm: started mopping with IPA wipes
  • 4:14 pm: finished mopping with IPA wipes
  • 4:15 pm: changed sticky floor mats
  • 4:18 pm: started particle count
    • zone 3:
      • 0.3 u: 23,113
      • 0.5 u: 9686
      • 1.0 u: 1371
    • zone 4:
      • 0.3 u: 7191
      • 0.5 u: 2951
      • 1.0 u: 290
Entry  Thu Oct 19 11:41:04 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update 6x
[Aiden, Tyler, Mohak]

Took some RGA data when we came into the room. The pressure of the chamber was 8.63e-8 Torr before turning on the RGA filament. We saw the usual spike in pressure when the filament was initially turned on. Took some data and saw that the chamber was definitely dirtier since the vacuum upgrade. See figures below.

Put the heater tape back onto the section that was removed. We may need to rearrange the heater tape again as there was not much heater tape to go around the upgraded section. We also tried to get some of the extra insulation around this section and we able to get some on around the 6-8 inch reducer.

We then took off the electronics for the gauges and the RGA, added the new extension cords to the PID controllers, and then started bake 6 which will go to 120 degC and stay that way until most likely Monday. The pressure before starting the bake was 8.28e-8 Torr.

Entry  Thu Oct 12 12:11:10 2023, Aiden, Update, VAC, Vacuum chamber Helium leak test IMG_4689.jpgIMG_4688.jpg
[Aiden, Tyler, Peter, Jon]

Continued tightening bolts on the turbo pump and 6"-8" reducer to reduce the leak. The final leak test values for the turbo pump flange was 3.0 e-9 and the other 6"-8" reducer flange was 4.0 e-9.

We will continue to let it pump down as the screws could not be tightened anymore. Looks like new gaskets will be needed to reduce the leaking on these flanges.

Entry  Wed Oct 11 20:47:11 2023, Jon, Update, VAC, Vacuum upgrade begins IMG_0619.pngIMG_0621.pngIMG_0618.png

[Jon, Tyler, Aiden, Peter]

Upgrade of the UHV system to a larger turbo pump began today. After obtaining a final RGA scan in the old configuration (Aiden to post), we vented all three volumes and proceeded to disassemble the 4.5"-diameter pump line. We completed installation of the new 6"-diameter pump line to the point where the new turbo pump will attach. This includes a 6" manual gate valve, 6"/2.75" reducing cross, and 6"/8" conical reducing nipple, as pictured below. Strain relief was also installed due to the longer length and greater weight of the new fittings.

Tomorrow we will continue with attaching the Varian TV 551 pump and perform a pump-down test. If this pump is confirmed to be operable, then we will relocate the entire system ~18" closer to the middle of the table and permanentize the setup.

Entry  Mon Oct 9 21:41:24 2023, Aiden, Update, Clean &amp; Bake, Clean and Bake Batch 19 
Bagged and tagged the parts from batch 18. Started the Copper batch that includes all the gaskets needed to start the vacuum chamber upgrade.
Entry  Mon Oct 9 16:59:21 2023, Shane, Jon, Update, CDS, timing chassis power cable and AI chassis testing for CyMAC IMG_1457.jpeg
[Shane, Jon]
    Today's CyMAC work:
  • Finished assembling external power supply cable for the timing chassis (see attached image)
  • Also did some debugging of AA and AI chassis re: power issues. After testing voltages at various test points on the power regulator board (TP1-TP6) in the AA chassis, it seems like it's the source of the problem. Used bench DC power supply to test, running 15V, and the correct voltage is coming in to the board but something significantly smaller is being output. We're also getting unexpected negative signs on voltage at certain test points, with leads in correct positions
  • Upon further examination, it looks like the lights on the filter boards are actually turning on (in both the AA and AI chassis), though it's only 2/4 lights on each board and they are very faint
  • Corrected DC on/off switch spade lug orientation in AI chassis.
  • Tested AI chassis power regulator board to see if the problem was the same, and found again that voltage coming in was correct, and voltage going out was not.
  • In case of interest in exact numbers, results were as follows:
    • Voltage difference between TP1(+Vin) and TP6(-Vin) is ~30V
    • Voltage difference between grounded chassis wall and TP1 (+Vin) is ~15V
    • Voltage difference between grounded chassis wall and TP6(-Vin) is ~-15 V
    • voltage difference between TP2(+Vout) and TP5(-Vout) is ~3V
    • Voltage difference between TP3 (gnd) and TP2(+Vout) is -0.065V
    • Voltage difference between TP5(-Vout) and ground is ~3V
Entry  Mon Oct 9 11:29:37 2023, Tyler, Update, Electronics, PSD/CSD Plot Updates Screenshot_2023-10-09_at_11.20.25_AM.pngwelch_csd-2.png
Continuing from Sophia's SURF Project this summer: Plotting the Power-Spectral Densities (PSDs) and Cross-Spectral Densities of two signals. A continued issue that has been observed in the plots is the random "jump" of one PSD curves. Below, a 1.4 kHz signal is driven with a magnitude of 0.7 Vpp, and connected to the two output ports of the Red Pitaya via an SMC T-Adapter. At the moment, I anticipate that this bug might have something to do with the Real-Time GUI code being used, since this hasn't been observed when running the calculations without it (see below).
Entry  Mon Oct 9 11:06:17 2023, Peter, Update, VLC Update, VLC Launch Chain IMG-3540.jpgIMG-3538.jpgIMG-3533.jpgIMG-3522.jpg
Implemented the new stage for the EOM. Took power data at different positions in the launch chain. Beam waist: 0.066mm (beam waist is inside EOM). Power before EOM: 0.473mW. Power after EOM: 0.452mW. Power after Faraday Isolator: 0.415mW. Might need to adjust better to configure for clipping losses. Images of setup are attached below.
Entry  Sat Oct 7 17:10:27 2023, Aiden, Update, Clean &amp; Bake, Clean and Bake Batch 18 
Bagged and tagged the parts from Batch 17 and placed them in the clean room on the optic table. Also started an aluminum batch of parts that included the kf clamps and the heater mounting parts.
Entry  Tue Oct 3 15:07:48 2023, Aiden, Update, Clean &amp; Bake, Clean and Bake Batch 17 
Cleaned and baked all the stainless steel parts in Batch 17. Check data base for more details on this.
Entry  Fri Sep 29 17:27:30 2023, Shane, Jon, Update, CDS, Timing chassis assembly progress (CyMAC) timing_chassis.jpegBI_chassis.jpeg
Worked on timing chassis assembly today for the CyMAC, settled on layout (see attachment 1). Frequency synthesizer and frequency divider tentatively mounted. Next steps involve putting together and installing an LED and DC on/off switch assembly like the one in the binary input chassis (attachment 2 for comparison; orange and black wires in BI chassis analogous to red and black wires in timing chassis). Will also use front and back panels of BI chassis as a template for the timing chassis panels, with the following alterations: two SMB feedthroughs in place of the ribbon cable connections shown on the back panel, the addition of an LED on the front panel to indicate power, and potentially a spot on the front panel for usb connection to programmable frequency synthesizer.
Entry  Fri Sep 29 11:53:54 2023, Shane, Update, Cleanroom, 5 zone particle count measurement in cleanroom  23.png23.png
Today's 5 zone measurement of cleanroom particulate concentration is attached
Entry  Fri Sep 29 11:22:33 2023, Shane, Aiden, Update, Cleanroom, cleaning and particle count 
[Aiden, Shane]

cleaning cleanroom and particle count

  • 10:06 am: ran zero count test on particle counter
  • 10:07 am: started particle count
    • zone 3:
      • 0.3 u: 2203
      • 0.5 u: 831
      • 1.0 u: 540
    • zone 4:
      • 0.3 u: 374
      • 0.5 u: 124
      • 1.0 u: 124
  • 10:25 am: began surface check and wipedown
  • 10:34 am: started vacuuming the floor
  • 10:44 am: finished vacuuming the floor
  • 10:45 am: started mopping the floor
  • 10:49 am: finished mopping the floor
  • 10:50 am: started cleaning the buckets
  • 10:57 am: started mopping with IPA wipes
  • 11:01 am: finished mopping with IPA wipes
  • 11:02 am: changed sticky floor mats
  • 11:03 am: started particle count
    • zone 3:
      • 0.3 u: 2535
      • 0.5 u: 374
      • 1.0 u: 166
    • zone 4:
      • 0.3 u: 581
      • 0.5 u: 41
      • 1.0 u: 0
Entry  Thu Sep 28 15:17:13 2023, Aiden, Update, Clean &amp; Bake, Clean and Bake Batch 16 
Bagged and Tagged the parts from batch 15 and started baking batch 16 which includes the 6" to 8" reducer.
Entry  Fri Sep 15 17:33:35 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update bake5_230915_ArC.pngbake5_230915_ArO.png
Took some more RGA data and see that the chamber has gotten much cleaner since monday. Next step would be another bake with some focus around heating the RGA filament more. The pressure in the chamber before testing was 5.32 e-8 torr.
Entry  Thu Sep 14 17:05:38 2023, Shane, Jon, Update, CDS, Timing chassis setup and testing 
Tested the setup today for the timing chassis (intended to provide the timing reference for the CyMAC). Was able to read the correct frequency, but voltage was significantly lower than needed. Still identifying source of problem, and looking into the relationship between the supportable ohm load and the voltage.
Entry  Tue Sep 12 15:31:31 2023, Aiden, Update, Clean &amp; Bake, Clean and Bake Batch 15 IMG_4647.jpg
Cleaned and Baked the SS screws for the heater mount. Check the Clean and Bake data base on the website to get a precise list of the parts and their numbers. Cleaned them with liquinox in the ultra sonic washer for 10 minutes. Then dried them with nitrogen. Then put the stainless steel parts into the oven for the following steps; 1. Ramp to 100 C in 15 minutes 2. Dwell at 100 C for 30 minutes 3. Ramp to 200 C in 30 minutes 4. Dwell at 200 C for 48 hours 5. Turn off
Entry  Mon Sep 11 16:02:42 2023, Aiden, Update, VAC, VAC System Heating Update bake5_230911_ArO.pngbake5_230911_ArC.png
The chamber has cooled down from bake 5 and I took the first set of data. The pressure measured during the RGA measurements reached 9.98 e-8 torr. The data shows that the chamber got dirtier, however this has been the case for every first scan after a bake so I assume there are still some more hydrocarbons to be vacuumed out and that the second scan will most likely give a better idea of where the chamber is at. After turning off the RGA the pressure immediately dropped to 7.4 e-8 torr and was still dropping.
Entry  Fri Sep 8 16:10:43 2023, Aiden, Update, VAC, VAC System Heating Update 
Turned off the PID controllers to let the chamber cool down. Final temperatures for the RGA cross and Turbo pump cross were 113 C and 80 C respectively. The system should be cool enough to start taking measurements on Monday.
Entry  Thu Sep 7 19:24:25 2023, Peter, Update, VLC Update, VLC Launch Chain IMG-3404(1).jpgIMG-3408(1).jpg
The launch optics up to the Faraday Isolator have been added to the breadboard. In the first image, the optics are (from L to R) the stirring mirror, half-wave plate, polarizing cube, 100mm f lens, electro-optical modulator, Faraday isolator, 50mm lens (not part of final design), stirring mirror (not part of final design)
Entry  Tue Sep 5 16:43:19 2023, Aiden, Update, General, VAC System Heating Update 
Checked on bake 5 today after 3 days of equilibrium. The RGA cross is at 106 C and the turbo pump cross is at 74 C. This was reached while the PID controllers were at 140 C. I will now slowly raise the temperature to 150 on the PID controllers and see if the difference in the RGA cross can be reduced.
Entry  Fri Sep 1 19:21:19 2023, Aiden, Update, VAC, VAC System Heating Update 
Started bake 5 today. This will hopefully be a longer and hotter bake with it lasting 6-7 days at around 150 C. The pressure in the chamber before removing the full range gauge and RGA box was 5.01 e-8 torr. The Argon leak was also left open for this bake to hopefully get rid of particulates on it. I also put the heater tape I removed last time back onto the RGA cross. This made the heating up process take much longer as I had to not increase too much or the cross would heat above 150 C. Hopefully some PID settings in the future will help with this issue. I was able to set the PID controllers to 140 C and after some equilibrium time I should be able to get the temperature up to 150 C. The temperature sensors are reading 150 C and 77 C for the RGA cross and Turbo pump cross respectively. The Turbo pump is drawing the normal .17 Amps at 33 C.
Entry  Thu Aug 31 12:56:29 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update bake4_230831_ArC.pngbake4_230831_ArO.pngbake4_230829_ArO.png
Took some more RGA data to see if the HC levels have further declined since bake 4 and it seems that it has started to plateau with August 29 160.7 e-10 Torrl/s and August 31 giving 158.4 e-10 Torrl/s. The pressure of the chamber before taking data was 5.1 e-8 Torr. I have attached an overlay of the data from August 29 and August 31. It seems that the extra two days has not noticeably changed the data and another bake will most likely be needed to meet LIGO's HC specifications. The pressure after leaving the RGA off for a bit was 5.9 e-8 torr and it was still slowly decreasing.
Entry  Tue Aug 29 22:07:38 2023, Aiden, Update, General, Electronic Bench IMG_4632.jpg
Dr Richardson is working on mounting more power supplies in the server rack and is using the electronics bench. Be aware to not move anything on the bench itself.
Entry  Tue Aug 29 19:09:21 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update bake4_230829_ArO.pngbake4_230829_ArC.png
Here are some more plots with the RGA data take August 29. It seems that more pumping time has led to the HC levels being dramatically reduced compared to only a day ago. The pressure also rises significantly when turning on the RGA filament and it doe not go back down to the pressure before turning it on while the RGA is still running. The pressure after I left was 6.86 e-8 torr.
Entry  Mon Aug 28 14:43:50 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update bake4_230828_ArC.pngbake4_230828_ArO.png
The PID controllers were turned off on Friday and the chamber was left to cool over the weekend. Just took data and it looks like signal to noise ratio is pretty bad again. I do not know if this means we need a hotter bake or if the chamber needs some more time to cool down. I will overlay this data and make sure to take a second set a bit later to compare. Some good news though is that the chamber has reached a pressure below 10e-8 torr with the full range gauge above the RGA line reading 6.85 e-8 torr and still dropping.
Entry  Mon Aug 21 17:13:25 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update bake3_230821_ArC.pngbake3_230821_ArO.png

Came in to take RGA data and found the turbo pump drawing .38 Amps. This was much higher than what it was on Friday. I investigated and found that the breaker had flipped controlling the power strip that the scroll pump was on. The scroll pump was thus not running. I flipped the breaker back and turned the scroll pump back on. I do not know if this will be a reoccurring problem as this has happened before, or if this was due to the storm. Either way the scroll pump is running and the turbo pump is now only drawing .18 Amps at 31 C.

Below are the graphs for the RGA scan that I took before starting bake 4. I have not overlaid them yet so the first one is for Argon leak closed and the second is the Argon leak open. It seems that the chamber had gotten dirtier since the leak and there is still a lot of water left in the chamber. I assume the water will go away after the low temp bake but the HC count may not go down without a longer baker. I also measured the pressure before starting the bake and it was 4.16 e-7 and 3.31 e-7 torr for t he main body volume and RGA volume respectively.

When starting the bake I noticed that the temperature sensor placed on the cross in the RGA volume was reading 40 C hotter that what the PID controller was reading for the lid. I had to remove some of the heater tape from the cross as it was way too hot compared to the lid. After removing the second strip across the cross it is still much hotter than most parts due to it being such a small part compared to the large lid. I hope that after a little bit of equilibration time that the difference between these numbers will go down. Both PID controllers were set to 120 C. The RGA cross was reading 130 C and the Turbo pump cross was reading 76 C.

Entry  Thu Aug 17 15:18:48 2023, Aiden, Update, VAC, VAC Heating System Update IMG_4628.jpg
Relocated the PID controllers so that the heating tape could be plugged in. In the picture the left one controls the top half of the chamber along with the RGA line and has its sensor on the lid near a fold. The right one controls the bottom half along with the turbo pump line and the bypass line and has its sensor on the barrel of the chamber. The chamber is almost ready to bake again and just needs to have the full range gauges and RGA electronics box removed.
Entry  Thu Aug 17 15:02:44 2023, Aiden, Update, VAC, VAC Heating System Update 11x

Put the heating tape back on and made sure to have 4 coils around the barrel of the chamber. To make this happen I did not put any heater tape on the ports but made sure to place some of the heater no more than 1 inch away from the ports. Also re-placed some of the heating sensors. For the PID controllers there is one sensor placed on the lid and one sensor placed on the barrel. For the temperature alarms one sensor was placed near the flange of the turbo pump and another placed on the cross in the RGA line. Note that all four of these sensors were placed under the heating tape compared to the last few bakes where they were on top.

The insulation was also put back on and now the chamber should be ready for a low temperature bake after some RGA data is taken before for comparison.

Entry  Wed Aug 16 17:17:02 2023, Shane, Jon, Update, CDS, Binary input chassis powering correctly  IMG_9253.jpeg
Binary input chassis passed power-on test, and is lighting up as expected. Binary output chassis also successfully powered on. AA and AI chassis not powering on correctly, need to do some debugging to find the problem.
Entry  Wed Aug 16 16:55:40 2023, Shane, Jon, Update, CDS, external power supply cables finished IMG_9251.jpeg
All four external power supply cables for the CyMAC chassis are now assembled. Using them now to test if chassis power up correctly.
Entry  Tue Aug 15 16:10:06 2023, Celeste, Update, TCS, 8/15/2023 Simulation Progress Simulation_Progress__1_32nd_Model_(2).pdf
 
Entry  Tue Aug 15 16:04:23 2023, Aiden, Update, VAC, VAC Heating System Update 6x

Pulled off the rest of the heater tape along with the aluminum tape left behind. The aluminum tape adhesive left behind a ton of junk on the walls of the chamber. This is probably due to excessive heating. In order to get the adhesive off I sprayed a vector alpha wipe with acetone and wiped down the walls. This took a lot of acetone to get it off.

When removing some of the aluminum tape I noticed small sections that seemed to have been melted to the silicone part of the heater tape and would have been damaging to try and forcefully remove it.

The heater tape is now ready to be put on again but now with the start of the tape placed on the other side so that the PID controllers can be placed on the shelf above the chamber and be seen outside of the curtain.

Entry  Tue Aug 15 13:32:37 2023, Sophia, Update, Scripts/Programs, Update on Laser Noise Data Collection and Analysis: Dynamic CSD and PSD Plots Screenshot_2023-08-15_at_4.27.58_PM.pngScreenshot_2023-08-15_at_2.21.18_PM.pngScreenshot_2023-08-15_at_5.25.05_PM.png
I have now fixed all issues that I was having this morning, and have added text boxes which show the peak values of both PSD's and the CSD alongside the graphs. They also update continuously with the graph. This is shown in the top image. The laser was driven at 400Hz, and had 0.5V peak to peak voltage, both of which appear correctly in the below graphs. Now that the code is almost fully working (we will finish debugging the screenshot method later today), our plan tomorrow is to drive the laser and see how the code performs with it. The below graph is from us driving the function generator at 100Hz to test the range. Update: Bottom graph is new version of graphs with better distribution of both graphs.
Entry  Tue Aug 15 10:35:00 2023, Sophia, Update, Scripts/Programs, Update on Laser Noise Data Collection and Analysis: Dynamic CSD and PSD Plots Screenshot_2023-08-14_at_8.18.49_PM.pngScreenshot_2023-08-14_at_8.18.43_PM.pngScreen_Recording_2023-08-14_at_8.17.50_PM.movScreenshot_2023-08-15_at_1.24.54_PM.pngScreenshot_2023-08-15_at_1.32.30_PM.png
I have successfully added a button to my graphics, but it has posed a strange issue with the CSD and PSD values. When I plot my original code, I still see the pretty peaks that I was getting originally, while my new code (as shown in the video and in the last screenshot) is giving me more of a line. In my code that gives the peak values, the CSD values also tend to fluctuate in this new code as well (shown in the first screenshot), before returning to the real value. I think that there is a problem with the averaging and am hoping to solve this issue today with Tyler. This is good progress though!
Entry  Fri Aug 11 18:32:00 2023, Aiden, Update, VAC, VAC System Heating Update 11x

[Dr. Richardson, Aiden] Large Update

Removed most of the insulation on the chamber in order to pull back some of the heater tape to get to the flange connecting the bypass line to the valve under the RGA line. Most of the heater tape on the bottom half of the chamber was pulled off and the rest will need to be removed as well in order to place the start of the heater tape on the barrel of the chamber rather than one of the flanges.

Engaged the valve under the RGA line to prevent it from getting more contaminated. Turned off the turbo pump. Turned off the scroll pump. Let the turbo pump sit for a few minutes to let the fans stop. Then leaked the turbo pump volume by turning the knob slowly on top of the turbo. Then proceeded to unscrew the bypass line after done leaking the volume. Replaced the copper gasket and then proceeded to screw it on while maintaining a circular path to ensure equal pressure on the gasket. BEWARE THAT REUSING SILVER PLATED SCREWS HAS A HIGH CHANCE OF STRIPPING THE SCREW AND WILL RESULT IN A LOT OF WORK TO GET THEM OFF. IT IS RECOMMENDED TO USE NEW SILVER SCREWS. HOWEVER WE HAVE NONE LEFT SO DO NOT TRY TO REUSE ANY SCREWS UNTIL WE HAVE SPARES. We were able to use the remaining two spare screws to tighten the flange to a point where it will not tighten anymore.

Then the lid was removed in order to inspect the inside of the chamber and the Viton O-Ring. The chamber had no physical damage and the viton had some visual damage that may correlate to the failure observed during bake 3. Note that some metal chips were found inside of the o-ring groove and needed to be removed. We changed out the o-ring for a new one and placed the old one inside of an anti static bag labeled "Viton O-Ring". Put the lid back on after inspecting for damage and put the bolts on hand tightened. Started to pump down again by turning on the scroll pump first until full range gauge 1 read below 1 torr and then began to turbo pump. The turbo pump was running for 1.5 hours until it plateaued around 3e-4 torr. We then realized the bolts on the lid needed to be tightened more with a wrench. After further tightening the pressure quickly dropped to 6e-6 torr. In the future the bolts should be tightened with a wrench from the begining.

Then proceeded to Helium leak test every weld, flange, and valve. Two of the flanges needed a little more tightening such as the 2 6" flanges. Other than that the only noticeable leak was from the flange just fixed today, however the leak is 10 times less than how it was yesterday and will most likely not hold the chamber back from reaching low 10e-8 torr pressures.

Entry  Fri Aug 11 10:57:20 2023, Celeste, Update, TCS, 8/11/23 Simulation Progress Simulation_Progress__1_32nd_Model_(1).pdf
 
Entry  Thu Aug 10 18:32:39 2023, Aiden, Update, VAC, VAC System Heating Update IMG_4588.jpg

[Dr. Richardson, Aiden]

DO NOT TOUCH ANY VALVES ON THE CHAMBER. THERE IS A PRESSURE DIFFERENTIAL BETWEEN THE RGA LINE, TURBO PUMP LINE AND THE MAIN VOLUME. THE TURBO PUMP WILL BE DESTROYED IF OPENED.

Closed the valves to the turbo pump line and RGA line. Turned the turbo pump back on and saw that the pressure in the RGA Line and Turbo pump line was going down so there was no large leak within that line or with the valves as the main body pressure stayed constant. Then raised the pressure of the main body of the chamber as we suspect the viton o-ring has failed and needs to be changed. The bolts to the lid of the chamber were also removed but the lid was left on.

Then performed a helium leak test on the section of the system that was under vacuum. We found two flanges that had small but significant leaks compared to the others in the lines. The flange connecting the full range gauge to the cross and the flange connecting the stainless steel tube to the valve under the cross. These showed large spikes when sprayed with helium and were then tightened to hopefully fix it. After tightening, the flange under the full range gauge was fixed as the bolts were pretty loose and tightening reduced any spike seen on leak test. The other flange on the SS tube could not be fixed with tightening and it still shows signs of helium leaking through. This flange will need to have its gasket changed to fix this leak. Then left the system where it is in the picture for further changes tomorrow August 11. Again, DO NOT TOUCH THE VALVES ON THE RGA LINE AND TURBO PUMP LINE AS THERE IS A PRESSURE DIFFERENTIAL AND IT WILL DESTROY THE TURBO PUMP IF OPENED.

Note: We also found that the pump under the table had flipped the breaker and needed to be turned back on. This may be something to look into.

Entry  Thu Aug 10 14:36:00 2023, Aiden, Update, VAC, VAC System Heating Update 
Came in to install one of the Full range gauges. Checked the temperature first of the cross and it was reading 30 C. After installing the gauge above the RGA line the controller was reading 2E-1 torr. Installed the other full range gauge to confirm this and it also read that pressure. There may be a leak so I will let it sit for a bit and then perform a Helium leak test.
    Reply  Thu Aug 10 15:10:12 2023, Jon, Update, VAC, VAC System Heating Update 
I shut down the turbo pump since this is evidently a large leak. We CANNOT turn on the RGA for leak checking with the pressure above 1E-5 Torr. I think we will have to manually inspect it. The most likely cause would be that the Viton seal around the lid overheated and failed.

Quote:
Came in to install one of the Full range gauges. Checked the temperature first of the cross and it was reading 30 C. After installing the gauge above the RGA line the controller was reading 2E-1 torr. Installed the other full range gauge to confirm this and it also read that pressure. There may be a leak so I will let it sit for a bit and then perform a Helium leak test.

Entry  Thu Aug 10 14:13:38 2023, Celeste, Update, TCS, 8/10/23, Simulation Graphical Progress Simulation_Progress__8_10_23.pdf
 
Entry  Wed Aug 9 17:35:26 2023, Shane, Update, CDS, Binary output chassis finished IMG_8685.jpegIMG_8686.jpeg
Finished the internal wiring for the binary output chassis today, which completes its assembly. Also secured ribbon cables and chassis lid with their respective screws. Note: one of the spade lugs' internal metal piece is a little loose and had to be reinserted after falling out once. Seemed secure after this, and I checked continuity on everything and it was all good.
Entry  Wed Aug 9 11:32:56 2023, Jon, Infrastructure, General, New power cables IMG_0299.jpg

I delivered new NEMA 5-15 (120V / 15 A) power cables to the lab for the following items:

  • WS2 (cleanroom) cart - 10ft cable
  • Electronics workbench overhead LED - 10ft cable
  • Both PI heater controller sets - (2) 6ft cables

I installed the new cables on the WS2 cart and the workbench myself, and left the two 6ft cables (as pictured below) for Aiden to install on the PID controllers after the current bake is finished.

Entry  Tue Aug 8 17:03:22 2023, Shane, Jon, Update, CDS, Binary input chassis finished IMG_8681.jpeg
Finished assembly of the binary input chassis today, including DC on/off switch and LED installation. external cable assemblies still needed, but internal work done.
Entry  Tue Aug 8 16:47:11 2023, Sophia, Update, Scripts/Programs, Update on Dynamic CSD and PSD Plots Screen_Recording_2023-08-08_at_7.42.30_PM.movScreenshot_2023-08-08_at_2.22.50_PM.pngScreenshot_2023-08-08_at_5.16.08_PM.png
We have fixed our rapid plotting error, and realized that this has not been affecting our data intake! Below is a video of the code progressing, alongside grabbed images of the raw data. The data is now continuous, and performs as we expect. Next, I plan to add a widget which will dynamically show the peak values instead of them just being printed in the terminal after each iteration. (Ignore the red box-- it was from me struggling with a now fixed issue).
Entry  Tue Aug 8 15:31:26 2023, Aiden, Update, VAC, VAC Heating System Update 10x

Vacuum Chamber equilibrium temperature for bake 3 are 126 C and 88 C for the chamber wall and turbo pump flange respectively. There were reached with the PID controllers both being set to 150 C.

Also noticed some discoloration around the port insulation. It could be burned from being exposed to the heater tape directly without insulation or it could be that the insulation, which looks much different, is depositing something around the ports.

The turbo pump overheated and the heating tape had to be turned off in order to get the pump back online. It was unusually hot at 52 C. Hottest it got in bake 2 was 38 C.

Entry  Mon Aug 7 15:36:18 2023, Sophia, Update, Scripts/Programs, Update on Laser Noise Data Collection and Analysis: Dynamic CSD and PSD Plots 7x
Today I was able to fix the red pitaya's plotting problem, and get my code to recognize driving frequencies from the function generator to within a 0.5 Hz estimation. The sinusoidal plots I have included are from sending a 1 Hz signal into the red pitaya to see the signal in real time. This allowed me to see exactly where the system was messing up, and fix from the ground up. Once I had that working, I began to test sending in frequencies in the range that my PSD/CSD code could observe and I was able to identify each driving frequency within 0.5 Hz. My code was able to correctly identify a 500 Hz signal, while other analyzed frequencies in the observable range have fallen lower than the sent in frequency by a less than 0.5 Hz. I believe this issue comes from the strange speed that the red pitaya is still acquiring data, even with my fixing it to now observe a continuous signal.
Entry  Mon Aug 7 13:58:46 2023, shane, Update, CDS, internal power supply cables done for AI chassis IMG_8674.jpeg
Finished assembling and installing the aLigo chassis internal power supply cables in the anti-imaging chassis today. Tested for continuity and everything looked good. Chassis lid still secured with two temporary screws because I'm not sure what the correct size is.
Entry  Fri Aug 4 15:21:33 2023, Aiden, Update, VAC, VAC System Heating Update 
Checked on Bake 3 today and the temperature sensors read 126 C and 91 C for the chamber barrel and turbo pump flange respectively. These were reached while the PID controllers were set to 150 C.
Entry  Thu Aug 3 18:03:42 2023, Shane, Jon, Update, CDS, Anti-Aliasing chassis complete IMG_8544.jpeg
We finished installing the internal power supply cables in the anti-aliasing chassis today, which concludes its assembly. Work on AI, BI, BO chassis still underway.
Entry  Thu Aug 3 17:47:51 2023, Aiden, Update, VAC, VAC Heating System Update 

Did some further testing to determine if it was within reason to increase the temperature of the chamber. I used a thermometer and pulled back some insulation to test many points on the chamber. Mainly focused on the barrel and the bottom lid of the chamber to see if it was possible to increase the temperature of just the PID controller that is powering the bottom half of the chamber.

Found that the barrel of the chamber seems to be hotter than what the sensor is saying, 125 C. Found many points on the barrel that reached 140 C. I believe this is because the sensor is taped on top of the heater tape rather than in between the aluminum and the heater tape.

Also measured many points on the bottom lid as it has the same configuration the top did before it damaged the insulation. It seemed to be consistently at 150 C but I was able to find a couple points that were hotter around 160 C. These hotter spots were most likely the heater folds. There is not much we can do about this as removing the insulation for fixing would required a very invasive procedure to do it safely.

Then moved to the stainless steel tube that connects the RGA and Turbo pump lines. This tube was around 150 C but many points on it were hotter around 160 C. Before another bake I think some of the tape around the tube may need to be pulled back and relocated to avoid damaging insulation while also providing more heat to the main body of the chamber.

Measured a couple more points on the cross that connects the RGA and the full range gauge and found it to be around 130-140 C which means this section could be hotter as the electronics of the full range gauge can reach 150 C.

Over all I believe that the chamber temperature should not be increased in its current state as the bottom lid is a concern with what happened with the top in the second bake. Some optimizations could be made for a fourth bake however. Moving the temperature sensors to be between the heater tape and chamber. Pulling some of the heater tape from the stainless steel tube and relocating it to the main body of the chamber. Moving the PID temperature sensor on the tube to be on the bottom lid or another hotter spot. These are some changes I would make for a fourth bake but maybe this bake could be the last with how the second bake went.

Entry  Thu Aug 3 16:00:25 2023, Aiden, Update, VAC, VAC System Heating Update 
Check on the temperature of the bake today to see the equilibrium temperatures. With both of the PID controllers set to 150 C, the temperature sensors for the wall of the chamber and the flange in front of the turbo pump read: 125 C and 90 C respectively. At these temperatures the bake would need to last at least a week unless the temperature were to be increased.
Entry  Wed Aug 2 17:02:38 2023, Aiden, Update, VAC, VAC System Heating Update 

Moved the temperature sensor on the PID controller to one of the switch backs on the lid.

Also started the next bake with both PID controllers set to 150 degC. When leaving the temperature sensors above the chamber read 119 C and 83 C. These sensors are on the chamber wall and flange in front of the turbo pump respectively.

Entry  Tue Aug 1 16:22:35 2023, Celeste, Update, TCS, Graphical Updates to HOM RH Modification, Tuesday 8/1 HOM_RH_Simulation_Progress_80123.pdf
Slides 20-33 are newly added (data/graphs from parameter sweep feature-1/8th heater unit length varied from 10% of original to 100% of original).
Entry  Tue Aug 1 15:44:31 2023, Sophia, Update, Scripts/Programs, Update on Laser Noise Data Collection and Analysis: Dynamic CSD and PSD Plots 6x
We have identified two problems facing the intensity noise calculations, which we are working to solve. The first of these problems, is that the red pitaya appears to be taking data approximately 4 times faster than we would expect from the decimation rate based on how quickly it runs. To see if this was affecting our data, we plugged the red pitaya into a function generator. We found that my code is able to identify the driving frequency, but consistently gives predictions that are roughly 7% greater than we expect. When we drive at 100 Hz, the plot says the peak is at 107 Hz, when driven at 400 Hz, we see between 422-427 Hz, etc. While this implies that the red pitaya is not taking data at a faster rate than we would expect (if it did we would anticipate a lower than expected frequency, by a factor of roughly 4), it does imply some intrinsic issue with either the red pitaya or with the code. To fix this, I am going to use my code on artificially generated signals and see if we still observe these issues.
Entry  Tue Aug 1 12:48:41 2023, Aiden, Update, Cleanroom, Pre Filter Change IMG_4564.jpgIMG_4563.jpgIMG_4562.jpg

Changed the pre filter inside of the 3 stage HEPA system next to the soldering station. It was rather dirty and I have attached images with a clean filter on the left and the used one on the right. I reset the pre filter age on the system. I tried to see if I could tell if the HEPA filter was dirty but I could not see it. I did not reset the age of the HEPA or UV stations. They are currently 378 days old.

Entry  Tue Aug 1 12:10:03 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update bake2_230801_ArC.pngbake2_230801_ArO.pngbake2_230801_Closed_Open.png

Dr. Richardson and I took off the insulation on the lid again to add more insulation in-between the heater tape folds in addition to what was added on top of the tape after discovering discoloration. Also cleaned the lid with IPA wipes.

Also took more RGA data, one with the leak closed and one with the leak open. The graphs below this show that the SNR is improving with the ratio now looking to be around 3. The chamber is still too dirty to be commissioned and we will need to be baked again soon.

Plugged the temperature sensor back in after getting another extension cord. Removed the electronics box for the RGA as well as the full range gauge above the RGA line.

Entry  Mon Jul 31 19:27:30 2023, Sophia, Update, Scripts/Programs, Update on Laser Noise Data Collection and Analysis: Dynamic CSD and PSD Plots Screenshot_2023-07-31_at_10.18.44_PM.pngScreen_Recording_2023-07-31_at_10.16.31_PM.movScreen_Recording_2023-07-31_at_10.19.55_PM.movScreenshot_2023-07-31_at_10.21.44_PM.pngScreenshot_2023-07-31_at_10.26.34_PM.png
An update on the CSD/PSD code: The code is now taking a dynamic average of the points, and that has significantly reduced the noise that we were reading and the issues I was having with the lines in the plots. The graph for the CSD is still putting up a fight though, and amassing many lines that do not appear when just scatter plotted. I plan to fix that tomorrow, alongside inserting my own generated signal into the data. I have plotted the coherence alongside these graphs (as shown in the first screen recording and in one of the images), and it is significantly less than 1-- starting at or below 10^(-1). As a note, I am unsure of why the raw data looks like this-- the laser goes through periods of extreme noise and I think this data was taken during one of them.
Entry  Mon Jul 31 12:39:01 2023, Shane, Update, Electronics, LED cable assemblies installed  IMG_8514.jpegIMG_8516.jpeg
Today I put together the two LED cable assemblies for the CyMAC and mounted them in the anti-aliasing and anti-imaging chassis.
Entry  Fri Jul 28 18:03:07 2023, Pamella, Update, FLIR, Final plot - FLIR 29Combined_HighTemp_Gaussian_Plot.jpg3Combined_HighTemp_Gaussian_Plot.jpgcalibration_plot(2).png
[Pamella]
    1. I was able to plot the final result with the data to the heater. I attached below the "3Combined_HighTemp_Gaussian_Plot." in this plot we can see better behavior on the Gaussian compared to the plot in ELOG 169, I was using the same data but with a different approach. On the ELOG 169, we have the center point isolated data and this new plot is the temperature more than 70 C isolated because we have a very good heater temperature distinguish do background. For the all data I got I was using a power current of 0.20A. To get the data I waited for 30 minutes until the heater became stable and after that, I started to take snaps, I took more than one snap for each one different 6 positions on the screen, and We can see the positions on ELOG 167.
    2. Also I attached the calibration plot ("calibration_plot") between the measurements with the FLIR camera and thermocouple and we can see looks good if we compare the final plot.
    3. For better analyses I attached a plot of the calibration line on the Gaussian plot.
    4. To do: I will finish the final report.
Entry  Fri Jul 28 17:45:45 2023, Celeste, Update, TCS, Graphical Updates to HOM RH Modification, Friday 7/28 HOM_RH_Simulation_Progress.pdf
Updated 1/8th Heater simulation modification graphs. Slides 7, 10, 16-19 are new additions.
Entry  Fri Jul 28 13:46:17 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update bake2_230720_ArC.pngbake2_230720_ArO.pngbake2_230728_Closed_Open.pngbake2_230728_Open_Open.png

Took some more data to look at the HC count. Initial data was from leaving the Argon leak closed and then left it open for 15 minutes and then took data for the open scenario. Attached are the graphs for these where attachment 1 is the closed scenario and attachment 2 is the open scenario.

From these graphs it looks like the signal-noise ratio of our calibration line is poor with the ratio between these two being 1.3. This means that the calibrated leak is barely being detected over the background. This should improve with more baking and pumping. I have also now attached overlayed graphs comparing the chamber when the leak is closed versus when it is open. As well as one comparing the chamber right after the bake versus the most recent data both with the leak open.

Entry  Fri Jul 28 13:39:39 2023, shane, Update, Cleanroom, full 5 zone cleanroom particle count download.png
Here's the 5 zone cleanroom measurement from today.
Entry  Fri Jul 28 13:07:39 2023, Shane, Aiden , Update, Cleanroom, cleanroom cleaning and particle count 6x
[Aiden, Shane]

cleaning cleanroom and particle count

  • 11:08 am: started particle count
    • zone 3:
      • 0.3 u: 4198
      • 0.5 u: 1080
      • 1.0 u: 581
    • zone 4:
      • 0.3 u: 1247
      • 0.5 u: 623
      • 1.0 u: 415
  • 11:24 am: break for removal of vac chamber insulation (pictures attached), with counts before removal as seen above, and counts after removal/replacement for zone 3 as follows:
    • zone 3:
      • 0.3 u: 2993
      • 0.5 u: 415
      • 1.0 u: 207
  • 12:02 pm: began surface check and wipedown
  • 12:13 pm: started vacuuming the floor
  • 12:25 pm: finished vacuuming the floor
  • 12:26 pm: started mopping the floor
  • 12:32 pm: finished mopping the floor
  • 12:32 pm: started cleaning the buckets
  • 12:37 pm: started mopping with IPA wipes
  • 12:43 pm: finished mopping with IPA wipes
  • 12:45 pm: changed sticky floor mats
  • 12:47 pm: started particle count
    • zone 3:
      • 0.3 u: 2951
      • 0.5 u: 290
      • 1.0 u: 41
    • zone 4:
      • 0.3 u: 290
      • 0.5 u: 0
      • 1.0 u: 0
Entry  Thu Jul 27 14:46:55 2023, Shane, Jon, Update, Electronics, AA chassis DC on/off switch assembled 
Made the first DC on/off switch assembly today and installed in anti-aliasing chassis. Second switch assembly to be completed later.
Entry  Thu Jul 27 14:11:42 2023, Sophia, Update, Scripts/Programs, Update on Laser Noise Data Collection and Analysis: Dynamic CSD and PSD Plots Screen_Recording_2023-07-27_at_5.08.25_PM.mov
Here's a screen recording of the dynamic raw data and PSD/CSD plots as they are now. Will begin working on implementing a code to generate the statistical estimator for the CSD uncertainty now. (Will talk to Tyler more about whether I can get the lines to happen or not)
Entry  Thu Jul 27 11:28:36 2023, Sophia , Update, Scripts/Programs, Update on Laser Noise Data Collection and Analysis: Dynamic CSD and PSD Plots Screenshot_2023-07-26_at_3.02.05_PM.pngScreenshot_2023-07-26_at_1.38.47_PM.pngScreenshot_2023-07-27_at_1.36.24_PM.pngScreenshot_2023-07-27_at_1.33.01_PM.png
This week I have successfully been able to implement our dynamic CSD and PSD plotting code, but along the way I encountered a few challenges which I will outline in this elog post. Challenges: 1. Once I was able to plot the data through time, I produced a graph of the raw data (shown below in the top to images) which showed pulsed data instead of a continuous stream. On Tuesday (26th of July) Tyler and I fixed this issue, realizing that calling the starting the trigger in the red pitaya was the issue. When I commented that line of code out, it immediately started plotting continuously. 2. When that issue was solved, We then started having problems with the automatically generated lines in the python program which would double back on each new iteration. I am still dealing with this issue, because the line likes to follow the progression of the data intake instead of through the plot. Currently, I am trying to plot the data as a scatter plot and then add the line as this might make it care only about the data's distribution instead of the order of the points in the list, but I am still unsure. I might try out np.sort (or some equivalent to sort the entire data set before plotting) as well.
Entry  Thu Jul 27 10:18:43 2023, Celeste, Update, TCS, Graphical Updates to HOM RH Modification HOM_RH_1_8_Unit_Modification_Graphs.pdf
Attached are updated graphs of the irradiance distribution from the 1/8th ring heater units (extruded and reduced in length).
Entry  Tue Jul 25 15:35:14 2023, Shane, Update, Electronics, More chassis moved IMG_8409.HEIC
Finished basic assembly of binary input and output chassis today, and moved one to top shelf of work bench. The other is in corner of work bench (image attached). They are delicate, so please do not move them or place anything on top of them.
Entry  Mon Jul 24 16:19:29 2023, Shane, Jon, Update, Electronics, Chassis semi-assembled and moved IMG_8386.pdf
Began assembly on AA and AI chassis today, moved them both to top work bench shelf (image attached). They are delicate so please do not disturb them or put anything on top of them.
Entry  Mon Jul 24 14:55:53 2023, Jon, Update, VAC, Removed extension power cable 
I removed the extension cable that was powering the leftmost heater controller, since there is no bake currently happening. It is currently powering the LED over the electronics bench, and can be removed if needed. I will be ordering more extension cords to permanentize our setups.
Entry  Thu Jul 20 21:00:23 2023, Pamella, Update, FLIR, Data plot FLIR and updates about the black body AcquisitionImage(Jul-20-2023_13_09).jpgAcquisitionImage(Jul-20-2023_13_15).jpgAcquisitionImage(Jul-20-2023_13_33).jpgAcquisitionData-480(Jul-20-2023_SIsolated_Plot.pngGauss.plot-2.jpeg
[Pamella]
  • Today I got more data to plot the Gaussian. So I took more snaps in each position for the six different spots than we be using to have a better calibration of the FLIR collected data. I attached the new plot below. Also, I did the same plot for each region as on the Elog 167 but I have more than 20 pics because I was using a big number of data so I just attached one example below.
  • To access the Elog, click here.

  • Also I think we have some real (non-ideal) heat diffusion by the screen and not noise like Dr. Richardson suggested. I was testing today and we can see the first pic before the start heater source turns on, the second pic is at 120.2 C (0.31A) with the heater on and the last pic is after the heater source cooled back down to room temperature. Just in the second pic, we have a strong spot on the top, so it looks like a non-ideal diffusion.
Entry  Thu Jul 20 18:03:19 2023, Aiden, Update, VAC, Vacuum Chamber Baking Update bake2_230720.png

Took another set of RGA data after the second bake has cooled down to 27 degC.

Just by visual comparison to the other graphs, the HC levels of the chamber has gone down further. I will soon overlay the data for an easier comparison.

I also reinstalled the full range gauge above the RGA line. It is still adjusting itself downwards so I will have to check again to get an accurate measurement of the pressure.

Entry  Wed Jul 19 19:10:31 2023, Pamella, Update, FLIR, Data plot FLIR and updates. 8x
[Pamella]
  • Today I was able to plot a graph for the isolation point on the center of the heater. I got data from six different positions on the screen (I shifted the all coordinates). I extracted the data for the center point and plot the Gaussian with this extracted data for temperature. I attached the all plots below
  • Also I took a snap using the black wall and with the heater at 120.1 C (0.30 A) try to have less noise but we can see this is not very good. At this temperature, we have noise on the top and I don't understand why because the heater is not in this location. I attached a snap below.
Entry  Wed Jul 19 14:39:19 2023, Pamella, Shane, Aiden, Update, Cleanroom, cleaning and particle count 
[Pamella, Shane, Aiden]

cleaning cleanroom and particle count

  • 1:10 pm: started particle count
    • Zone 3:
        0.3 u: 2535
        0.5 u: 207
        1.0 u: 41
    • Zone 4:
        0.3 u: 789
        0.5 u: 41
        1.0 u: 0
  • 1:30 pm: began surface check and wipedown
  • 1:41 pm: started vacuuming the floor
  • 1:55 pm: finished vacuuming the floor
  • 1:57 pm: started mopping the floor
  • 2:01 pm: finished mopping the floor
  • 2:02 pm: started cleaning the buckets
  • 2:08 pm: started mopping with IPA wipes
  • 2:17 pm: finished mopping with IPA wipes
  • 2:18 pm: changed sticky floor mats
  • 2:19 pm: started particle count
    • Zone 3:
        0.3 u: 3990
        0.5 u: 1080
        1.0 u: 374
    • Zone 4:
        0.3 u: 540
        0.5 u: 207
        1.0 u: 0
Entry  Sat Jul 8 14:26:17 2023, Pamella, Update, FLIR, Data with the new configuration without the mask and reflector. 6x
[Pamella] I started collecting data by moving the camera FLIR and covering all six positions on the screen (2x3). I was looking and taking snaps for more than one hour and a half. I'll repeat this one more time to make sure we have enough data to do analysis. I attached snap data below. This images is processed on python code.
    Reply  Tue Jul 18 16:35:06 2023, Pamella, Update, FLIR, Plot-Data with the new configuration without the mask and reflector. Gauss.plot.jpeg
[Pamella]
  • I was able to plot the first graph for a result between the six different positions on the screen, for now we can see the behavior of the heater temperature in a Gaussian graph with combination data between the six files.
  • To do: Tyler gave me some ideas today to improve the plot. So I'm going to change the code to have insulation on the values for just the heater ("insulation") and I'm going to plot after this insulation data as well I'm going to get more data and compare with more data for the same position.
  • I was using the data than I got last week and I shared on Elog (151) and we can see on this quote

Quote:
[Pamella] I started collecting data by moving the camera FLIR and covering all six positions on the screen (2x3). I was looking and taking snaps for more than one hour and a half. I'll repeat this one more time to make sure we have enough data to do analysis. I attached snap data below. This images is processed on python code.

 

Entry  Mon Jul 17 11:46:24 2023, Pamella, Update, FLIR, Thermocouple plot. calibration_plot-2.jpegcalibration_plot-3.jpeg
[Pamella]
  • I collected data to plot a calibration with the heater. I took measurements with current and temperature (the thermocouple - thermometer) to compare with the FLIR measurements.
  • I made a plot with this data and we can see how temperature vs current behaves. Note: This data I measured manually.
    Reply  Tue Jul 18 16:12:27 2023, Pamella, Update, FLIR, Thermocouple plot. Comp.plot.jpeg
  • I noticed that these measurements have some issues with the weather on different days. We can see in the photo attached below how different the temperatures are on different days, I took the data with the same procedure every day, but we can see the differences between them.
  • To Do: I will do a new data collection using FLIR and thermocouple at the same time to plot comparison between both.

Quote:
[Pamella]
  • I collected data to plot a calibration with the heater. I took measurements with current and temperature (the thermocouple - thermometer) to compare with the FLIR measurements.
  • I made a plot with this data and we can see how temperature vs current behaves. Note: This data I measured manually.

 

Entry  Tue Jul 18 16:04:26 2023, Pamella, Update, FLIR, Setup FLIR with black wall (black body) AcquisitionImage(Jul-18-2023_15_24).jpgIMG_8721.jpegIMG_8722.jpeg
[Pamella]
  • Today I tried get data the heater with the black screen but doesn't looks possible have just one "energy" point straight to FLIR camera. Tyler and I tried different current and temperatures but keep very bad data. I attached a snap below.
  • I attached a photo about the new setup below. The FLIR is in the most close point possible/safety with the heater. The heater is very close to the black wall but is not touch the screen so is safety.
Entry  Tue Jul 18 14:13:46 2023, Sophia , Update, Scripts/Programs, Update on Laser Noise Data Collection and Analysis 6x
We [Sophia and Tyler] have found a code which will partition our data and generate PSD's and CSD's automatically. We are now in the stage of writing this into a dynamic code, which so far has been fast-paced because of the framework we have built for it over the past few weeks. Something to note is that we have found, especially over long periods of time, the laser goes through periods of extreme noise and the signals often cross from where we set them at some point throughout our data collection. We have made the assumption that this is something to do with the laser itself, and not our setup or surrounding space because of both the times that these noise/intensity spikes took place and the duration of the spikes (1.5-2.5 hours). To try and correct for this, we have been "cutting" the noise, and just looking at sections which don't include these big fluctuations. An example of the "noise cut data" is shown in the graph titled "Signals Over Time 7-18-23 Noise Cut Data" and all of the PSD/CSD graphs have been made using only these "noise cut" regions.
Entry  Mon Jul 17 14:01:41 2023, Aiden, Update, VAC, VAC System Heating Update IMG_4535.jpg

The insulation on the lid of the vacuum chamber has some discoloration and it may be wise to place a sensor closer to this spot in future bakes.

Entry  Mon Jul 17 13:50:41 2023, Aiden, Update, VAC, VAC System Heating Update 

Started to cool down the chamber today. Final temperature readings of the chamber were 146C and 91C for the body and cross respectively.

Entry  Sun Jul 16 15:21:56 2023, Pamella, Update, General, General update about some problems in the lab. IMG_8637.jpgIMG_8633.jpgIMG_8631.jpg
[Pamella]
    General information about the lab facility.
    1. Changed sticky floor mats, because close to entrance the cleanroom, both sticky floor had a many died ants on top.
    2. The light on top of the internet cable bridge is burned out.. I just saw this today but I am not sure if was like this before.
    3. The ant bait traps seem very efficient and right now only a few ants are running around in the lab, most are dead in the bait traps, so probably in a day or two we can change those bait traps.
Entry  Fri Jul 14 16:49:42 2023, Pamella, Update, FLIR, New bridge and calibration data IMG_8606.jpeg
[Pamella]
    Aiden 3D printed a new bridge for the heater and I installed the new bridge yesterday.
    I started collecting data to plot a calibration with the heater. I'm doing measurements with current and the thermocouple (thermometer) to compare with FLIR measurements and have a good calibration.
Entry  Fri Jul 14 14:37:25 2023, Aiden, Update, VAC, VAC System Heating Update 

Checked on the vacuum system and it looks like it will either need to be increased in temperature or baked for a longer time. The main body is at 146C while the cross is at 91C.

Entry  Thu Jul 13 15:31:21 2023, Jon, Update, General, Ant traps placed around lab 

In response to reports that ants have been observed in the lab, I placed five ant bait traps around the room today. Each is sitting on the floor on top of a piece of aluminum foil, in areas unlikely to be inadvertently stepped on. They contain liquid which will spill out if picked up, so please take care not to disturb them.

    Reply  Thu Jul 13 16:59:03 2023, Jon, Update, General, Ant traps placed around lab 

Update: After seeing the strong response to the first set, I redistributed them to the hottest spots and added one more trap.

Quote:

In response to reports that ants have been observed in the lab, I placed five ant bait traps around the room today. Each is sitting on the floor on top of a piece of aluminum foil, in areas unlikely to be inadvertently stepped on. They contain liquid which will spill out if picked up, so please take care not to disturb them.

 

Entry  Thu Jul 13 14:56:43 2023, Aiden, Update, VAC, VAC System Heating Update 

Checked on the vacuum system today to change the PID controls back to their default values in order to try and get the temperature of the cross in front of the turbo pump higher. Currently it is sitting at 90 degC before changing the controls. While the main body is at 146 degC.

Will update again tomorrow on new equilibrium with the default PID settings.

Entry  Mon Jul 10 13:23:23 2023, Aiden, Update, VAC, VAC System Heating Update 

Checked on the system today.

The flange on the turbo pump has reached an equilibrium temperature of 87 degC when set at 150 degC. While the main body of the chamber has reached an equilibrium temperature of 142 degC.

Entry  Fri Jul 7 15:11:39 2023, Aiden, Update, VAC, VAC System Heating Update 

The temperature of the flange connecting to the turbo pump after reaching equilibrium is 74 degC. This means that it is safe to proceed with raising the temperature from 120 degC to 150 degC.

Raised the set temperature of the chamber from 120 degC to 150 degC in 15 deg steps.

Entry  Thu Jul 6 18:03:19 2023, Pamella, Update, FLIR, FLIR project - New configuration IMG_8193.jpegIMG_8183.jpegAcquisitionImage(Jul-06-2023_17_18)_(1).jpgregion_temperature1.jpg
[Pamella]
    Cao suggested using the project without the reflector and mask because in this case we probably got good images around the screen. So I started this yesterday and today I started to get some data to see the stabilization position and check how the parameters fluctuated. I was looking and taking snaps for an hour and a half. I'll repeat this one more time to make sure we have enough data to do analysis.
    To do: The next step is to start collecting data by moving the camera FLIR and covering all six positions on the screen (2x3). Also Aiden is on hand to help and is going to make a new 3D print bridge to have good heater support.
    I attached a image for the new configuration below and a snap data.
Entry  Thu Jul 6 16:16:03 2023, Aiden, Summary, VAC, Vacuum Chamber Baking Update 

Pressure Measured Before Removing Gauge 2.31 E-7 Torr.

Went in and turned on the heating tape in increments of 30 degC until 120 degC was reached. I will let it equilibrate over night and then asses whether or not the chamber can be raised to 150 degC without having the flange to the turbo pump reach over 120 degC as it is not recommended for that flange to be any hotter.

If it can safely be raised to 150 degC, then only 2 days of baking is necessary. If 120 degC is the bake temperature, a week will be needed.

Entry  Thu Jul 6 13:34:48 2023, Pamella, Shane, Julian, Aiden, Update, Cleanroom, cleaning and particle count 
[Pamella, Julian, Aiden, and Shane]

    cleaning cleanroom and particle count

  • 12:00 pm: started particle count
    • Zone 3:
        0.3 u: 2826
        0.5 u: 457
        1.0 u: 166
    • Zone 4:
        0.3 u: 457
        0.5 u: 83
        1.0 u: 41
  • 12:17 pm: began surface check and wipedown. NOTE: found a few ants crawling up the metal table frame and on the desk
  • 12:29 pm: started vacuuming the floor
  • 12:45 pm: Finished vacuuming the floor
  • 12:46 pm: Started mopping the floor
  • 12:52 pm: Finished mopping the floor
  • 12:55 pm: Started cleaning the buckets
  • 1:02 pm: Started mopping with IPA wipes
  • 1:11 pm: Finished mopping with IPA wipes
  • 1:12 pm: Changed sticky floor mats
  • 1:14 pm: started particle count
    • Zone 3:
        0.3 u: 2577
        0.5 u: 457
        1.0 u: 166
    • Zone 4:
        0.3 u: 457
        0.5 u: 41
        1.0 u: 0
Entry  Wed Jul 5 16:02:12 2023, Aiden, Update, Clean &amp; Bake, Clean and Bake batch 14 Bagging 
Bagged and Tagged the 2.75" copper gaskets from Batch 14 and placed them into the clean room on the work bench.
Entry  Wed Jul 5 15:46:47 2023, Aiden, Cao, Infrastructure, VAC, Vacuum Chamber Baking Update bake1_230705.png

Cao and Aiden put the RGA back on to the chamber and measured the outgassing rate after the chamber has cooled down from its first bake. The figure attached shows the RGA measurements with the Argon leak open.

Also put the Full Range Gauge #2 [RGA line] back onto the system to measure the pressure and got a reading of 2.78 E-7 Torr. We believe it is actually lower as the chamber temp is still at 28 degC rather than the 24 it was previously measured at. The gauge also may have needed more time to equilibrate.

Entry  Tue Jul 4 15:35:38 2023, Pamella, Update, FLIR, FLIR - reflexion problem AcquisitionImage(Jul-03-2023_14_29).jpgAcquisitionImage(Jul-03-2023_14_31).jpgAcquisitionImage(Jul-03-2023_14_49).jpgCaderno_sem_título_(26)-2.jpgparabol1.print.png
[Pamella] I was testing all the positions we need to cover when moving the FLIR camera or the reflector. I tried to find out more about the problem so I tested the position without the mask, just with the old bridge and I got the same problems, in the middle of the screen we have a very good image but if we move we have the visualization problem and we don't see the reflection very well (intensity, emissivity) in FLIR. For this test I used very low current (0.04 A) for keep everything safety. I also think that problem is not in the focal point of the reflector because we can see very well in the center of the screen, but maybe it is because in the parabolic reflector the reflection in the focal point is "extremely" straight, so for you to see the reflection in this point you need keep close to the middle of the screen, to see around the reflector, at the extremes, we need to change the position for the cable or the light to "change" how the flashes of light reflect and thus achieve exactly the position on the camera. It is something like the sketch/ photo attached below.
Entry  Mon Jul 3 18:38:13 2023, Pamella, Update, FLIR, FLIR project Region.jpgtriangular_region_temperature-2.jpgheatmap.jpgisolation1-4.jpg
[Pamella]
  • I was able to work on the python code to do analysis on the FLIR-Reflector data.
  • I could plot images of total area (Tyler help me on that) with csv file and also could have isolation area for triangles. I have attached examples below. Just for now the images are of different data, so there are some differences in the shapes.
  • I'm working on getting a complete analysis code to work with the different positions of the triangles and to be able to do out the statistical analysis.
  • Also we keeping have problem to get good data if when we move the camera or the reflector on horizontal or vertical position. I am working a some ideas for that.
Entry  Mon Jul 3 16:26:21 2023, Cao, Infrastructure, DAQ, Access and control Red Pitaya remotely and run it on local machine 
[Cao]

To access and control the Red Pitaya using Python locally on a machine within the local network, one should follow these steps:

  1. Start the SCPI server. This is achieved by first log onto the Red Piatay page

    rp-xxxxxx.local/ 
  2. Go to Development >> SCPI server and turn the server on. (Note : The server is currently running)
  3. Communication with Red Piataya is done through PyVista, install PyVista with:
     sudo pip3 install pyvisa pyvisa-py 
    This has been installed on Chimay. Ensure that you have pip3 install, if not, you can install it using:
     sudo apt-install python3 pip 
  4. To start talking to the RedPitaya, ensure you have the scipt
     redpitaya_scpi.py 
    in your local folder. This is the standard class that you will import to your code to establish connection with the Red Pitaya. This code can be found in directory
     ~/RedPiatya 
     or this link
    

Entry  Mon Jul 3 14:32:24 2023, Cao, Infrastructure, VAC, Cooling down vacuum chamber 
[Cao]

After leaving the the chamber to bake at 120 deg C from Thursday 3:41 pm. Today I started to cool the chamber down to room temperature at 11:30 am (total bake duration: 91 hours 49 minutes). Ideally, this process should be ramped down slowly, approx. 6 degree per hour. However we had no ramping function with out controller. The only method to tune this cool/ heat rate is to tune the PID parameters, which are:

  1. Pb : Proportional band, this quantity is inversely proportional to the P-gain
  2. ti : Integral time. Increasing integral time makes the output response slower to error, thus the opposite effect of increasing integration gain
  3. td : Differential time
Since the differential term doesn't contribute to rise time significantly, we neglect it for now and first change Pb and ti . The factory default settings :
  1. Pb : 50
  2. ti : 100 s
  3. td : 25 s
Initially Ichanged Pb from 50 to 200 (max) and ti to 999 s (max) but there is a large offset error. Currently, Pb and ti are sitting on the following settings:
  1. Pb : 200
  2. ti : 800 s

At this setting it takes 25-30 mins to drop 6 degrees, which is not as slow as we want but we will have to tune our PID more carefully. At the first stage, I dropped the temperature to 60 deg C. After 3 hours, we dropped the setpoint to 25 degrees and let the vacuum chamber to cool to room temperature.
Entry  Fri Jun 30 16:43:14 2023, Pamella, Update, FLIR, Updates: Small moving the FLIR camera AcquisitionImage(Jun-30-2023_16_23)_(3).jpgAcquisitionImage(Jun-30-2023_16_23)_(1)(1).jpgAcquisitionImage(Jun-30-2023_16_24).jpgAcquisitionImage(Jun-30-2023_16_22)_(1)(1).jpgAcquisitionImage(Jun-30-2023_16_22)_(1).jpg
[Pamella]
    Today, I was able to make some adjustments to the FLIR camera angle, suggested by Dr. Richardson, and we got small possible movements keeping the same pattern in the shapes of the triangles. I have attached photos below. I was able to move left and right as well as up and down and it worked in four points that I marked on the table.
    The only problem is that it only worked on a part of the screen, if I try to place it farther to the right or to the left, we are back to the same problem as yesterday.
Entry  Fri Jun 30 15:57:28 2023, Pamella, Update, FLIR, Data and python code update  isolation1-2.jpgAcquisitionImage(Jun-29-2023_18_27)_(1).jpgAcquisitionImage(Jun-29-2023_18_38).jpgAcquisitionImage(Jun-29-2023_18_39).jpg
    [Pamella]
    Updates: Problems with the emission intensity and python code.
  • Yesterday I was working on get data from FLIR reflector but unfortunately we got some problems:
    1. I realized than if I move the reflector a to left or right the screen doesn't get data very well(I attached a photo below). This is a problem because our idea is have the same type of emission every part on screen. Tyler and I worked to tried fix that but don't had success.
    2. Dr. Richardson gave me the idea to move the FLIR camera to left or right (The same happens if I move up and down) and keep the refletor on the same position every time but unfortunately we got the same problem, the screen doesn't get data very well(I attached a photo below). Now I am working to tried fix that.
  • Also I was able to work on the code to isolate the triangle shape for analyzes, I attached the image for that below.
Entry  Thu Jun 29 18:27:26 2023, Jon, Cao, Infrastructure, VAC, Vacuum bake attempt 3: success! NewInsulation.pngBypassLineInsulation.jpg
[Jon, Cao]

Summary : We resolved problems with heaters tripping power and were able to proceed with chamber baking

1. Circuit connection adjustment

After yesterday elog 137, today we resolved most of these issues. After Jon contacted Facilities, the LP3B 6 circuit was reset and the cleanroom filter & light panels resumed to work as normal.

Regarding the connection of the heaters. we made the following adjustments:

  • High-temperature controller powering lid + upper volume heater: connect to LP3B 8 circuit (clean room sides, 2 outlets)
  • High-temperature controller powering bottom + lower volume heater : connect to LP3B 4 circuit (workstation side, 2 outlets)

2. Replacement of vacuum nipple insulation

We had also received new insulation pieces from Worbo today to replace the existing insulation with the new ones (see images). These cover the 2 4" tubes (for 6" flanges ) and the 4 1.5" tubes (for 2.75" flanges). The new insulations fit perfectly on these tubes. I also placed all insulation taken off from the last elog back onto the chamber ( these are insulations for the pumps and RGA lines).

3. Baking

We started ramping up chamber temperature at 1:41 pm over the course of two hours:
  • Starting set point: 40 deg C
  • Step increase: 10 deg C up to 80 deg C, 5 deg C from 80 deg to 120 deg C
  • At each step, the temperature readouts show approx. 2.1 deg C overshooting, wait to settle back to approx 1.5 deg C overshoot before increase the set point again
We noticed some smoke emanating from flexible bypass line insulation but none from other locations that were previously smoking . We think this is because the high winding density around the bypass line for such a small volume. Adjustment for next bake: Change the location of PID controller RTD to the bypass line . For now, we remove the insulation around bypass to prevent insulation overheating and encourage convection cooling (see image)

The temperature of the chamber reached as stable 120 deg C without any power issues at 3:45 pm. I waited another 15 minutes to verify its stability and the official baking duration started at 4:00 pm Jun 29 2023. Since we are baking at 120 deg C instead of the standard 150 deg C for Aluminium, the duration for the bake will be over three days until Monday morning, upon which we will slowly ramp down the the temperature.

Entry  Wed Jun 28 15:58:56 2023, Shane, Cao, Infrastructure, VAC, Power trip problem remains, source of smoke is insulation Pumpline_afterRemoveInsul.jpgRGAline_afterRemoeInsul.jpgMeltedInsulation1.jpgMeltedInsulation1.jpgMeltedInsulation2.jpg
[Shane, Cao]

With the new change in wiring configuration described in elog 136, we tried to power up the heaters for baking the vacuum chamber again.

Given that we were worried about the turbo pump overheats, we set the setpoints of of bother high temperature controller and PID controller to be 120 deg C before turning the heaters on

1. Evidence of smoke originating from CoolSkin insulation

We then removed most of the CoolSkin insulation on the Pump and RGA lines ( apart from the one around the flexible bypass line connecting the two ) (see image Pumpline_afterRemoveInsul and RGAline_afterRemoeInsul) . Upon removal of the insulation, we noticed that the insulating foam melted onto the heating tape (see image MeltedInsulation1 and MeltedInsulation2). This is the first indication that the smoke had most likely coming from the insulating foam itself

Once we started baking, upon reaching 80 degree range. We observed no smoke at the location that we removed the insulation. However, We observed smoked coming from underneath the insulation around the flexible pipe, and not from the velcro areas.

What could be causing this, given that the maximum operating temperature of the insulation is 200 deg C? Most likely, the heating tape is much hotter than we think it is. But given that the temperature sensor readout is much lower than 200 deg C, it's likely that this is due to poor thermal contact and it takes a while for sensor to reach a thermal equilibrium with the heating tape. Here, I suggest we should implement the following:
  • We should look into usingsome form of thermal tape (if possible to secure the temperature sensors)
  • Unfortunately or controller does not allow programming process, we will have to implement manual temperature stepping, emulating ramping process over the first hour, until slowly reach 120 deg C
  • OR Tune the PID controller coeffs, especially P and I for longer rise time and settling time

2. The heaters still trip our power

Upon reaching 80 deg C,our main power trip. Unfortunately I don't know how to reset this. Do we need to contact facility on this? Reading elog 136, I noticed that both controllers are connected to the same circuit LP3B 6, which is the same circuit the some of the fan-filters and LED light panels of the cleanroom connected to. From the elog, the circuit has a 20 A limit . An max operation, the 2 heater controllers draw 30 Amps, approx 7 Amps for the fan-filters, and another 1.5 A for LED panel. The combination of these equipment must have overload the circuit and tripped it . Currently half the fans + lights are off in the cleanroom are off due to power trip. Here, I would make a suggestion that each heater controller should be connected to a separate circuit . Currently we LP3B 7 (same side next to LB3B 6) and LB3B 4 (opposite side of the rail) having no equipemts connected to them, but will require cable extensions.
Entry  Wed Jun 21 20:25:05 2023, Cao, Infrastructure, VAC, Vacuum chamber bake attempt 1 6x

TL;DR:

We are not yet able to bake the chamber at 150 deg C due to some current limit, most likely caused power supply switching off. Also, smoke was observed at some insulation points, mainly in the small arm sections, This is likely because the insulation does not fit well and the velcro came into direct contact with heat tape. Some Velcro (made from Nylon/ Polyester) has lower melting temperature point (in 90-120 deg C range)

Full version:

20 June 23:

  • Turn off heater (short term testing) Close valves to RGA line and main volume. Pressure (Torr) readout:
    • Gauge 1 (main volume): 3.43E-6
    • Gauge 2 (RGA line): 2.61E-6
    • Gauge 2 (pump line): 3.8E-4
  • Turn off turbo pump, let vacuum line vent
  • Connect high temperature control unit to main power, power up, set setpoints:
    • Temperature setpoint: 150 deg C
    • High temperature setpoint (to switch off) : 175 deg C
    • Hysteresis: 10 dec C
  • change setpoint of PID control unit to 150 dec C, with high alarm set at 165 deg C
  • Connect power output of high temperature control units to PID temperature control units, ensuring both are off
  • Turn off scroll pump
  • Replace Pirani gauge in front of turbo pump with blanks (see image)
  • Pump the vacuum line back down
  • Open up valves and wait until pressure of full system drop back down to 1E-6
  • Install the high temperature controller thermocouples onto the chamber (see images):
    • One thermocouple is installed on the other side of the cross before the turbo pump
    • One thermocouple is installed on the main volume next to the PID controller RTD
  • Attempt to remove electronic box and magnetic shield of full range gauges:
    • Electronic box is easily removed with an Allen key
    • Magnetic shield cannot be removed since the gap between the vacuum flange and the gauge bolt is too short for a spanner to go in. This is mainly due to the bolt washers are in the way (see images)
    • To remove the magnetic shield, the main volume has to be vented and the gauges need to be readjusted.
  • Attempt to power heaters (but only heat to 80 deg C):
  • Leaving the gauges intact, the high temperature controller + PID controller are turned on to test heating the chamber
  • At this point, both of the high temperature controllers are connected to the same power strip (Vacuum chamber end of the table)
  • After heating up to 65-70 deg C range, the powers turned off on both controllers + the lights on one end of the table
  • Upon inspection, the power strip has turned itself off, I don't know what the model of the power strip but we should check its current limit
  • For a quick test, I connect one of the two heater controlling system to the power board on the work desk while leaving the other running off the same power strip: The heaters appeared to be function ok and able to reach 80 deg C, at which point I turned it off and left for the day

21 June 23:

The goals of today was to remove the electronic boxes and magnetic shields on full range gauges to enable high temperature bakeout

  • Upon returning to the lab, the gauges readout of vacuum pressures were:
    • Gauge 1 (main volume): 3.31E-7
    • Gauge 2 (RGA line): 3.40E-7
  • Venting the both main volume and RGA line
  • Remove the two full range gauges from their flanges
  • Electronic boxes and magnetic shields were removed according to the gauge manuals (see images)
  • Mount the gauges (with only its probing volume) back onto their respective flanges, ensuring that the flange washers do not block access to the magnetic shield screws
  • Only remount magnetic shield + electronic box for one gauge (gauge 2: RGA line) for monitoring chamber pressure
  • Turn on scroll pump and let the chamber pump down
  • Rearrange heater controller connections while waiting for pumping down:
    1. Controllers for bottom + pump & RGA line heaters remain the same: connected to power strip on vacuum end of the table
    2. Controllers for lid + upper chamber main volume: connected to power strip on clean&bake end of the table
  • Once the pressure readout by gauge 2 reached 3 Torr, the turbo pump was turned on and left to run for 45 minutes
  • Upon returning to the lab, pressure on gauge 2 read 5E-6 Torr and was still decreasing
  • Disconnect the ethernet cable to gauge 2, remove its electronic box and magnetic shield
  • Turn on heater controller units and let them drive the heaters to get up 150 deg C
  • At 95 degree range, I could see smoke at some locations, mainly the RGA and pump lines where the insulation do not fit properly and the velcros are likely to be overheated
  • Upon reaching 90 degree range (measured by sensors), the powers turned off on both sides of table (including heaters, lights and scroll pump)
    • Turn off both heaters controllers and unplug them from power strip. Attempt to switch the power strip back on but nothing happened
    • It is now not the power strips problem and must be further down the line from outside the tent, most likely the power supply that these strips connected to: What is the power supply model + current limit?
  • The heater controllers left unplugged, I temporarily plugged scroll pump to the desk power strip so it can still run

    Reply  Tue Jun 27 21:47:56 2023, Jon, Infrastructure, VAC, Vacuum chamber bake attempt 1 IMG_0256.pngIMG_0257.pngIMG_0254.png

The electrical overload problem encountered in ELOG 130 has been resolved. The two heater controllers, which draw up to 14.1 A each, overloaded the UPS and tripped one of its circuit breakers, shutting off power to both power strips mounted above the optical table.

I reset the circuit breaker and rerouted the two heater power cables instead to two separate 20 A outlets in the overhead cable tray outside the cleanroom (both on the LP3B 6 circuit). The two high-limit temperature controllers are now permanently positioned, as shown in the photos. For now, the PID controllers have been left sitting at the table level. I am ordering extension cords that will enable us to move those up to the overhead shelf, as well. I ran the heaters in their new configuration for several minutes without issue. Thus we should be able to now proceed with baking the chamber.

For future clarity, I added labels to power strips around the lab indicating which ones are powered by the UPS. To avoid overloading the UPS, only sensitive electronics or devices that could be damaged by a sudden loss of power should be connected to these.

Entry  Tue Jun 27 15:18:26 2023, Pamella, Update, FLIR, New data collection FLIR_data.002.jpegFLIR_data_2.002.jpeg
    [Pamella]
    Yesterday, I did a new data collection. I could get a better data in this time and I realized than I need use some angle on the reflector for got a better shot. I need do that because the FLIR camera just is able to get the triangle shape for complete if I keep exactly in same line for center point on the camera but for the data now I need move the refletor to go up and go down. So wasn't working very well if I keep the reflector without angle.
    Now I am using the refletor with a angle. In the more high part I turn the mask for look the table and in the lower part I turn the mask to look up. I attached a photo below for this configuration. Also the processes to get the data was the same than I using last time, the only diference is now I just moved the pillar after get data for high position and lower position for the same reference point on the triangle shape.
    Note: In most data it is impossible to keep the same parameter for current, voltage and temperature. Most have a small variation but not a big difference. For example: I got the temperature in the first position 46.8 °C and in the second position I got 47.1 °C, it's just an example. It's just so we know that we don't have the exact same parameters all the time. In my opinion this is not a problem because it is just a small variation.
    The process to get data
  • 09:35 am: Turned on the device (current on). I wanted for 30 minutes before start get data.
  • 10:05 am: Started taking snap on position one (Reference point: -0.10, 0.050). Parameters:0.11A,1.7V,46.8°C
  • I took four snap on the same position for compare after on data analyzes. I just wanted one minute break between the snaps. I did the same for every position.
  • 10:15 am: Started taking snap on position two (Reference point:-0.10,-0.050 ). Parameters: 0.11A,1.7V,47.1° C
  • 10:22 am: Started taking snap on position three (Reference point:0.00 ,0.050). Parameters: 0.11A,1.6V,48.1°C
  • 10:26 am: Started taking snap on position four (Reference point: 0.00,-0.050). Parameters:0.11A,1.6V,48 °C
  • 10:32 am: Started taking snap on position five (Reference point: 0.05,-0.050). Parameters:0.11A, 1.6V, 48°C
  • 10:37 am: Started taking snap on position six (Reference point: 0.05,0.050). Parameters: 0.11A,1.7V,47.6 °C
  • We can see in the photos attached below every position also I am working in the analyzes.
Entry  Tue Jun 27 14:04:42 2023, Sophia A. , Update, Measuring Noise in Interferometer, Interferometer set up and connection to red pitaya IMG_6756.jpgIMG_6754.jpgIMG_6755.jpg
Today we (Sophia and Tyler) constructed the set-up for the electrical noise calculation that I will be conducting this summer. I have included images of the setup below. Our system is effectively a green laser, that feeds into a type of polarizer, then into a beam splitter which sends the laser light down two arms into detectors. We started by connecting the detectors to an oscilloscope to determine whether the signal will exceed 1V, as the red pitaya (our planned data collection device) cannot receive signals with a higher voltage than 1V. We spent most of our time calibrating the oscilloscope and fine-tuning the set-up so that we would have approximately equal voltages in each arm of the interferometer. Once confirming that the output voltage would not meet or exceed 1V, we switched from an oscilloscope to the red pitaya for our measurements. Now that the system is set up, we will be able to run code in the red pitaya interface that will run an FFT on the signal, and then do noise analysis from there.
Entry  Tue Jun 27 12:09:37 2023, Shane, Update, Cleanroom, cleanroom 5 zone particle count measurement 23.png
Attached is 5 zone measurement for cleanroom particulate count. Zone 3 (in front of vacuum chamber) higher than usual, likely due to recent vac work. Slightly above ISO class 5 standard in 1.0 micron range, measuring 997 particles/cubic meter while ISO standard is 832 particles/cubic meter in this range. Zero count test on particle counter performed prior to today's measurement.
Entry  Fri Jun 23 15:47:06 2023, Pamella, Update, FLIR, Collecting data - Moving horizontal and vertical on screen. 6x
[Pamella]
  • 02:09 pm: Turned on the device (current on)
  • 02:42 pm: Started taking snap on position one (Reference point: 0,-0.062). Parameters:0.10A,1.5V,41.5C
  • I took multiplier snap on the same position for compare after on data analyzes. I just wanted one/two minute break between the snaps. I did that same for every position.
  • 02:55 pm: Started taking snap on position two (Reference point:-0.10,-0.062 ). Parameters: 0.10A,1.5v,43 C
  • 03:01 pm: Started taking snap on position three (Reference point:0.05 ,-0.062). Parameters: 0.1A,1.4V,42.8C
  • 03:07 pm: Started taking snap on position four (Reference point: 0.05,0.045). Parameters:0.10A,1.5V,43.6 C
  • 03:15 pm: Started taking snap on position five (Reference point: 0,0.045). Parameters:0.10A, 1.4V, 44.1C
  • 03:22 pm: Started taking snap on position six (Reference point: 0,0.045). Parameters: 0.10A,1.4V,43.3 C
  • We can see in the photos attached below than have some differences between every position so I should be starting analyzes on that.
Entry  Thu Jun 22 13:58:00 2023, Pamella, Julian and Shane, Update, Cleanroom, Cleaning and Particle Count 
[Pamella, Shane, and Julian]
    cleaning cleanroom and particle count
  • 12:00 pm: started particle count
    • Zone 3
      • 0.3u: 3533
      • 0.5u: 540
      • 1.0u: 166
    • Zone 4
      • 0.3u: 290
      • 0.5u: 124
      • 1.0u: 41
  • 12:31 pm: Started checking the surface inside the cleanroom and began surface wipedown
  • 12:50 pm: started vacuuming the floor
  • 1:05 pm: Finished vacuuming floor
  • 1:09 pm: Started mopping the floor
  • 1:21 pm: Finished mopping the floor
  • 1:22 pm: Started cleaning the baskets
  • 1:25 pm: Started mopping with IPA wipes
  • 1:39 pm: Finished mopping with IPA wipes
  • 1:41 pm: Changed sticky floor mats
  • 1:45 pm: Started particle count
    • Zone 3
      • 0.3u: 2327
      • 0.5u: 581
      • 1.0u: 207
    • Zone 4
      • 0.3u: 1662
      • 0.5u: 374
      • 1.0u: 290
Entry  Tue Jun 20 22:14:24 2023, Pamella, Cao, Infrastructure, VAC, Short term testing of vacuum heater controller units 
[Pamella, Cao]

Fuse replacement

  • Replace blown 10A fuse in ucontroller outside cleanroom
  • Replace 10 A fuse in main power connection slot of the controller unit inside cleanroom
  • Pamella wiped down unit outside cleanroom.
  • Controller units turned on and temperature setpoint set to be 80 deg C
  • Temperature settle in approx. 15 minutes(as recorded by the RTD). No problems with fuses observed
  • Recording of pressure gauges (in Torr) :
    1. Before turning heater on :
      1. Gauge 1(main chamber): 3.73E-7
      2. Gauge 2(RGA line): 3.65E-7
      3. Gauge 3(Pump line): 3.8E-4
    2. After 15 minutes :
      1. Gauge 1(main chamber): 7.07E-7
      2. Gauge 2(RGA line): 6.12E-7
      3. Gauge 3(Pump line): 3.8E-4
  • Reduce setpoint temperature to 60 deg C due to Pinrani gauge (Gauge 3) temperature limit
  • Upon returned to lab to reduce temperature (35 minutes after turned on):
    1. Gauge 1(main chamber): 1.22E-6
    2. Gauge 2(RGA line): 9.98E-7
    3. Gauge 3(Pump line): 3.8E-4
  • Once temperature has settled to 60 C (approx 20 mins after changing setpoint), pressure readout showed:
    1. Gauge 1(main chamber): 1.37E-6
    2. Gauge 2(RGA line): 1.10E-6
    3. Gauge 3(Pump line): 3.8E-4
  • Heater left on for the whole afternoon, pressure readout upon returning to lab at 5:30 pm:
    1. Gauge 1(main chamber): 3.43E-6
    2. Gauge 2(RGA line): 2.61E-6
    3. Gauge 3(Pump line): 3.8E-4

Entry  Tue Jun 20 17:28:23 2023, Pamella, Update, Electronics, Heater system parts - Wiped  IMG_7696.jpg
[Pamella]
    Heating system
    Wiping the heater system parts.
  • 04:37 pm: Started wiping the electronic device part for the heater system (HL101 Series Digital Benchtop temperature limit control).
  • 05:19 pm: Finished wiping the parts to the heater system (HL101 Series Digital Benchtop temperature limit control). I wiped the HL101 Series Digital Benchtop temperature limit control and I didn't bagged and tagged because we should install that soon.
  • 05:23 pm: I putted heater electronic device inside the cleanroom without the bag. Also the electronic device is near to the vacuum chamber and the other parts to heater system.
  • I attached the photo below.
Entry  Mon Jun 19 11:20:57 2023, Pamella, Update, FLIR, FLIR - Fixed some problems AcquisitionImage(Jun-19-2023_11_00).jpg
[Pamella]
  • 08:59 am: Turned on the electronic device (current on) for started taking data.
  • 09:37 am: Tried understanding the error in the focal point. I realized the pillars was in the wrong place and because of that we got problems to keep the reflector in the correct position to FLIR focus.
  • 09:58 am: Started checking the temperature and the parameters.Changed the pillars to the original position (0.5645m) just for checking with the problem was the pillar in the wrong place.
  • 10:06 am: Changed the reflector to point (0.3282m) and now in the correct position for the pillars. Started take snap and collecting data. I moved up and down the reflector for got data to compare later.
  • 10:37 am: Used the closest point possible for the reflector in front of the FLIR camera with the correct spot for the pillars.(0.2032m)
  • 11:00 am: Started taking snap after kept the current on for a few hours. Parameters: Current: 0.10A , Volt: 1.3V and Temperature: 41.9 C.
  • I attached below the snap in the most close point possible, now i can see a better photo and I think a fixed the problem about the focal point in the reflector for have more uniformity between the triangles, isn't perfect yet but now is just some adjustments. Furthermore after that I should be change the reflector position and also the optical focus distance in the FLIR camera and try use the black wall.
    Entry  Fri Jun 16 17:40:28 2023, Aiden, Update, Clean &amp; Bake, Clean and Bake Batch 14 IMG_4441.jpgIMG_4440.jpg
    Cleaned and Baked the new and 2.75" copper gaskets for the vacuum system. Cleaned them with liquinox in the ultra sonic washer for 10 minutes. Then dried them with nitrogen. Then put the copper parts into the oven for the following steps; 1. Ramp to 100 degC in 15 minutes 2. Dwell at 100 degC for 30 minutes 3. Ramp to 175 degC in 30 minutes 4. Dwell at 175 degC for 24 hours 5. Turn off Also bagged and tagged the parts from Batch 13 and placed them into the clean room on the computer table.
    Entry  Fri Jun 16 16:17:13 2023, Pamella, Update, FLIR, FLIR - Change the position IMG-7637.jpg
    [Pamella]
      Today I change the distance between the FLIR camera and reflector (3D-Mask with mirrors and light). Now the distance is 0.3282 m.
    • Note: In this distance is possible move up and down the reflector and take data to compare.
    • The focal point inside the reflector keeping like little problem, every time I tried adjust this I got some triangles is not with "perfect emission" (looks like different than the others). Also if I move up or down the focal point inside the reflector have some issues as well.Therefore I am working on that.
    Entry  Wed Jun 14 15:35:36 2023, Pamella, Update, VAC, Heating system installation  heater_equipment_install.jpg
    [Pamella and Cao]
      Heating system installation - Second day.
    • Today we kept installing the equipment for the heating system.
    • First: Started installing the two heating cable around the chamber vacuum, the arms and covered it with aluminum tape.
    • Second: Started installing the insulation stuff around the vacuum chamber and around the connections points (the arms) in the vacuum chamber.
    • Third:Started installing the heater system (electronic device) and tried testing.
      • Note: The around part of the chamber vacuum was difficult to cover, so we spent a little time on. Also one heater system electronic device wasn't working because one fuse is burned so we could not finished this part and we need wait for a new one to replace and working on it.
    Entry  Tue Jun 13 21:33:46 2023, Pamella, Update, General, New cabinet for PPI 
    [Pamella and Dr.Richardson]
      Dr. Richardson installed the new cabinet outside the room for the PPI equipments, and then I wiped all surfaces inside and outside of the new cabinet.
      Dr.Richardson and I have finished organizing the PPI within the new cabinet. Also we have new supplies of gloves, and will likely have more supplies for other PPIs soon.
    Entry  Tue Jun 13 21:08:46 2023, Pamella, Infrastructure, VAC, Heater system - Installation IMG_7563.jpegIMG_7561.jpeg
    [Pamella, Cao and Jon]
      Heating system installation
    • Today we started installing the equipments for the heating system.
    • First: Started installing the heating cable on the top lid and covered it with aluminum tape.
    • Second: Started installing the insulation cover on top of the chamber lid.
    • Third:Started installing the heating cable from under the vacuum chamber and covered with aluminum tape.
    • Forth: Started installing the insulation cover under the vacuum chamber
    • Note: The under part of the chamber vacuum was very difficult to cover, so we spent a little time on it and we couldn't finish the whole installation today. So tomorrow we should be able to keep doing the installation.
    Entry  Tue Jun 13 13:25:05 2023, Aiden, Summary, Clean &amp; Bake, Clean and Bake Batch 13 
    Cleaned and Baked the new 1.33" and 2.75" blanks for the vacuum system. Cleaned them with liquinox in the ultra sonic washer for 10 minutes. Then dried them with nitrogen. Then put the two stainless steel parts into the oven for the following steps; 1. Ramp to 100 degC in 15 minutes 2. Dwell at 100 degC for 30 minutes 3. Ramp to 200 degC in 30 minutes 4. Dwell at 200 degC for 48 hours 5. Turn off
    Entry  Tue Jun 13 10:28:50 2023, Pamella, Update, General, Wiped and bagged the heating and cords. heater_cords_wiped.jpg
    [Pamella]
    • Cleaning the heater system parts.
    • 09:13 am: Started wiping the last parts for the heater system (heating and cords).
    • 10:18 am: Finished wiping the parts to the heater system (heating and cords). I wiped, tagged and bagged the heating and cords.
    • Note: In some parts looks like the silicone insulation material is having some sort of residue on the wipe so I wiped very careful this part and just for a few minutes.
    • 10:23 am: I putted all bags inside the cleanroom.
      I attached the photos below.
    Entry  Mon Jun 12 18:52:00 2023, Pamella, Update, General, Heater system parts - Wiped and bagged heater_equipment_wiped.jpg
    [Pamella]
      Cleaning the heater system parts.
    • 04:32 pm: Started wiping the heater system parts.
    • 06:38 pm: Finished wiping the heater and some parts to the system. I wiped, tagged and bagged the heater system, power cables, adapter cables and power connectors. Also I wiped, bagged and tagged the aluminum foil tape.
    • 06:43 pm: I putted all bags inside the cleanroom.
    • To do: I started but I was not able to finished wiping the heating and cords for the heater system so I will finished this parts after.
    • I attached the photos below.
      Entry  Mon Jun 12 12:15:10 2023, Pamella, Update, FLIR, FLIR- Take data in the closest point. AcquisitionImage(Jun-12-2023_12_04).jpg
      [Pamella]
      • Used the closest point possible for the reflector in front of the FLIR camera.
      • 11:32 am : Turned on the electronic device (current on) for started taking data.
      • 11:50 am: Started checking the temperature and the parameters.
      • 12:04 pm: Started taking snap after waited for 30 minutes with the current on. Parameters: Current: 0.13A , Volt: 1.8V and Temperature: 51.4 C.
      • Note: This snap is in the most close point possible, after that I should be change the reflector position and also the optical focus distance in the FLIR camera.
      • We can see, in the photo attached below, thought in this closest position the cable connect to reflector is a bit problem to take a good snap also the have issues to keep very uniform triangles (temperature) in the reflector.
      • To do: I'll change the position on the light inside to see if the problem it is in the focal point inside the reflector (mirror).
      Entry  Thu Jun 8 14:51:58 2023, Pamella, Update, FLIR, FLIR- Distance AcquisitionImage(Jun-08-2023_14_33).jpgthumbnail_IMG_7441.jpg
      [Pamella, Tyler]
      • Today we change the distance between the FLIR camera and reflector (3D-Mask with mirrors and light). Now the distance is 0.2032 m.
      • Note: This distance is just for take a snap most close possible but we need move again for a little far way because in this distance we can't move up and down the reflector for have data to compare.
      Entry  Tue Jun 6 16:15:09 2023, Peter, Update, VLC Update, Launch Optics for Visible Light Cavity IMG-0882.jpgIMG-0883.jpg
      I assembled the first few components of the launch optics for the visible light cavity. Below is an image of the current table configuration, and the image is how the cavity will be oriented on the table.
      Entry  Tue Jun 6 16:04:46 2023, Aiden, Update, General, Water 
      Aiden went and refilled the de-ionized water to continue clean and bake batches.
      Entry  Fri Jun 2 14:28:40 2023, Pamella, Update, FLIR, FLIR project - Test without the black wall. 1Axis_y___tests.jpg
      [Pamella]
        Test without the black wall.
        Note: So today i collected data for some positions in axis Y (height) for starting analyses and compares the triangles shapes. I tried keep the same parameters every time.
        First position:
      • 01:20 pm : Started testing and collection data. Parameters: 0.10 A, 1.6V. Reference position: (0,0.05).
      • 01:30 pm : Started snapping the screen. Parameters: 0.10 A, 1.6V and 37.7 C. Reference position: (0,0.05).
      • Second position:
      • 01:34 pm : Started testing and collection data. Parameters: 0.10 A, 1.6V Reference position: (0,0).
      • 01:44 pm : Started snapping the screen. Parameters: 0.10 A, 1.6V and 40.6 C. Reference position: (0,0).
      • Third position:
      • 01:50 pm : Started testing and collection data. Parameters: 0.10 A, 1.6V. Reference position: (0,-0.05).
      • 02:00 pm : Started snapping the screen. Parameters: 0.10 A, 1.6V and 39.1C. Reference position: (0,-0.05).
      • Fourth position:
      • 02:03 pm : Started testing and collection data. Parameters: 0.10 A, 1.6V. Reference position: (0,-0.10).
      • 02:13 pm : Started snapping the screen. Parameters: 0.10 A, 1.6V and 39.6 C. Reference position: (0,-0.10).
      Entry  Thu Jun 1 14:41:36 2023, Pamella, Update, FLIR, FLIR project - Test without the black wall. thumbnail_IMG_7316.jpgAcquisitionImage(Jun-01-2023_14_14).jpgthumbnail_IMG_7320.jpg
      [Pamella]
        Test without the black wall.
          General test:.
      • 11:15 am : Started running the code. Parameters: 0.11 A, 1.9V and focus distance around 0.55m.
      • 11:28 am : Started snapping the screen. Parameters: 0.12 A, 1.8V and 44.1 C .
      • First trying:
      • 01:18 pm : Started testing and collection data. Parameters: 0.09 A, 1.4V. Reference position: (0,0).
      • 01:28 pm : Started snapping the screen. Parameters: 0.10 A, 1.5V and 37.9 C. Reference position: (0,0).
      • Second trying:
      • 01:34 pm : Started testing and collection data. Parameters: 0.08 A, 1.4V. Reference position: (0,-0.10).
      • 01:44 pm : Started snapping the screen. Parameters: 0.09 A, 1.7V and 35.8 C. Reference position: (0,-0.10).
      • Third trying:
      • 01:50 pm : Started testing and collection data. Parameters: 0.08 A, 1.3V. Reference position: (0,-0.05).
      • 02:00 pm : Started snapping the screen. Parameters: 0.09 A, 1.4V and 35.4 C. Reference position: (0,-0.05).
      • Fourth trying:
      • 02:04 pm : Started testing and collection data. Parameters: 0.09 A, 1.3V. Reference position: (0,0.05).
      • 02:14 pm : Started snapping the screen. Parameters: 0.11 A, 1.6V and 41.7 C. Reference position: (0,0.05).
        Note: So today i tried collecting data for every possible position in Y (height) way for starting analyses and compares the triangles shapes. I realize maybe we get a problem because i keep the same time in every try but the final temperature and the parameters change every time, so i will try do a better system to keep the parameters equal, maybe i can wait the reflector be back to a normal temperature after every test or keep the system on all the time and just change the reflector position. I pretty sure this was the problem.
      Entry  Wed May 31 16:55:55 2023, Pamella, Update, FLIR, FLIR- Focus distance AcquisitionImage(May-31-2023_16_40).jpgthumbnail_IMG_7310.jpg
      [Pamella and Tyler]
      • We changed the FLIR Focus Distance for around 0.55 m.
      • Note: The old focus distance was 1.3 m.
      • We tested this new focus distances and looks good. I attached a snap below.
      • Parameters: 0.1 A , 1.5 V and 38.4 C.
      Entry  Wed May 31 16:18:41 2023, Aiden, Summary, General, Mock FROSTI IMG_4394.jpg
      Finished assembly on the Mock FROSTI so it is ready for the fit test at LIGO lab.
      Entry  Wed May 31 12:16:28 2023, Shane, Update, Cleanroom, cleanroom particle counts (full 5 zone measurement) 23.png
      Attached is the full 5 zone particle measurement for the cleanroom after this week's cleaning, 5/31/23.
      Entry  Wed May 31 11:42:16 2023, Pamella, Julian and Shane, Update, General, Cleaning room and particle count 
      [Pamella, Shane and Julian]
        Cleaning room and particle count
      • 09:58 am: Started the particle count
        1. Zone 3:
        2. 0.3u : 1,995
        3. 0.5u : 540
        4. 1.0u : 0
        5. Zone 4:
        6. 0.3u : 124
        7. 0.5u : 0
        8. 1.0u : 0
      • 10:25 am: Started checking the surfaces inside the cleanroom.
      • 10:30 am: Started vacuuming the floor.
      • 10:45 am: Finished vacuuming the floor.
      • 10:46 am: Started mopping the floor.
      • 10:58 am: Finished mopping the floor.
      • 11:00 am: Started wiping floor with polypropylene wipes.
      • 11:03 am: Started and finished cleaning the mop buckets.
      • 11:15 am: Finished wiping floor with polypropylene wipes.
      • 11:16 am: Changed sticky floor mats.
      • 11:20 am: Started the particle count.
        1. Zone 3:
        2. 0.3u : 2,951
        3. 0.5u : 872
        4. 1.0u : 207
        5. Zone 4:
        6. 0.3u : 374
        7. 0.5u : 83
        8. 1.0u : 0
      Entry  Tue May 30 14:51:27 2023, Pamella, Update, FLIR, New 3D mask - Bigger triangles shapes. AcquisitionImage(May-30-2023_14_38).jpgthumbnail_IMG-7303.jpg
      [Pamella]
        Change the 3D mask
      • Started removing the old mask in the reflector.
      • Started cutting the new aluminum lid for the new 3D mask and assembling in the 3D mask.
      • Started doing the new cable connections for the light.
      • Started testing the resistance in the new cable connections. The multimeter show us 14.2 Ω.
      • Started attaching the mask with the light and the thermometer sensor.
      • Started assembling the 3D mask in the reflector.
      • Started the initial tests.
      • 2:00 pm: Started testing the new mask. Parameters: 1.4 V 0.1A and 27 C
      • 2:38 pm: Started taking snap. Final parameters:1.4 V 0.1A and Temperature: 39.9 C
      • Started doing some adjustments in the triangles shapes for the futures tests.
      Entry  Wed May 24 14:28:26 2023, Peter, Update, VLC Electronics, Laser intensity/polarization drift measurements Time_Series_Trial_7_16hrs.pngPower_vs_Time_16hrs.pngPolar_angle_vs_time_16hrs.pngRel_Intens_vs_time_16hrs.png
      I went in and took polarization drift data for 16 hours. The run started at 6:08pm and finished at 9:15am the next day. The four plots below are the same plots shown for the 2 hour collection and previous trials, except they extend to 16 hours. The only one that is different is the Power vs. Time graph. This is a graph of the actual incoming power of the laser (as opposed to the signal voltage that the PDA's output into the red pitaya). This was done using the calibration factors of the respective PDA's and as we can see, since there is a difference in the calibration factors between detectors, there is a difference in the power that's coupled into S and P polarization.
      Entry  Wed May 24 14:06:27 2023, Pamella, Update, FLIR, FLIR project - Tests AcquisitionImage(May-24-2023_10_50).jpgthumbnail_IMG-7146.jpgAcquisitionImage(May-24-2023_14_30).jpg
      [Pamella]
        Initial tests
      • 10:30 am : Started trying take some test with the new position/configuration between the 3D reflector-mask and the FLIR camera.
      • 10:41 am : Started running the python code and take a snap. Parameters: 0.10 A, 1.4 V.
      • 10:50 am : Started take the snap.It is possible see the triangles, this is a good thing. Negative thing: The middle/center point for the light maybe would be some problems for the future measurements. Parameters: 0.10A, 1.4 V and 41 C.
      • 11:00 am : Started working to better align the entire structure. And double-check the distance between the 3D reflector-mask and the FLIR camera, following the instructions in Cassidy's Final FLIR Project Report.
      • 11:10 am : Difficult point: I tried to attach the complete FLIR camera to the table, but I had a problem to secure the four screws to the table, the distance is not completely compatible with the table stand. Yesterday I just put two screws in the diagonal position, it works fine, but it's not the correct position to work.
      • 12:00 am : Note: Two triangles take more long time to come back a not (low) irradiation position (east and south point).
      • 2:00 pm : Started running the python code again.
      • Parameters: 0.13 A 1.8 V.
      • 2:30 pm: Started take snap. Parameters: 0.13 A, 1.8 V and 49.1 C
      • 3:00 pm: Note: This time every triangles was able to come back a low irradiation position.
      Entry  Tue May 23 16:52:56 2023, Pamella, Update, FLIR, FLIR project - Reinstalling the mask and Reconfiguration FLIR position. AcquisitionImage(May-23-2023_16_36).jpgReconfiguration.jpg
      [Pamella]
        Reinstalling the mask and Reconfiguration FLIR position.
      • Today i change the aluminum foil inside the 3D mask. After some tries i was able to have a better shape for the triangles.
      • I reinstalled the connections (the light with the thermometer point). Also i checked for the focal point inside the reflector, looks fine.
      • I did a reconfiguration for the initial tests, without the black wall. I moved the FLIR camera and the Reflector-Mask for other position on the table.
      • To do:
      • Start the test with the power current on.
      • I need figure out a better position for the light cables because in front of the mask isn't a good position for us do measurement.
      Entry  Mon May 22 17:08:50 2023, Pamella, Update, FLIR, FLIR project - Installing the mask. Mask.jpgAcquisitionImage(May-22-2023_16_35).jpgAcquisitionImage(May-22-2023_16_01).jpg
      [Pamella]
      • The new mask for the reflector.
      • 1:40 pm: Started reconfiguration on the FLIR camera project. Changed the old bridge for the new mask-bridge.
      • 2:00 pm: Started figure out the best way to cutting the aluminum foil with the new mask. Unfortunately, I had been some problems for cutting the perfect shape triangles with the mask because the size inside the triangle is different (smaller) than cutter/knife, so is not able to do the cut with precious and carefully then maybe I need other tool for this job. Also I tried use the scissor, didn't work. However, just for the initial testing I worked with the not perfect triangles shape.
      • 2:49 pm: Started installing/attaching the light in the mask.
      • 3:21 pm: Finished installing the light in the mask-bridge.
      • 3:22 pm: Started testing the current and voltage in the new mask-bridge for make sure the light cable is working well.
      • 3:25 pm: Started measurement the resistance with multimeter.
      • 3:29 pm: The measurement looks fine. The multimeter show us 14.1 Ω;
      • 3:38 pm: Started putting the reflector( with the mask attached) in front of the black wall.
      • 3:44 pm: Started roll the testing with the python code to observer the behavior with this new mask. Parameters: 0.14 A and 1.9 V.
      • 4:00 pm: Started snapping. Parameters: 0.13 A and 1.9 V. Final Temperature: 42.7 C.
      • 4:02 pm: Started trying again with more current. Parameters: 0.16 A and 2.2 V.
      • 4:36 pm: Started snapping. Parameters: 0.16 A and 2.2 V. Final Temperature: 50.3 C.
      • 4:55 pm: For now, we can't see the triangles in the snap so i need do some changes.
      • To do:
        1. Change the FLIR camera position for the other side on the table.
        2. Start the test without the black wall.
        3. Try a better tool to cut the triangles inside the 3D-mask.
      Entry  Mon May 22 16:43:28 2023, Peter, Update, VLC Electronics, Laser intensity/polarization drift measurements S-P_Polarization_Diagram.svgPolar_angle_vs_time.pngRel_Intens_vs_time.png
      In order to fully analyze the polarization data taken last Thursday, I needed to convert the signal output (which is in volts) to power (units of watts). I used the power meter to accomplish this. Keeping the exact same configuration of PD's and beam splitting, opened the red pitaya's oscilloscope package. I then took the power meter, and held it in front of the PD to measure the amount of Watts at each PD. I then wrote down the corresponding voltage being seen in the red pitaya. I took 5 sets of measurements for each PD to get experimental accuracy. I then used a simple y = mx + b fit to find out the constant m that converts the input wattage into voltage. For the s polarization, the conversion factor is 0.83. For the p polarization, the conversion factor is 1.12. I then used this data to plot polarization angle as a function of time, and the relative intensity drift as a function of time. The plots are shown below. The physical meaning of the polarization angle is shown in the unit circle diagram below, in which P is the total power.
      Entry  Thu May 18 14:07:08 2023, Peter, Update, VLC Update, 532nm Intensity Measurement Time_Series_Trial_4.pngTime_Series_Trial_5_2hrs.png
      I figured out a method in which to capture power measurements including the initial seconds in which the beam is first turned on. I first clear and restart the kernel of the python notebook. Then I run the command to connect the red pitaya oscilloscope package to the input data being taken in both channels. To my understanding, this allows for data acquisition as the code compiles. I then started looping the 1.074s trigger bunches, and then roughly 2 seconds after I ran that command, I went and turned on the laser. The first plot shown is a 2 minute practice trial of me trying this technique to make sure that the python package was correctly registering the input of the red pitaya. It is clear that initially the laser is off, and then as I turned it on, the voltage in each channel spikes, which is compelling evidence that the code is working. I then set the data collection to be 7518 seconds (7000 loops), which is about 2 hours and 5 minutes. I repeated the same technique as for the first plot, only changing the amount of time I collected data. The second plot shown here is the voltage being read in each channel as a function of time. As we can see, over a period of hours, the intensity drifts quite dramatically for the first several minutes, and then begins to stabilize slightly. However, there are still some strong sudden fluctuations in each channel.
      Entry  Wed May 17 12:18:08 2023, Pamella, Julian and Shane , Update, General, Cleaning room and particle count 
      [Pamella, Julian and Shane]
        Particle count:
      • 10 am: Started particle count
        1. Zone 3 :
          • 0.3u: 1288
          • 0.5u: 332
          • 1.0u: 124
        2. Zone 4 :
          • 0.3u: 498
          • 0.5u: 166
          • 1.0u: 83
      • 10:40 am: Checked the surfaces inside the cleanroom.
      • 10:50 am: Started vacuuming the cleanroom.
      • 11:15 am: Started mopping the cleanroom.
      • 11:35 am: Started wiping the cleanroom floor.
      • 11:40 am: Finished cleaning the cleanroom.
      • 11:41 am: Started the particle count.
      • 12:17 am: Finished the particle count.
        1. Zone 3 :
          • 0.3u: 3782
          • 0.5u: 706
          • 1.0u: 207
        2. Zone 4 :
          • 0.3u: 374
          • 0.5u: 83
          • 1.0u: 83
      Entry  Tue May 16 11:56:33 2023, Peter, Update, VLC Electronics, 532nm Intensity Measurement Time_Series_Trial_3.png
      With the configuration the exact same as before, I used the Jupyter notebook in the red pitaya's development package to collect data from both input channels. Last week, I was able to take data, yet only for a very short period of time, and I did not know how to change it. I went online to the red pitaya's user manual to figure out how to change the sampling period for longer. The link to the page is here: https://redpitaya.readthedocs.io/en/latest/appsFeatures/examples/acqRF-samp-and-dec.html#s-rate-and-dec Though I now know how to change the period of time for which data is taken, the maximum amount of time is still only about 8 seconds. So with help from Cao, we looped over the data taking samples, and got a mean value for each iteration. We then put all those mean values in an array, and plotted it. Below, we see a plot of both the S and P polarizations, and a sum of both of them. As seen in the graph, I have set the time to be able to take data for almost 2 minutes. There is some slight drift in the respective intensities. The next steps I believe are to convert the units into watts, and take data for longer periods of time.
      Entry  Sun May 14 15:50:48 2023, Cao, Infrastructure, Computers, High resolution display of logrus machine 
      [Cao]

      The display resolution of the logrus has been 1064x768 and has been the only option, which is not great. While remote access to logrus using rdesktop allows rendering a virtual display of user's chosen resolution, it is not fast when using graphic-intensive program. NoMachine allows user to take over and control the machine remotely and thus appears as the same machine. However, NoMachine cannot render a virtual display like rdesktop. This has been limiting the resolution of using logrus via NoMachine.

      On Friday, I found that even though we had NVIDIA Quadro P600 graphic card installed, we were not actually using it. The monitor has been connecting to the the integrated VGA display connector. This uses Microsoft Basic Display Adapter which limits the the resolution. Today I got a HDMI to Mini-display cable to connector the monitor to the Nvidia graphic card. Then in Display settings, go to Graphic settings, then enable Hardware-accelerated GPU scheduling. After restarting the machine, the machine recognised the Display 2using the Nvidia Quadro P600. In multiple displays field, selected "Show only on 2" and remove the VGA connection to the monitor. Logrus is now set at Nvidia Qadro P600 native display resolution of 1920x1080. This is now also the display resolution in NoMachine.

      Entry  Fri May 12 20:28:34 2023, Aiden, Cao, Physics, VAC, Vacuum chamber Helium leak test PXL_20230512_211717602.jpgArLeak_230512.png

      [Aiden, Cao]

      1. Helium leak test

      • 2:00 pm: Uninstall regulator from nitrogen gas tank and move to helium gas tank. Place helium onto cart and move to the rear door of the clean tent. With the tank remaining outside, feed hose through the flexible wall to use in clean tent - See attached image
      • 2:25 pm: Start Helium leak test: At each CF connection, He gas is sprayed while its level is monitored with the RGA in leak detection mode. A constant flow of helium is maintained until the level of helium detected by the RGA plateaus out.
        • All connections show low helium leak detected (< 3e-11 Amp)
        • The connections with highest leak detected are from reducing cross to flex hose and cross to RGA. They are on 2 - 3e-11 Amps. All other connections are less than 8e-12 Amps. We verified tightness of these two connection but they cannot be tighten any further

      2. Argon calibrated leak test

      After finishing the Helium leak test.
      • We opened the Ar calibrated leak. Upon opening the valve to allow Ar to flow through, we can see a surge in pressure measured by the gauges from 6.7e-7 mbar to 1.2e-6 mbar. This is then drop down and stabilised around 8.9e-7 after 5 minutes.
      • Upon the the equilibrium is reached, we ran RGA scan twice in Analog mode with the following settings:
        • Points Per AMU: 10
        • Start Mass : 1
        • End Mass : 100
        • Focus Voltage: 90 V
        • Channel Electron Multiplier (CEM) : On
        • CEM Voltage: 1060 V
        • Unit: Amps (ion current)
        The settings is saved as rga100amu_scan.rga RGA application file in C:/Users/controls/Documents/Vacuum/VacuumChamber/RGA. The data file is saved in Data folder as ArLeak_230512.txt. This file contains the current values for corresponding AMUs. Using this dataset, we can obtain our chamber outgassing rate.
      • Using RGA_scan_process.py , which is adapted from Mike Zucker's Matlab code E2000071, and the Ar calibrated leak posted in elog 95 we can compute the outgassing rate to be 150.5E-10 Torr l/s . Our outgassing rate is 37.5 times higher than the required (4.00E-10 Torr L/s per E080177)
      • See image attached for the spectrum and the hydrocarbon (HC) tracer masses used to evaluate outgassing
      • All codes and data are stored in Vacuum git repo . I'll qrite up an instruction to use the code and post it on our wiki page.

      After finishing with Ar cal leak test, we close Ar valve, disconnect and turn off RGA. The He tank is moved back to the wall mount. The chamber is ready for baking installation

      Entry  Wed May 10 10:49:34 2023, Aiden, Update, General, RGA Software 
      [Aiden, Cao] Went over how to use the RGA software, how to change the graph units, scaling and mass detection. Also went over how to remove the RGA from the vacuum system as well as procedure for turning it on.
      Entry  Tue May 9 20:55:12 2023, Jon, Infrastructure, VAC, Calibrated Ar leak rate VTI-Calibrated-Ar-Leak.jpeg

      For future reference, the calibrated Argon source has a leak rate of 7.55E-8 atm cc/s, or equivalently 5.74E-8 torr L/s. This can be used to calibrate RGA scans to units of physical leakage (outgassing) rate.

      Entry  Wed May 3 19:03:47 2023, Julian,Pamella and Cao, Physics, VAC, Modify vacuum asssembly and install RGA vaccum_chamber_re-configuration.jpg
      [Pamella, Julian, Cao]
        Today we started re-configuring the vacuum chamber components.
        Particle count
      • 10:45 am : Starting the particle count in the clean room.
      • 11:13 am : Finished the particle count in the clean room.
      • Zone 3 :
        • 0.3 u: 2535
        • 0.5 u: 1413
        • 1.0 u: 789
      • Zone 4 :
        • 0.3 u: 457
        • 0.5 u: 290
        • 1.0 u: 207
          Starting the reconfiguration.
        • 11:21 am: Started removing up-to-air valve
        • 11:30 am: Finished removing up-to-air valve.
        • 11:33 am: Started removing calibrated Ar Leak and the elbow.
        • 11:35 am: Finished removing calibrated Ar Leak and started assembling the up-to-air valve.
        • 11:47 am: Finished assembling up-to-air valve.
        • 11:48 am: Started removing magnetron gauge.
        • 11:55 am: Finished removing magnetron gauge.
        • 11:57 am: Started installing the elbow and calibrated Ar Leak and started removing the RGA probe
        • 12:13 pm: Finished installing the elbow and calibrated Ar Leak.
        • 12:20 pm: Break for lunch.
        • 01:25 pm: Come back from lunch break.
        • 01:30 pm: Started removing RGA line.
        • 01:39 pm: Finished removing RGA line.
        • 01:39 pm: Started removing gate valve [RGA line] and finished removing gate valve.
        • 02:00 pm: Started installing gate valve in the new position.
        • 02:08 pm: Fished installing gate valve [RGA line].
        • 02:09 pm: Checked the screws in the elbow to gate valve. [RGA line].
        • 02:28 pm: Finished checking the screws in the elbow to gate valve [RGA line].
        • 02:29 pm: Started installing RGA line.
        • 02:39 pm: Finished installing RGA line.
        • 02:50 pm: Started installing magnetron gauge.(In this part we assembled gauge with the used gasket)
        • 03:02 pm: Finished installing magnetron gauge.
        • 03:04 pm: Started installing RGA probe [RGA line].
        • 03:13 pm: Finished installing RGA probe [RGA line].
        • 03:15 pm: Connected the cables to the magnetron gauge.
        • 03:20 pm: Started the testing in the vacuum chamber.
        • 04:30 pm: Started installing the RGA 200 and connected the cables (power cable and DB9 cable).
        • 04:52 pm: Finished installing the RGA 200 and connected the cables (power cable and DB9 cable).
        • 04:53 pm: Started testing the RGA connections. Logrus is able to recognize and connect to RGA unit. We are leaving the turbo pump on for a few hours before checking back for pressure readouts.
        • 05:00 pm : Starting the particle count in the clean room.
          1. Zone 3 :
            • 0.3 u: 2244
            • 0.5 u: 997
            • 1.0 u: 207
          2. Zone 4 :
            • 0.3 u: 2993
            • 0.5 u: 1579
            • 1.0 u: 498
        • 05:30 pm : Finished the particle count in the clean room.
        • 05:34 pm: Test pressure readout from the gauges.
          1. Channel 1 : 1.06E-5 mbar
          2. Channel 2 :8.89E-6 mbar
          3. Channel 3 :5.0E-4 mbar
        • 05:59 pm: Test pressure readout from the gauges.
          1. Channel 1: 9.09E-6 mbar
          2. Channel 2: 7.75E-6 mbar
          3. Channel 3: 5.0E-4 mbar
          Reply  Tue May 9 15:49:20 2023, Jon, Infrastructure, VAC, Permanent cable routing 

      Today I brought in a fresh supply of zip ties (we now have 1500 in the tool chest) and used them to permanentize the cable routing for the gauges, pumps, and RGA.

      I also brought and installed a 3-foot 15A extension cable for powering the scroll pump. Installing the cable required shutting down the pumps, which I did and then reverted via the following procedure:

      1. Close the 4.5" gate valve, 2.75" gate valve, and the bypass line angle valve.
      2. Shut down the turbo pump.
      3. Shut down the scroll pump.
      4. Unplug the scroll pump and install the extension cable.
      5. Power on the scroll pump.
      6. Power on the turbo pump.
      7. Open all three valves.

      Incidentally, before I started, I noticed that the pressure in the main volume had reached 7E-7 torr, which is lower than the pressures seen last week. The system quickly returned to this pressure after I restarted the pumps.

      Entry  Mon May 8 12:00:03 2023, Pamella, Shane, Julian, Update, General, Cleanroom particle counts and cleaning the cleanroom. 
      [Pamella,Julian, Shane]
        Today we cleaned the clean-room (floor, surfaces) and particle count.
        10:00 am: Started particle count.
      • Zone 3:
      • 0.3u: 1330
      • 0.5u: 540
      • 1.0u: 415
      • Zone 4:
      • 0.3u: 290
      • 0.5u: 83
      • 1.0u: 0
        Clean-room:
      • 10:30 am: Started wiping down the surfaces inside the clean-room
      • 10:41 am: Finished wiping down the surfaces inside the clean-room and Started vacuuming the clean-room.
      • 10:58 am: Finished vacuuming the clean-room.
      • 11:00 am: Started mopping on the floor.
      • 11:20 am: Finished mopping on the floor and started wiping on the floor.
      • 11:34 am: Finished wiping on the floor.
      • 11:35 am: Started the particle count.
      • 11:57 am: Finished the particle count.
      • Zone 3
      • 0.3u: 997
      • 0.5u: 290
      • 1.0u: 207
      • Zone 4
      • 0.3u: 374
      • 0.5u: 207
      • 1.0u: 207
      Entry  Thu May 4 14:01:10 2023, Peter, Update, VLC Electronics, 532nm Intensity Measurement graphs(3).jpggraphs(2).jpg
      I adjusted the rotational mount of the wave plate to see if the power can be 100% coupled into either S or P polarization. The images shown below of the oscilloscope indicate that this is not possible. The minimum transmitted power we can obtain in either S or P polarization is 75mV. The maximum voltage we obtain in either S or P polarization is ~ 740mV. This means that at a maximum, we can obtain ~ 90% polarization in either direction, indicating that our laser has a slightly elliptical polarization.
      Entry  Tue May 2 17:03:14 2023, Jon, Cao, Physics, VAC, First pump-down test of vacuum chamber PXL_20230502_203343616.jpgPXL_20230502_210234897.MP.jpg

      [Jon, Cao]

      1. Re-routing of cables

      We re-routed the connections between the turbo pump and its fan to the controller. Instead of going through the side of the server rack, they are now routed along the the cable tray and came down from the top of the server rack.

      2. Planning for vacuum assembly re-configuration

      While preparing for our first pump-down, we notices that RGA pump line gate valve, at its fully closed position, is higher than the height of the chamber lid. The full range gauge attached to the RGA line, while not that high, can also cause obstruction during removal/ installation of the vacuum lid. The calibrated leak, eventhough is now running within the perimeter of the optical table, it stills introduce weak points that are susceptible to damage if personnel installing chamber lid may lean onto it. Thus we made a few suggested modification to the vacuum chamber assembly:
      • Move the entire RGA arm to the mirrored CF port, where the Up-to-Air valve is at
      • Move the Up-to-Air valve to the calibrated leak port
      • Move the calibrated Ar leak the main chamber full-range gauge port
      • Move the full-range gauge to the RGA line port

      3. First test pump-down

      1. With all valves closed, we started scroll pump, pump line quickly got down to 6.08 mbar from atmospheric 1000 mbar (measured by Pirani gauge, channel 3 on controller )
      2. We open Lesker angled valve and let the RGA arm pumped down, Pirani gauge read 6.3 mbar while the full-range guage on RGA line reads 4.9 mbar ( channel 1 on controller )
      3. We open the pump line gate to expose the pump to the main volume, all gaugues readout immediate rise back up 1000 mbar. After 3 minutes, we started to see channel 3 slowly dropped down. A minute later channel 1 and 2 (main body) also dropped down. The slow pressure dropping speed and 6.3 mbar measured earlier got us suspected that there is some large leaks
      4. We proceed to tighten all the ports as the vacuum is pumped down. In particular, we found that large feedthrough port still required a lot of tightening up
      5. As we tighten up all the ports, after 40 minutes, the gauges are now
        • Channel 1 : RGA line full-range gauge: 2.55E-1 mbar
        • Channel 2 : Main chamber full-range gauge: 2.60E-1 mbar
        • Channel 3 : Pump line Pirani gauge: 2.94E-1 mbar
        Compare this to the scroll pump manual , Table 1, page 3, the ultimate pressure of the scroll pump is 2.5E-1 Torr (3.3E-1 mbar), we thus managed to achieve scroll pump ultimate pressure
      6. Turn on turbo pump : Change turbo pump controller from REMOTE to FRONT PANEL mode by pressing both "COUNTERS" and "MEASURE" buttons at the same time, select "MODE=FRONT"
      7. Shorting interlock pin: since we do not have an interlock signal for the controller, use the provided DB-9 connector that has pin 3 and 8 shorted and connect this to the P1 IN connection at the rear of the controller (see attachment 1 )
      8. Press "START" on the controller to start the turbo pump
      9. The pressure readout from the gauges quickly dropped down. After 3 minutes, the Pirani range is maxed out at 0.5E-3 mbar. After 20 minutes, we recorded the following values:
        • Channel 1 : RGA line full-range gauge: 1.50E-5 mbar
        • Channel 2 : Main chamber full-range gauge: 1.89E-5 mbar
        • Channel 3 : Pump line Pirani gauge: 5.0E-4 mbar
        This is Medium vacuum , we want to further reduce this by 2 orders of magnitude. However, we can run RGA test + helium leak test at this pressure
      10. Turn off turbo pump, wait for 10 minutes, turn off scroll pump, open Up-to-Air valve, all pressure gauges indicated pressure returned back to atmospheric pressure

      3. To-do actions

      • Run RGA test to get information about contamination status of vacuum
      • Implement suggested changes in section 2
      • Check and modify suspected poor connection: Pirani gauge on pump line. A gap can be seen between connection. There's no good way to tighten it with the screw. Maybe use threaded pin + hex bolt?
      • Controller communications
      Entry  Tue May 2 15:55:33 2023, Peter, Update, VLC Electronics, 532nm Intensity Measurement IMG-0221.jpgIMG-0222.jpggraphs(1).jpgTime_Series_Trial_2.png
      I changed the 1/2 wave plate from the lens mount to the rotational optic mount. This allowed me to rotate the 1/2 wave plate, which changed the respective polarization power transmitting through S and P polarization. Initially, more power was coupled into the P polarization. Now, with the 1/2 plate rotated, both channels are experiencing the same voltage reading. Before feeding the PDA signals into the red pitaya, a 50 ohm terminator had to be placed at the SMA connection port so that the input power into the red pitaya did not exceed 1V. With this configuration, both channels experience about 0.35mV. (See attached) I then opened the Jupyter notebook, and ran a demo time series measurement from the red pitaya. This time, I was able to get a plot featuring both channels (green is P polarization. Blue is S polarization). The plots are consistent with what is shown in the red pitaya oscilloscope. However, the time collection (I'm assuming) only runs for about 0.018s. I will have to write some of my own code to loop over this measurement, and collect more data.
      Entry  Mon May 1 18:56:57 2023, Peter, Update, VLC Electronics, 532nm Intensity Measurement graphs.jpgTime_Series_Trial_1.png
      I've configured the two PDA's to the Red Pitaya. I put a 50 ohm resistor connector to each red pitaya input port. This was because the oscilloscope showed that the voltage reading from the P polarization PDA was almost at 1V, which was the limit of the red pitaya. Once both S and P polarization PDA's were connected, I opened the red pitaya's oscilloscope. A screenshot of the voltage readings is shared below. Channel 1 (Yellow) is for S polarization. Channel 2 (Green) is for P polarization. It would seem that there is a significant amount of polarization in the P direction as opposed to the S direction. I then tried running the template time series measurement within the python notebook from channel 1 only. The python notebook graph is shown below. I have not figured out what are the units of time on the x axis, and I have not figured out how to change the amount of time that the red pitaya takes data. A plot of the time series measurement is shown below.
      Entry  Mon May 1 17:10:25 2023, Julian, Cao, Physics, VAC, Installing Pirani gauge and RGA probe onto to vacuum chamber PXL_20230501_225241491.jpgPXL_20230501_235854958.jpgPXL_20230501_234750795.MP.jpg

      [Julian, Cao]

      • 03:00 pm: Particle count
        1. : Zone 3
          • 0.3 um: 498
          • 0.5 um: 124
          • 1 um: 124
        2. : Zone 4
          • 0.3 um: 748
          • 0.5 um: 457
          • 1 um: 374
      • 03:32 pm: Installing Pirani gauge onto pump line
      • 03:51 pm: Finish installing Pirani gauge, start installing RGA probe
      • 04:03 pm: Finish installing PRGA probe, start routing cable from gauge controller to Pirani gauge
      • 04:30 pm: All ethernet cables are routed and connected to gauge controllers
      • 04:48 pm: Power gauge controller up, all gauges are recognised and readout shows atmospheric pressure as expected (1000 mbar)
      • 04:51 pm: End-of-work particle count
        1. : Zone 3
          • 0.3 um: 1413
          • 0.5 um: 872
          • 1 um: 623
        2. : Zone 4
          • 0.3 um: 374
          • 0.5 um: 166
          • 1 um: 166
      We also closed all the valves so we can start testing vacuum pump down of isolated volume tomorrow.

      Entry  Thu Apr 27 09:48:34 2023, Aiden, Summary, General, Batch 12 Bagging IMG_4279.jpgIMG_4278.jpg
      I took batch 12 out of the oven and put them in a bag and placed the bag inside the clean room in the first large stainless steel container. I also looked at the small gauge that we felt like needed to be baked and I can confirm that without further cleaning around the inside of the gauge it should not be connected to the main vacuum. I have attached a photo of the inside of the gauge.
          Reply  Fri Apr 28 19:39:19 2023, Cao, Summary, General, Clean and Bake Leybold TTR 91 Pirani Gauge 

      Quote:
      I took batch 12 out of the oven and put them in a bag and placed the bag inside the clean room in the first large stainless steel container. I also looked at the small gauge that we felt like needed to be baked and I can confirm that without further cleaning around the inside of the gauge it should not be connected to the main vacuum. I have attached a photo of the inside of the gauge.

       

      Following the problem with contamination particles observed in the the Leybold thermovac TTR 91, we have taken the following step to clean the gauge:

      1. Wipe with IPA-wetted Vectra Alpha: Cover the tip of a ziptide with Vectra Alpha wipe corner that has been wetted with IPA, push the wipe around and remove visible particulates
      2. Fill the gauge flange with IPA: (following Jon's recommendation to use Lesker's procedure for cleaning their Pirani gauge), flip the gauge up such that the CF flange points upward, fill the flange with IPA all the way up. Use the tip of a SSTL tweezer to agitate the IPA. Let it sits for 20 minutes, agitate every 5 minutes. After 20 minutes, pour the IPA out then spray with dry pure nitrogen
      3. Passive drying : Let the gauge sit inside the flowbench for 3 hours (3:30 pm to 6:30 pm)to ensure all IPA has evaporated
      4. Baking : Leave the gauge in oven at 50 degree C for 48 hours (maximum allowed temperature is 65 deg C, we use 50 deg C to ensure we are well below this limit). Baking started at 7pm, should finish on Sunday 7pm and ready for assembling to vacuum chamber on Monday morning

      Entry  Fri Apr 28 19:00:13 2023, Cao, Physics, VAC, Tighten CF ports on vacuum chamber TightenCF.png
      [Cao]

      After Jon's comment yesterday that some of the connection did not seem to have good metal-metal contact, in particular the gate valve connection, I went through the ConFlat connections today and retighten them. I found a lot of the CF connections are not particularly tightened and there were a lot of range left that can be tightened with the wrench. After re-tightening, the copper gaskets are not visible anymore. For example, see the attached images for the difference before and after tightening.

      Note for future installation of CF

      • After tightening the bolts/ screws in jumping order (to provide uniform torque) and there is resistance appearing in further tightening, start going through each screw/ bolts in a direction, each time applying a small torque until it resists to further tightened
      • After each time going all the bolts/ screw and returning to the starting point, one will find they can further tighten the screws/ bolts. Repeat the process until no further tightening can be achieved
      • The copper gasket should not be clearly visible at the connection

      Entry  Thu Apr 27 16:23:44 2023, Cao, Pamella and Julian, Physics, VAC, Installing vacuum system (cont.) IMG_0139.pngIMG_0136.png
        [Pamella, Cao and Julian, Shane]
      • Particles account
      • 10:37 am: Starting the particles account
        1. Zone 3:
          • 0.3u: 1662
          • 0.5u: 872
          • 1.0u: 415
        2. Zone 4:
          • 0.3u: 831
          • 0.5u: 124
          • 1.0u: 0
      • 11:14 am: Start removal of calibrated leak to install 45 deg elbow
      • 11:21 am: Elbow installed, re-install calibrated leak back on
      • 11:29 am: Finished re-install calibrated leak, start installing gate valve on pump line
      • 11:47 am: Finished installing gate valve, start installing reducing cross onto gate valve
      • 12:02 pm: Finished installing reducing cross, start installing 90 deg elbow to reducing cross
      • 12:17 pm: Finished installing reducing cross, lunch break
      • 01:24 pm: Come back to the lunch break.
      • 01:26 pm: Start installing vacuum hose to elbow.
      • 01:40 pm: Finished installing vacuum hose.
      • 01:43 pm: Start installing turbo pump.
      • 02:00 pm: finished installing turbo pump .
      • 02:10 pm: Start installing standard wall hose from turbo pump to scroll pump
      • 02:21 pm: finished installing hose onto scroll pump, start installing lid. Remove lid from chamber, insert viton O-ring. Place lid back
      • 02:30 pm: Secure lids with screw. Start installing turbo pump controller cable: Pass cable from outside (controller) up the top of clean tent and connect to 8 pin connector on turbo pump
      • 03:00 pm: Installing air cooling unit for turbo pump, found 8 M3 screws for air cooling unit in the C&B cabinet to install the fan bracket onto the back of turbo pump. Fan control cable is routed up to the top of the cleanroom to the controller
      • 03:15 pm: Installing full-range gauge cable to the controller outside cleanroom. Ethernet cables 1 and 2 are used. Cable 1 is used on the RGA line gauge. Cable 2 is connected to the main body gauge. Cable1 and 2 are connected controller's channel 1 and 2 respectively.
      • 04:00 pm: Finish installing gauges cables. Cables are routed up along the frame to the controller sitting outside the cleanroom
      • 04:15 pm: Finished. End-of-date particle count
        1. Zone 3:
          • 0.3u: 3699
          • 0.5u: 1454
          • 1.0u: 872
        2. Zone 4:
          • 0.3u: 1662
          • 0.5u: 706
          • 1.0u: 290
            Reply  Thu Apr 27 21:43:07 2023, Jon, Physics, VAC, Grounding vacuum system IMG_0141.pngIMG_0140.png

        This afternoon I made up a green 10 AWG grounding cable and connected it to the vacuum system.

        One end is tightly connected to the bottom flange of the vacuum chamber (photo 1). It is run along and up the table framing to the top of the cleanroom, where it exits into the overhead cable tray in the same location as the other power cables. It drops down from the top of the server rack all the way to the bottom, where the other end is connected to the lab's electrical ground in the rear of the 240 V UPS (photo 2).

        The connections were confirmed to be secure, but continuity testing with an ohmmeter remains to be done to confirm that the chamber and tabletop are indeed grounded.

               Reply  Fri Apr 28 18:16:57 2023, Cao, Physics, VAC, Grounding vacuum system 

        Quote:

        This afternoon I made up a green 10 AWG grounding cable and connected it to the vacuum system.

        One end is tightly connected to the bottom flange of the vacuum chamber (photo 1). It is run along and up the table framing to the top of the cleanroom, where it exits into the overhead cable tray in the same location as the other power cables. It drops down from the top of the server rack all the way to the bottom, where the other end is connected to the lab's electrical ground in the rear of the 240 V UPS (photo 2).

        The connections were confirmed to be secure, but continuity testing with an ohmmeter remains to be done to confirm that the chamber and tabletop are indeed grounded.

         

        [Cao]

        Continuity Test

        Following from Jon's grounding work on the vacuum system, I did a continuity test with the afternoon with a multimeter. The chamber is indeed grounded:
        • Chamber wall to optical table: continuity confirmed, resistance: 0 Ohm
        • Chamber wall to ground point connection on chamber: continuity confirmed, resistance: 0 Ohm
        • Turbo pump to ground point connection on chamber: continuity confirmed, resistance: 0 Ohm
        • Turbo pump to optical table: continuity confirmed, resistance: 0 Ohm
        • Optical table to chassis frame outside cleanroom: continuity confirmed, resistance: 0 Ohm
        • Front of chassis frame to earth point: continuity confirmed, resistance: 0 Ohm

        Entry  Fri Apr 28 11:21:01 2023, Peter, Update, VLC Update, Laser intensity/polarization drift measurements IMG-0183.jpg
        The Digi-key cables have arrived, and I have began implementing them in the intensity drift measurements. There was a slight problem initially in connecting the SMA to BNC cables from the photodiode to the red pitaya, since the red pitaya was way on the other side of the lab. Cao and I connected the red pitaya to a new ethernet cable that extended far enough for the red pitaya to sit comfortably on the breadboard with the optics. Right now the PDAs are not connected to the red pitaya. I have connected them to the oscilloscope in order to read out how much voltage they produce upon incidence of 532nm laser light. This was done in order to make sure that they do not surpass the limit of the red pitaya (+-1V). I have not acquired a value for the readout voltage of the PDAs since I had to go to class. I will gather this preliminary data soon.
        Entry  Wed Apr 26 18:05:41 2023, Pamella, Julian, Shane, Update, Cleanroom, cleanroom particle counts and cleaning log counts4_26_23.png
        • pre-cleaning particle counts:
          • zone 3
            • 0.3 mu: 2494
            • 0.5 mu: 748
            • 1.0 mu 124
          • zone 4
            • 0.3 mu: 374
            • 0.5 mu: 41
            • 1.0 mu: 0
        • 3:45 pm: Started wiping the surfaces(laser table,chamber, computer) inside the cleaning room.
        • 4:05 pm: Finished wiped the surfaces
        • 4:08 pm: Began vacuuming cleanroom floor
        • 4:28 pm: Finished vacuuming cleanroom floor.
        • 4:29 pm: Began mopping the cleanroom floor.
        • 5:15 pm: Finished cleanroom clean.
        • 6:00 pm: post-cleaning particle counts (full 5 zone measurement) attached below
        Entry  Tue Apr 25 11:56:37 2023, Jon, Update, VLC Electronics, Red Pataya has arrived Red_Pataya.jpg
        The Red Pataya 125-14 starter kit that we ordered for locking the 532 nm cavity has arrived. I left it laying on the optical table near the laser.
        Entry  Mon Apr 24 17:38:45 2023, Aiden, Summary, General, Clean and Bake Batch 12 IMG_4269.jpgIMG_4268.jpg
        Today I Bagged and tagged the o-rings from batch 11 and placed them inside the clean room. I also cleaned batch 12 parts in liquinox for 10 minutes and them placed them into the oven where they will undergo the following steps; 1. Ramp to 100 degC in 15 min. 2. Dwell at 100 degC for 30 min. 3. Ramp to 200 deg C in 30 min. 4. Dwell at 200 deg C for 48 hours. 5. Off
        Entry  Fri Apr 21 16:51:26 2023, Pamella, Update, General, Cleaning cables. IMG_5416.jpeg
        Cables for the vacuum system.
        • Today i wiped, bagged and tagged two cables for the vacuum system. I used IPA wipes for cleaning this two split power cord. I attached a image below.
        Entry  Fri Apr 21 15:21:18 2023, Pamella, Update, FLIR,  AcquisitionImage(Apr-21-2023_14_26).jpg
        FLIR project updates
        • 01:50 pm: Starting test position 34 mm distance to black wall.
        • Parameters : 0.100 A, 1.5 V and the temperature inside the mirrors 40°C.
        • 2:09 pm : Finished the test and figured out this position it is too far the black wall so now we change for more close position.
        • 2:17 pm: Starting test in another position: 10 mm distance to the black wall( this measurement is between the black wall and the aluminum lid)
        • 2:26 pm : Finished this second tried and take a snap. The image is attached below.
        • The name for the picture for this tried is “AcquisitionImage(Apr-21-2023_14 26)”.
          Note: The second tried the temperature didn't up more than 40°C for 8 minutes so I change the current for a few seconds. I started with 0.98 A with 1.7 V and up until 0.350 A with 2.5 V, just for a few seconds and in this way the temperature up to 72°C and I get the snap.
            The next step should be understand the problem with the shape and work in changes for get the triangle in the FLIR image.
        Entry  Wed Apr 12 16:13:19 2023, Cao, Physics, VAC, Vacuum prep and installation VacAssy230412.png
        Aiden, Pamella, Peter, Shane, Cao

        Today we started vacuum chamber assembly work

        • 10:16 am: Particle count measurement of clean room
        • 10:34 am: Particle counting finished: meets ISO 5 standard
          1. Zone 3 :
            • 0.3 u: 3159
            • 0.5 u: 789
            • 1.0 u: 83
          2. Zone 4 :
            • 0.3 u: 498
            • 0.5 u: 41
            • 1.0 u: 0
        • 10:45 am: Assemble vacuum feedthrough
        • 11:08 am: Finish assembling feedthrough
        • 11:14 am: Assemble inverted magnetron pirani gauge
        • 11:29 am: Finish assembling magnetron gauge
        • 11:31 am: Assemble calibrated Ar Leak
        • 11:47 am: Finish assembling Ar leak
        • 11:49 am: Assemble up to up-to-air valve
        • 11:59 am: Finish assembling up-to-air valve
        • 12:00 pm: Break for Lunch
        • 1:00 pm: Came back from lunch
        • 1:20 pm: Assemble 45 degree elbow [RGA Line]
        • 1:35 pm: Finish assembling 45 degree elbow
        • 1:35 pm: Assemble Reducing nipple [Pump Line]
        • 1:49 pm: Finish assembling Reducing nipple
        • 1:53 pm: Attempt to install gate valve [Pump line] but bolts could not fit to the gap between 2.5" reducing nipple (0.95" length, shortest 5/16 bolt is 1.5" in total length).
          Thickness of of CF flange on reducing nipple is 0.75" inch. Ideally, we want to have 0.2" engagement to the gate valve, thus0.95" + 0.25" head thickness = 1.2" > 0.95" gap.
          We thus most likely will need a replacement for the reducing nipple. We decided we would hold up on installing the rest of the pump line until we have got components to fix this problem

        • 2:05 pm: Assemble gate valve [RGA line]
        • 2:15 pm: Finish assembling gate valve [RGA line]
        • 2:18 pm: Assemble 4-way cross [RGA line]
        • 2:30 pm: Finish assembling 4- way cross [RGA line]
        • 2:37 pm: Assemble manual bellow sealed angle valve [RGA line]
        • 2:43 pm: Finish assembling sealed angle valve [RGA line]
        • 2:45 pm: Assemble inverted magnetron pirani gauge [RGA line]
        • 2:55 pm: Finish assembling magnetron pirani gauge [RGA line]
        • 2:56 pm: Assemble vacuum hose, thin wall [RGA line]
        • 3:04 pm: Finish assembling vacuum hose, thin wall [RGA line]
        • 3:45 pm: Packing up for the the day
        • 4:00 pm: End-of-date particle count measurement
          1. Zone 3
            • 0.3 u: 1080
            • 0.5 u: 124
            • 1.0 u: 83
          2. Zone 4
            • 0.3 u: 540
            • 0.5 u: 83
            • 1.0 u: 83

            Reply  Fri Apr 21 00:06:43 2023, Jon, Update, VAC, Vacuum prep and installation - parts have arrived SS_parts.png

        The two parts needed to complete the vacuum assembly (ELOG 70) have arrived.

        • (10) 5/16"-24 x 1 3/4" threaded rods - for attaching the turbo pump reducing nipple to the CF 4.5" gate valve;
        • (1) 45 degree CF 2.75" elbow for attaching the calibrated Ar/He leak to the chamber.

        I left them laying on top of the ultrasonic washer. They both need to cleaned and baked following the standard procedure for stainless steel, as the threaded rods are visibly dirty.

        Entry  Wed Apr 19 17:39:50 2023, Pamella, Update, FLIR, FLIR project AcquisitionImage(Apr-19-2023_10_23)(1).jpgAcquisitionImage(Apr-19-2023_10_57)_(1).jpgAcquisitionImage(Apr-19-2023_11_18)_(2).jpg
          FLIR project updates- Initial tests
        • 10:00: Starting test in position 2 cm to the black wall.
        • Parameters : 0,305 A, 05,5 V and the temperature inside the mirrors 141,8°C.
        • 10:23 Finished this first tried and take snap. The image is attached below.
        • The name for the picture for this tried is “AcquisitionImage(Apr-19-2023_10 23)”.
        • 10:37. Starting test in another position now 3 cm distance to the black wall ( this is more close than the original position.)
        • Parameters : 0,348 A, 05,5 V and the temperature inside the mirrors 160,3°C.
        • 10:57 Finished this second tried and take a snap. The image is attached below.
        • The name for the picture for this tried is “AcquisitionImage(Apr-19-2023_10 57)”.
        • 11:03 Starting test another position 1.3 cm distance to black wall.
        • Parameters : 0,347 A, 05,5 V and the temperature inside the mirrors 158,7°C.
        • 11:18 Finished this second tried and take a snap. The image is attached below.
        • The name for the picture for this tried is “AcquisitionImage(Apr-19-2023_11 18)”.
          The next step should be fix the problem with the shape (aluminum foil lid).
        Entry  Mon Apr 17 17:06:49 2023, Aiden, Summary, General, Clean and Bake batch 11 IMG_4262.jpg
        Cleaned the Viton O-Ring for the main chamber in Liquinox for 10 minutes. Then put it in the oven to back for; 1. Ramp to 100 degC in 15 min. 2. Dwell at 100 degC for 30 min. 3. Ramp to 180 degC in 30 min. 4. Dwell at 180 degC for 24 hours. 5. Off Note: There were three viton -rings in the bag sent to us. I cleaned and baked 2 of them and left the third in the bag.
        Entry  Wed Apr 12 16:17:50 2023, shane, Update, General, Particle Counter moved IMG_6693.HEIC
        With the added height of the new docking station, the particle counter no longer fits under the Windows monitor in the electronics rack and has been moved to the desk in the corner of the lab.
        Entry  Wed Apr 12 10:53:02 2023, Aiden, Summary, General, Valve Cleaning 
        Bagged and Tagged the parts from batch 10 and placed them inside the clean room. Then cleaned the last gate valve in liquinox for 20 minutes (10 minutes each side). Then dried the valve, bagged, tagged, and placed it inside the clean room.
        Entry  Tue Apr 11 17:56:15 2023, Pamella, Update, General, Lab cleaning  
        Today Pamella and Julian finished cleaning of the cleanroom, starting with the HEPA vacuuming, mopping and clearing all floor with IPA wipes. Also we wiped down some surfaces of the blue table, computer table and the top of chamber.
        Entry  Tue Apr 11 13:15:40 2023, Cao, Infrastructure, Clean &amp; Bake, Nitrogen gas tank replaced 
        The nitrogen gas tank has been replaced with a new unit. The new tank is ultra pure nitrogen (>99.9% nitrogen). The new tank has been placed and secured to the rack where the old one is; cap is removed and regulator is reinstalled onto the new tank.
        Entry  Fri Apr 7 09:48:09 2023, Pamella, Update, General, Clean the system parts 7x
        Pamella and Julian wiped and tag system parts for the vacuum machine. We used isopropyl and vectra wipes in the most import pieces: Inverted magnetron pirani gauge and the air cooling kit 81. The other parts we uses the IPA wipe for cleaning. So for now we finished with ever system parts which was in the gabinetes. I put photos below. The photos is for all part we cleaning, tag and which puted inside the cleaning room.
        Entry  Thu Apr 6 10:20:43 2023, Peter, Update, VLC Update, Laser intensity/polarization drift measurements Optical_Setup_4-6-23.jpg
        More optical components were added to the optical set up for laser intensity / polarization drift measurements. Both lenses and both PDs were added to the configuration, as seen in the image below. The beam is already well aligned into the center of both of PDs, and focused nicely by the lens. Both PD's take BNC connecting cables, and the Red Pitaya takes SMA connecting cables. Since we are currently without a BNC to SMA cable, and we do not want to cut, strip, and crimp what we have, then measurement process cannot proceed until we get the cables.
        Entry  Tue Apr 4 16:52:08 2023, Jon, Update, Cleanroom, Particle counter docking station Met_One_Dock.png
        Due to the problems we have encountered trying to serially communicate directly with the Met One DR-528 particle counter, I went ahead and ordered the add-on communications/charging dock. The dock "ethernetizes" the serial communications by wrapping them in TCP packets and transmitting them over the lab network. This will allow our Python code to communicate using the standard Internet sockets package, rather than PySerial, PyNut, etc. the docking station arrived today and I delivered it to the lab. I left it laying next to the particle counter in the electronics rack.
        Entry  Tue Apr 4 16:43:53 2023, Jon, Update, VLC Electronics, Additional Thorlabs PDA10A2 PDA10A2.png
        I ordered a second PDA10A2 and mounting post + spacer (which puts the aperture at the VLC's standard 3" beam height). These arrived today and I delivered them to the lab. They are sitting on the VLC table near the laser.
        Entry  Tue Apr 4 09:53:37 2023, Peter, Update, VLC Update, Laser intensity/polarization drift measurements initial_Intens_measure_set_up.jpg
        The set up for the next round of beam characterization measurements has begun. The beam is initially passing through a half waveplate, is split at a polarizing beam splitter, and then stirring mirrors are used to properly aim the beam into photodiodes (not yet installed). This is the current configuration of the set up.
        Entry  Tue Apr 4 09:39:58 2023, Peter, Update, VLC Electronics, 532 M2 Measurements OmegaY_M2_Fit_8.pdfOmegaX_M2_Fit_8.pdfM2_Measurements_Set_Up.svgBeam_Data_8_3lens.txt
        Final M squared measurements were taken Wednesday, 3/29/23 by Peter and Ryan Hinosawa. 5 separate sets of data were taken, and upon discussion, we declared the plots shown below in attachment 1 and 2 as the final plots of our M squared measurements. The optical design of the M squared measurement process is given in attachment 3. The laser and three lenses shown below are mounted on the optical table. The track is placed behind the third lens, and the camera is moved along the track to take successive measurements of the beam's width. This will allow us to see a change in the beam's width over its propagation direction. The raw data is given in attachment 4 as a Beam_Data_8_3lens.txt file. This is eventually what gets used to generate the plots shown below. The code to run the analysis on these measurements (as well as analysis on the Gaussian intensity profile fitting) can be found: git@git.ligo.org:uc_riverside/visible-light-cavity.git
        Entry  Mon Apr 3 17:04:05 2023, Aiden, Summary, General, IDP Scroll Pump Assembly IMG_4244.jpg
        Aiden installed the isolation valve and the exhaust silencer kits on the IDP-3 Scroll pump. The entire assembly still needs to be wiped down but overall no residue came off when putting on the kits.
        Entry  Fri Mar 31 14:23:13 2023, Pamella, Update, General, Clean and bake batch 11 4AC705B8-D906-47E3-86E4-49E4967910E7.jpeg
        Today I bagged and tagged batch 11. I wiped the some tools: Centering ring alum( 2 pieces), reversible ratcheting, gasket removal (CF). After wiped that I bagged and tagged this parts and put inside the cleanroom. Also I wiped one power cable (3 meters), bagged and tagged that and inside the cleanroom. I put photo below.
        Entry  Wed Mar 29 16:00:36 2023, Pamella, Update, Cameras, FLIR project  15D13FE3-48A9-4ACF-9422-07032DD8D028.jpeg
        Today Pamella and Tyler started work in the updates for the FLIR project. We trie for the first time cover the mirrors with aluminum foil and run the code with this. We work in figured out how the python codes works with real datas. To do: Understand how get the real datas and how to compere that with the old datas. Starting test with the FLIR and mirrors with aluminum foil in with the power on. Testing the FLIR camera more times with the mirrors covered with aluminum foil.
        Entry  Fri Mar 24 13:36:17 2023, Pamella, Update, General, Clean and Bake batch 10 260AEB73-02D0-4635-93B3-B2EB3269FB84.jpeg59FD199A-A444-439A-8D51-C242B65BBECD.jpeg9A48A0EE-5EFE-409D-ACC0-17011F6F7EBF.jpeg950F85B7-D304-4724-AB3D-B606E422F1E3.jpeg
        Today I bagged and tagged batch 10. I wiped the RGA vacuum component for around 25 minutes after that I bagged and tagged this part and put inside the cleanroom. The RGA vacuum component have a big size and because off that i used the big bag. I wiped one power cable (2 meters), bagged and tagged that and inside the cleanroom. For the parts in the oven, a bunch of screws, I bagged and tagged the screws and put inside the cleanroom. I put photos below about this process.
        Entry  Wed Mar 1 21:50:46 2023, Jon, Infrastructure, Computers, Workstation 2 (ws2) mounted on cleanroom cart ws2_cart-1.jpegws2_cart-2.jpeg

        The Linux workstation (ws2) that used to sit on the blue workbench (now inside the cleanroom) has been mounted on a mobile cart, as pictured below. This is intended to be a clean cart that will be housed inside the cleanroom.

        The cart is currently dirty and will need to be throughly wiped down (along with the computer monitor and peripherals) prior to being moved into the cleanroom. Once the cleaned cart has been moved inside, it should never be brought back outside the cleanroom and should never be touched with ungloved hands.

        I also upgraded the OS to Debian 11.6 and upgraded the CDS workstation tools.

            Reply  Fri Mar 24 07:14:38 2023, Jon, Infrastructure, Computers, Workstation 2 (ws2) mounted on cleanroom cart 
        The ws2 cart has been thoroughly wiped down with IPA wipes and moved inside the cleanroom. I have reconnected it to power and Ethernet (cables bundled and ran to the server rack just outside the cleanroom). It is ready for use.

        Quote:

        The Linux workstation (ws2) that used to sit on the blue workbench (now inside the cleanroom) has been mounted on a mobile cart, as pictured below. This is intended to be a clean cart that will be housed inside the cleanroom.

        The cart is currently dirty and will need to be throughly wiped down (along with the computer monitor and peripherals) prior to being moved into the cleanroom. Once the cleaned cart has been moved inside, it should never be brought back outside the cleanroom and should never be touched with ungloved hands.

        I also upgraded the OS to Debian 11.6 and upgraded the CDS workstation tools.

         

        Entry  Thu Mar 23 18:40:08 2023, Julian, Update, General, Cleanroom Update 
        Today Pamella and I came in to Hepa vacuum and mop the floor of the cleanroom for general maintenance.
        Entry  Wed Mar 22 15:25:00 2023, Shane, Update, General, Clean room recertification particle counts  counts3.22.23.pdf
        Attached are the five zone particle measurements for the clean room now that the fan speeds have been set to MEDIUM. 2 min sample time, 3 samples per zone. The occupied clean room measurements were unusual in that they generally got larger towards minute 6 instead of settling and going to zero, and for this reason didn't stay beneath the class 5 requirement at the end of the samples. The unoccupied counts look more similar to what was expected, and generally settle under the class five requirement.
        Entry  Wed Mar 22 12:16:20 2023, Jon, Infrastructure, Cleanroom, Experimenting with HEPA fan speeds 

        Jon, Cao

        In effort to try to reduce the noise level inside the cleanroom, we have dialed all four HEPA fan-filter units (FFUs) down from HIGH to MEDIUM speed. These dials can only be accessed from inside the cleanroom, by bringing in the large ladder and opening adjacent ceiling tiles.

        We tested three configurations, in each case with all the FFUs on either HIGH (initial state), MEDIUM, or LOW. We measured the ambient noise in each configuration.

        Fan speed Noise inside cleanroom (dB) Noise outside cleanroom (dB)
        HIGH 80 70
        MEDIUM 74 66
        LOW 71 66

        Going from HIGH to MEDIUM yields the largest improvement, reducing the ambient sound intensity by 6 dB (i.e., by a factor of 4, corresponding to a ~35% reduction in perceived volume).

        An additional 3 dB of noise reduction can be achieved by further reducing the fan speeds to LOW. However, even after allowing some extended settling time (few hours), we found the particle counts to be fluctuating right at the threshold zone for ISO Class 5. Thus we dialed the fan speeds back up to MEDIUM with the expectation that this will be sufficient for Class 5 performance.

        The cleanroom now needs to be recertified with a fresh round of five-zone particle count measurements.

        Entry  Fri Mar 17 19:46:39 2023, Aiden, Summary, General, Clean and Bake batch 9 IMG-4208.jpgIMG-4209.jpg
        Bagged and Tagged the reflector arms and bases and placed them inside the clean room. Total of 2 bags used. Cleaned and Baked parts in batch 9 on the spread sheet and used the following procedure; 1. Ramp to 100 degC in 15 min. 2. Dwell at 100 degC for 30 min. 3. Ramp to 200 degC in 30 min. 4. Dwell at 200 degC for 48 hours. 5. OFF Also soaked the 2.75" CF gate valve in acetone to try and clean the open threads around the part. Then cleaned it in the ultrasonic washer with liquinox for 20 minutes (10 minutes each side). It looks better than it used to but the threads still seem to be the problem and will probably need even further cleaning.
        Entry  Tue Mar 14 18:21:41 2023, Aiden, Summary, General, Clean and Bake batch 8 
        Starting off Peter and I refilled the deionized water barrel. Then Aiden Cleaned and Bake the FROSTI arms and bases in liquinox for 5 minutes. Then placed them in the oven where they will undergo the following steps; 1. Ramp to 100 degC in 15 min. 2. Dwell at 100 degC for 30 min. 3. Ramp to 120 degC in 30 min. 4. Dwell at 120 degC for 48 hours. 5. OFF Also cleaned the 2.75 MDC Gate valve for 20 minutes (10 minutes each side) in liquinox. It looks significantly cleaner in areas I could not reach before. However some areas like the flat bottom threaded holes are still very dirty. I also made sure to dry it thoroughly and wrapped it in UHV foil until I further cleaning is decided.
        Entry  Fri Mar 10 12:08:09 2023, Peter, Update, VLC Electronics, 532 M2 Measurements OmegaX_M2_Fit_4.pngOmegaY_M2_Fit_4.png
        Took more M2 laser data today. The configuration is the same as before except now the beam camera is the only component moving. Pictures can be seen below. The beam shape in x and y is very consistent with low error. However, the M2 value is still a bit high.
        Entry  Thu Mar 9 13:51:42 2023, Shane, Update, General, Clean room counts 3/9/23 particlecounts3.9.23.pdfclean_room_zones.JPG
        Here's the clean room counts from this morning. Also attached is rough diagram of where the five zones are in the clean room. Counts taken with 2 minute sample time, three samples in each zone.
        Entry  Thu Mar 9 12:03:59 2023, Peter, Update, VLC Electronics, 532 M2 Measurements OmegaY_M2_Fit_3.pngOmegaX_M2_Fit_3.pngoptical_setup.jpg
        Took more M2 Data today. Picture of the optical set up is shown below. lens1 f = 100mm, lens2 f = 50mm, lens3 f = 150mm. There was a nice converging/diverging beam profile, and the beam waist was able to be read by the camera. I took as much data as I could before clipping loss. The M2 value is quite high.
        Entry  Wed Mar 8 19:29:00 2023, Aiden, Summary, General, Clean and Bake batch 7 IMG_4180.jpgIMG_4182.jpg
        Today gave another cleaning to the MDC gate valve. It is still very dirty an will need more cleaning. I also cleaned the other 3 valves and the argon leak. These are also in bags inside the clean room. I cleaned them by hand with IPA wipes and had to specifically give the MDC up to air valve a harder clean with acetone as it was not getting clean with the IPA. This valve still has a ring around the face as shown in the first image. Be very cautious when moving the parts in the large ESD bag, it may be heavy and the parts will move inside.
        Entry  Wed Mar 8 18:35:52 2023, Pamella, Update, , Lab cleaning  
        Today Pamella finished cleaning of the cleanroom, starting with the HEPA vacuuming, mopping and clearing all floor with IPA wipes. Also Pamella and Julian finished cleaning of lab floor, starting with the HEPA vacuuming and mopping. Shane and Pamella wiped down every surfaces of the laser table, computer table and the table with the vacuum pieces inside the cleanroom. Shane, Peter, Tayler, Pamella and Julian then wiped down every surface of the laser table outside the cleanroom. We wiped the main tabletop as well as the legs and all parts for the table. We wiped the computer desk, the boxes, the cabinets and every part outside the cleanroom. For now we finished the lab cleaning.
        Entry  Mon Mar 6 18:48:43 2023, Pamella, Update, General, Cleanroom update  203863E0-106A-465E-8D9C-461B0358FB60.jpeg779F360D-CAD0-4C49-AE0B-973F97F6D099.jpeg276B9F0C-6661-441F-AD34-D79DA61E1FC3.jpeg
        Today Pamella and Julian finished cleaning of the new lab cabinets. Also we wiped the computer and put inside the cleanroom so now the computer is not move out side anymore. We saw some dirty parts in the cleanroom floor again and is possible for the next step we should be clearing the floor one more time. Possible is necessary order more IPA wipes for keep cleaning in nexts weeks. A photos of the cabinets and the computer are attached below.
        Entry  Mon Mar 6 15:32:58 2023, Jon, Infrastructure, General, Cabinet installation completed IMG_0088.jpgIMG_0089.jpg

        Jon, Cao, Peter

        This morning Facilities delivered and installed two new cabinets with sliding glass doors.

        The smaller of the two (36" W x 13" D x 84" H) has been installed in the Clean & Bake area adjacent the flow bench. The larger one (48" x 16" D x 84" H) has been installed in the back of the room next to the electronics bench. Both cabinets have been securely anchored to the wall in two places each for earthquake safety.

        We also installed the sliding glass doors and leveled them. However, we have not installed any of the shelves yet because the cabinets are quite dirty from the installation. Everything needs to be wiped down with IPA wipes, and it will be easier to do that before the shelves are in place.

        Entry  Sat Mar 4 00:34:46 2023, Julian, Update, General, Cleanroom Update 
        Today I was able to finish cleaning the frame of the laser table, and for good measure I wiped down the tabletop and exterior of the vacuum chamber when I was finished. I was also able to go through and wipe down the bags containing the vacuum parts as well as the tabletop of the workbench.
        Entry  Fri Mar 3 19:13:33 2023, Aiden, Summary, General, Clean and Bake Batch 6 IMG_4173.jpgIMG_4174.jpg
        Started to clean the dirtiest of the valves. I could not finish but I definitely made good progress on it. The MDC valve is very dirty and there are many places I could not reach with my fingers. I used Acetone and IPA for this first round of cleaning on it. I also was going to bag the viton O-Ring from the previous Batch, however it seems to have broken during the bake and I am leaving it inside the oven for now.
        Entry  Thu Mar 2 20:53:56 2023, Julian, Update, General, Cleanroom Update 
        Today Pamella and Julian began the final cleaning of the cleanroom, starting with the HEPA vacuuming and mopping then wiping down every surface of the laser table. We wiped the main tabletop as well as the legs, but we were unable to completely wipe down the upper frame of the table before we had to leave. For next steps, Julian will come in on Friday and finish cleaning the frame, then both of us will come in on Monday to finish the final cleaning.
        Entry  Wed Mar 1 21:27:20 2023, Jon, Infrastructure, Cleanroom, Over-table shelf height raised cleanroom-shelf.jpg

        Jon, Cao

        Today we raised the height of the shelf overhanging the cleanroom laser table by 8 inches. This was done to create more vertical clearance between the top-loading vacuum chamber and the bottom of the shelf. The added clearance should make both removing the chamber lid and inserting large parts easier.

        The procedure required unmounting the shelf and removing all eight vertical support posts (1" x 1" x 18.5" pieces of 80/20 unistrut). The support posts were taken to the machine shop and cut, retapped, and cleaned (coarsely, with IPA wipes) prior to reinstallation. We took care to minimize the contamination introduced into the cleanroom, but some amount of particulate from disturbing the shelf was unavoidable.

        This work is completed, and the cleanroom is now ready for final cleaning (HEPA vac, mopping, and wiping down of all surfaces including the softwalls).

        Entry  Tue Feb 28 19:37:22 2023, Aiden, Summary, General, Clean and Bake batch 5 IMG_4168.jpgIMG_4169.jpgIMG_4170.jpg
        Bagged and Tagged batch 4 parts by placing no more than two part numbers per bag and taped them with kapton tape and labeled them with their name and part number. Then placed them in the clean room on the work bench. Cleaned batch 5 part (Viton O-Ring) with liquinox and placed the into the oven for 5 steps; 1. Ramp to 100 degC in 15 minutes. 2. Dwell at 100 degC for 30 minutes. 3. Ramp to 180 degC in 30 minutes. 4. Dwell at 180 degC for 48 hours. 5. Turn off and cool down to room temperature. To see the specific parts in batch 5 please refer to the Clean and Bake spread sheet on the Richardson lab page: https://docs.google.com/spreadsheets/d/19gnv1q9l64gxnq76KfcXizbqShJfK0ayn2Js1SiAZok/edit#gid=1765414234 Hand cleaned stainless steel containers and silver coated screws. Designated each container with its contents with the label maker and placed inside the clean room. Should be noted that the fasteners were very clean before the hand cleaning and showed not dirt on the wipes. Added these parts to the clean and bake data base sheet and designated the type of cleaning as "rough cleaning". Gabriella helped with this cleaning and today was her first day in the lab.
        Entry  Tue Feb 28 19:33:51 2023, Peter, Update, , 532 M2 Measurements 
        Y axis of plot in units of micrometers. X axis in units of millimeters.
        Entry  Tue Feb 28 19:31:05 2023, Peter, Update, VLC Electronics, 532 M2 Measurements X_width_and_Y_width.png
        Took M2 measurements today. Configuration: Lens 1 (f = 50mm) at 0mm. Lens 2 (f = 150mm) at 200mm, camera at 350mm. The laser beam was being moved in -z direction on track (so further away from the first lens). Quick data shown in the sheets plot. Not a real fit. I was trying to see where the beam waist was if there even was one. Seems that it is much further than we have room for on the track. Will need to come back and take more data. I suggest maybe Dr. Richardson or Cao come and see the configuration in person and how the beam diverges for themselves on the detector card. Maybe they can offer pointers to make this go smoother.
        Entry  Tue Feb 28 13:53:17 2023, Pamella, Update, General, Vacuum chamber cleaning  EE5E0296-D362-4EA6-B482-85A629D93B46.jpeg4C0AA805-667E-45AD-8704-03389BD63489.jpeg51CE3D1E-F48E-4F57-8450-8F58C27154BB.jpeg58ADE656-52AD-4F0E-88BA-B993F977A519.jpeg
        Pamella, Dr. Richardson and Dr.Cao finished checking and cleaning the interior of the chamber, chamber lid, and exterior of the chamber with Vectra Alpha wipes, IPA and in some parts we used acetone . We flip the chamber and put chamber on the table again. A picture of the specific situation is attached below. The next step from here would be to finish the cleaning the floor . The black residues on the side of the table probably is some reaction between the Vinil and the wipes so is not necessary cleaning this part deeply.
        Entry  Mon Feb 27 17:09:04 2023, Pamella , Update, General, Vacuum Chamber Cleaning Side_of_Table.jpegWipes_from_table.jpeg
        Pamella and Julian finished cleaning the interior of the chamber, chamber lid, and the table. We found some black residue on the side of the table but not sure what the issue is. A picture of the specific area of the table that is giving off the black residue is attached below. The next step from here would be to flip the chamber on its side and finish the cleaning the exterior.
        Entry  Thu Feb 23 21:12:33 2023, Julian, Update, General, Vacuum Chamber Cleaning ChamberLid_inside.jpgChamberLid_outside.jpgVacuumChamber_inside.jpg
        Today I was able to come in and wipe down both sides of the vacuum chamber lid using the regular alcohol wipes and also wipes that were left to dry in the fume hood then saturated with acetone. I managed to get a good amount of the residue off both the inside and outside surfaces of the lid, then did a test wipe of both sides using acetone-soaked wipes; pictures of the wipes are attached below. Once I finished with the lid, I used another acetone wipe to test wipe the inside of the vacuum chamber. The inside is still giving off residue, but very minimally, a photo for this is attached as well.
        Entry  Thu Feb 23 13:32:55 2023, Shane, Update, General, Clean room floor particle counts 2.23.2023.pdf
        Here are the counts from the clean room floor today. The counts should be dated- the ones from today (2/23/23) are the last 8 in the chart. The first set of 2 measurements from today were under the table by the clean room entrance, the next two were under the table by the vacuum chamber, the next two were on the floor by the vacuum chamber lid, and the last two were on top of the table for comparison. All measurements were taken using 2 minute sample time.
        Entry  Tue Feb 21 17:51:04 2023, Aiden, Summary, General, Clean and Bake batch 4 IMG_4148.jpgIMG_4147.jpg
        Bagged and Tagged batch 3 parts by placing no more than two part numbers per bag and taped them with kapton tape and labeled them with their name and part number. Then placed them in the clean room on the work bench. Cleaned batch 4 parts with liquinox and placed the into the oven for 5 steps; 1. Ramp to 100 degC in 15 minutes. 2. Dwell at 100 degC for 30 minutes. 3. Ramp to 200 degC in 30 minutes. 4. Dwell at 200 degC for 48 hours. 5. Turn off and cool down to room temperature. To see the specific parts in batch 4 please refer to the Clean and Bake spread sheet on the Richardson lab page: https://docs.google.com/spreadsheets/d/19gnv1q9l64gxnq76KfcXizbqShJfK0ayn2Js1SiAZok/edit#gid=1765414234
        Entry  Fri Feb 17 19:12:39 2023, Aiden, Update, General, Clean and Bake batch 3 IMG_4126.jpgIMG_4125.jpg
        Bagged and Tagged batch 2 parts by placing no more than two parts per ESD bag then taped them with kapton tape and tagged them with their name and part number. Than placed them inside the clean room on the work bench. Total of 3 Bags used. For Batch 3- Cleaned all copper gaskets with liquinox for 10 minutes, dried them off with nitrogen, then placed into oven where the are currently undergoing the following steps; 1. Ramp to 100 deg C in 15 minutes. 2. Dwell at 100 degC for 30 minutes. 3. Ramp to 175 degC in 30 minutes. 4. Dwell at 175 degC for 24 hours. 5. Turn off and cool down to room temperature. To see the specific parts in batches 2 and 3 refer to the clean and bake data sheet. https://docs.google.com/spreadsheets/d/19gnv1q9l64gxnq76KfcXizbqShJfK0ayn2Js1SiAZok/edit?skip_itp2_check=true#gid=1549161924
        Entry  Mon Feb 13 18:57:53 2023, Aiden, Summary, General, Clean and Bake batch 2 
        Cleaned second batch of SS parts with liquinox for 20 min. Then put in oven for 5 steps; 1. Ramp, 100 degC, 15 min 2. Const, 100 degC, 30 min 3. Ramp, 200 degC, 30 min 4. Const, 200 degC, 48 hours 5. Ramp, 25 degC, (off).
        Entry  Sat Feb 11 17:09:29 2023, Shane, Update, General, clean room particle counts 2/10/23 occupied2.10.23.pdfunoccupied2.10.23.pdfparticlecounts2.10.23.PDF
        Took a round of clean room counts after the latest clean of vacuum chamber on Feb 10. Used 60 second sample time, 5 samples for each of the 5 zones. Plots attached for both occupied clean room (one person inside, attachment 1) and unoccupied clean room (empty attachment 2), as well as the raw data from the particle counter (attachment 3).
        Entry  Sat Feb 11 00:17:27 2023, Julian, Update, General, Vacuum Chamber Cleaning 20230210_181404.jpg20230210_181424.jpg20230210_181541.jpg20230210_181606.jpg
        Today I finished wiping down the rest of the vacuum chamber, specifically focusing on the connecting ports and outside surface of the chamber. When I was finished, I test wiped every surface of the chamber and took pictures confirming the current state of cleanliness; Attachment 1 "Wipes for top and bottom of chamber's upper lip." Attachment 2 " Top and bottom of chamber's lower lip." Attachment 3 "Inside and Outside main chamber." Attachment 4 "Inside connecting ports."
        Entry  Fri Feb 10 16:34:45 2023, Huy Tuong Cao, Infrastructure, Clean & Bake, Nitrogen gas tank ready to use AirGunSealed.jpg
        Cao,

        Today I fixed the final bit related to the nitrogen gas tank, which is to apply sealing tape to M-NPT connector of the hose to prevent leakage (file: AirGunSealed.jpg)
        After application of the tape, no audible leak can be heard from connection between the hose and the air gun.

        The general operating procedure for the gas tank is as following:

        1. Turn the regulator (blue handle) anti-clockwise still it's loose
        2. Turn the valve on nitrogen as tank anti-clockwise, immediately the RHS meter of the regulator would jump to approx 2000 psi. This is the standard pressure for high pressure gas tank
        3. Turn the regulator clock-wise slowly until the pressure one the LHS meter face reads approx 60 psi. This is sufficient for drying parts with. At this point, the flow pressure still should register zero
        4. Press the trigger on the air gun, a high pressure air flow should come out and the flow meter should increase
        5. When finished, close the gas tank valve, turn the regulator anti-clockwise, then press the air gun trigger to release gas left in the hose/gun

        Entry  Fri Feb 10 15:15:30 2023, Aiden, Update, General, Bagging First Batch 
        Aiden Bagged and Tagged the first batch of stainless steel parts shown on the google spread sheet. 1. Removed two parts from the oven. 2. Place them in the ESD bag. 3. Seal bag with Kapton Tape. 4. Create label including part name and number underneath it. 5. Put label onto the side of the bag where it is not sealed with tape. 6. Placed bagged items into clean room on work table. ps. total bags in first batch = 4
        Entry  Tue Feb 7 17:44:17 2023, Jon, Infrastructure, Computers, Workstation 1 (ws1) set up ws1.jpg
        The Linux workstation (ws1) that used to sit on the old workbench has been mounted on the new electronics bench and is now ready for use again. I upgraded the OS to Debian 11.6 and also upgraded the CDS workstation tools.
        Entry  Tue Feb 7 17:27:30 2023, Aiden, Physics, ELOG, Clean and Bake Batch #1 
        Cleaned SS parts with liquinox for 20 min. Then put in oven for 5 steps; 1. Ramp, 100 degC, 15 min 2. Const, 100 degC, 30 min 3. Ramp, 200 degC, 30 min 4. Const, 200 degC, 48 hours 5. Ramp, 25 degC, (off) PS. Ultrasonic washer does not have heating feature.
        Entry  Mon Feb 6 20:02:32 2023, Julian, Update, General, Cleanroom Update 
        I wiped down the main table (including frame, legs, and transparent shelf) and workbench using alcohol wipes. Once I cleaned all of the surfaces, I used the Hepa vacuum to pick up any fallen debris.
        Entry  Sat Feb 4 17:01:03 2023, Peter, Update, VLC Electronics, Laser Data OmegaX_M2_Fit_3.pngOmegaY_M2_Fit_3.png
        Peter and Ryan took laser beam data. Configuration: 100mm focal length lens is ~100mm from lens. 150mm focal length lens is ~200mm from first lens. Beam waist is ~420mm from second lens. Beam waist is very small still. Had to input large amounts of error in data collection. Took width data successively at points near waist and at >= Rayleigh range. Plots are shown below. Key points: Took a while to figure out optimum configuration for lenses to be placed so that an accessible beam waist could be obtained. Beam waist is still very small. May need to do an ABCD calculation to see if there is anything bigger that can be obtained.
        Entry  Fri Feb 3 13:04:04 2023, shane, Summary, General, clean room particle counts 1/25/23 cleanroomcountsJan25.pdf
        Clean room count graphs for each zone (as of January 25, 2023) attached
        Entry  Fri Jan 27 18:44:31 2023, Julian , Update, General, Vacuum Chanmber Cleaning 
        I used the IPA wipes to wipe down the inside of the chamber the best I could. I cleaned the main chamber but not any of the connecting joints. When I finished I did a once over with a fresh wipe and found no residue.
        Entry  Thu Jan 26 18:58:25 2023, Aiden, Update, General, Oven Heating 
        Aiden cleaned the oven with methanol again and set the oven to 260 degC for 12 hours.
        Entry  Mon Jan 23 17:26:15 2023, Peter Carney, Update, General, Oven cleaning 
        Aiden and Cao Turned on the oven to 120 deg C for 12 hours. After 12 hours, put it at 200 deg C for 48 hours.
        Entry  Wed Jan 18 22:06:05 2023, Julian, Update, ELOG, Cleanroom Update 
        I wiped down all the inner walls of the cleanroom using alcohol wipes, as per Cao's instruction.
        Entry  Wed Dec 14 18:34:33 2022, Jon, Configuration, Electronics, Adapter for 532 nm laser power supply laser_power.png
        I installed an EU-to-US plug adapter for the 532nm laser's 9V power supply. I then re-measured the laser's power with the correct supply voltage (previously we had been using a 6V supply). At 9V, the max power is 0.83 W, so the laser is confirmed to be Class 2 as labeled.
        Entry  Wed Dec 14 17:35:41 2022, Jon, Infrastructure, Computers, Windows Laptop laptop.png

        I set up the new Windows 10 laptop (pictured below), which arrived yesterday. This laptop is intended to be used for running lightweight Windows-only programs, such as the Thorlabs beam profiler software or the SRS RGA client. However, none of that software is installed yet.

        Configuration details

        As usual, the computer is configured with one shared account (username: controls) and the standard password. Note that it is connected to the campus wifi (UCR-SECURE).

        If a connection to the lab's local network is required, then the laptop must be connected by an Ethernet cable to the switch in the top of the server rack.

        Entry  Mon Nov 28 18:10:23 2022, shane, Update, ELOG, Particle counts in the clean room clean_room_particle_counts_11_28_-_Sheet1.pdf
        Particle count stats for the clean room Nov 28, 2022: Took 10 sample runs in each of 5 regions in the clean room (5 runs per region with a person inside the clean room for the measurement, and 5 runs per region without anyone in the clean room for the measurement), for a total of 50 samples taken. Sample time was 60 seconds. Overall clean room average particle count for the size ranges are as follows: 0.3 micrometers- 3405.76 (room occupied), 974.92 (room empty) 0.5 micrometers- 409.72 (room occupied), 409.72 (room empty) 1.0 micrometers- 1102.2 (room occupied), 282.6 (room empty) 2.5 micrometers- 692.32 (room occupied), 183.68 (room empty) 4.0 micrometers- 254.28 (room occupied), 84.72 (room empty) 5.0 micrometers- 141.24 (room occupied), 84.72 (room empty) 7.0 micrometers- 56.48 (room occupied), 84.72 (room empty) 10.0 micrometers- 42.36 (room occupied, 42.36 (room empty) More statistics (including individual stats on the 5 regions within the clean room) attached.
        Entry  Mon Oct 3 17:21:39 2022, Cao, Update, TCS, Inspection of macor parts 7x
        The macor parts arrived and inspected today. These include:
        1. Macor spacer (drawing: LIGO_Redesign_Macor_Spacer_Drawing_v4.pdf attached below), quantities: 40
          • No defects, damages observed
          • Parts are free from grease/ machining fluid
          • Wall thickness of 1 mm appear to provide sufficient stiffness to part
          • Images of parts: Macor_spacer_0.jpg, Macor_spacer_1.jpg
        2. Macor 5-40 UNC screw (drawing: LIGO_Redesign_Macor_Screw_Drawing_v6.pdf attached below), quantities: 20
          • One screw broke, location of break: should edge between head and shaft (see image Macor_screw_5.jpg )
          • All other screws look ok, no damage observed, clean surface overall
          • Images: Macor_screw_0.jpg , Macor_screw_4.jpg
        Entry  Wed Aug 17 16:04:30 2022, Phoebe Zyla, Summary, Lore, Testing the Cartridge Heater and Collecting FLIR Data Screenshot_(74).pngScreenshot_(75).pngScreenshot_from_2022-08-15_11-24-40.pngAcquisitionImage(Aug-15-2022_14_16).jpg

        We have tested the heater to find emissivity, mounted the heater system to the optical table, and have taken irradiance maps of the heater projected onto the screen.

        The heater's emissivity was determined by using a thermocouple in conjunction with the FLIR's temperature calibration. To attach the thermocouple to the heater initially, I used Kapton tape and ran both the wires of the heater and the thermocouple through the heater bridge. This allowed for the heater to rest on an optical post and be observed without anyone directly holding it, but there were some measurement issues. The thermocouple had a very wide range of temperatures it was reading, which may have been due to intermittent contact or a short between the two legs of the thermocouple. To solve this and make the temperature measurements more stable, we pried apart the two ends of the thermocouple (to ensure there was no short) and put tape on either side, leaving the end connection bare. This was then taped to the heater, and the thermocouple was much more stable. We also used a K-type thermocouple that has an adhesive tape on it already, which assisted with the intermittent contact as well. With the thermocouple measuring the temperature of the heater, we could point the FLIR directly at the heater and calibrate the emissivity until the FLIR and the thermocouple agreed. Cassidy's emissivity calculator was also used, as I could input a temperature and observe what the emissivity of an area was based on that temperature. We found the emissivity of the heater to be 0.57.

        As a note, when observing the heater with the FLIR, it appeared that there was a hot spot in the center, where the Kapton tape sat. Because the Kapton has a different emissivity than the 304 stainless steel of the heater, the FLIR will read it as having a different temperature than it actually does. When using the FLIR in the future, be sure to ascertain whether there is a temperature difference somewhere or if there may be different emissivities.

        Additionally, the first heater that I used was taken to a very high temperature and oxidized. The emissivity of this oxidized heater is not known, but could be good information for knowing how oxidation affects these heaters specifically.

        To mount the heater system in front of the screen, I used 1/2'' optical posts and the mount I designed using COMSOL's CAD program. The heater was originally 2.5 inches away from the screen, and has since been moved back by an additional two inches so that we could observe the heater side of the screen with the FLIR. We wanted to see what temperature the heater side of the screen was when irradiated by the heater, and how that compared to the camera side of the screen. When the heater ran at 1.12 W of input power, the heater side of the screen had a max temperature of around 29.7 C, and the camera side of the screen read at about 29.5 C. This means that there is very little thermal loss between the two sides of the screen, and any insulation that the screen's adhesive may have is largely negligible. Additionally, the camera was placed at an angle and undetermined distance for these tests, confirming that the temperature measurements compensate well/don’t depend on changes in angle or distance between the camera and the screen. However, there was spots on the back of the screen that the camera was measuring as hot spots where there shouldn’t have been any. I have included an example below. It would be useful to run a test where the camera is directly on the back of the screen without the heater to characterize the screen and see if the hot spots are physically present on the screen or if this is an artifice of the camera because of something like angle of viewing.

        Taking irradiance maps of the screen was straightforward. After checking that the emissivity of the screen is 0.99 by viewing it at room temperature, we monitored the max temperature while slowing increasing the wattage the heater was running at. There is not a large change until the heater is at around 95 C, at which point the screen began to rise in temperature from 27 C to 28 C. We took measurements of this while the heater was 2.5 and 4.5 inches away from the screen. The irradiance map has a very symmetrical and circular shape, but does not have the ring pattern that we expected. There may be a few reasons for this: there could be some conduction between the two sides of the screen that is causing the pattern to spread further, the heater setup may not be as ideal as it was modeled to be, or there could be a different, unknown issue.

        TO DO:

        - It would be useful to run a test of the camera in multiple different positions to ensure our conclusion that the camera’s measurements don’t depend on angle or distance (or that these factors are well accounted for in the current temperature calculations) is correct.

        - Measure the back of the screen straight on to identify bright spots and possible reasons as to their appearance.

        - Recalibrate camera to ensure it is still correct after testing in multiple positions.

        - Take another irradiance map of the screen at a higher input power, as well as moving the heater close/further away to try and replicate the COMSOL irradiance maps. It would be useful to also redo the COMSOL modeling at lower powers and variable distances.

        Pictures included of full table setup, the heater mount, the heater with Kapton tape attaching the thermocouple as well as FLIR's measured irradiance map.

        Entry  Tue Jul 26 14:10:35 2022, Cassidy, Update, Cameras, Optical Post Replacement and Realignment YAxisAlignment.pngXRotZAlignment.pngNewOpticalPost.png
        Today I replaced the 3" optical post that the camera rests on with a 2" optical post in order for the screen to correctly fill out the camera's FOV. The 3" post is now in the glass optics cabinet next to the FLIR camera configuration box, wrapped in the protective materials from the 2" post for safekeeping.

        There were no issues with the physical replacement of the post, except that the fork clamp on the post needs to be on one of the perpendicular, not diagonal, axes in order to be secure. I chose the front axis (towards the screen) as before in order to easily access the alignment knobs.

        To align, I followed the same process as last time except for a more purposeful original rough alignment. For alignment purposes, the visual camera was used. For the first rough alignment, I pulled the camera as far back as possible on the x axis (with the z axis roughly centered), then moved the entire stage setup back until I could just see both the top and bottom edge of the screen. Then, I set the z-axis to an extreme in order to use the edge of the screen to align the rotational and y-axis pieces for the fine alignment.

        For the fine alignment, starting with the z and x axis at extremes, I began by aligning the rotational axis. To do this, I used the gaps between the top of the screen and the camera window on the far left and right of the image. When these gaps were equal I knew the rotation was adequately set. Then, I set the y-axis so that the pattern was centered. If the gaps were no longer even, I redid the rotation alignment and ditto with the y axis until both were set. This resulted in a rotation of about two degrees and a y axis at just under 3.5.

        To set the z and x axis, I centered the z-axis using the top and bottom of the screen, which should both be visible if the rough alignment was done correctly. Then, I adjusted the x axis by pushing it forward until the top and bottom of the screen were just out of the frame. As with the rotational and y-axis, I iteratively fine tuned the x and z axis until both the image was centered in the z axis and only the screen was in view. This resulted in a z-axis value of just over 5.5 and an x axis value of nearly 1.75.

        Pictures are included of all alignment knobs and the new post/stage setup!

        Entry  Fri Jul 22 13:20:28 2022, Phoebe, Update, , Comsol 
        I will be using comsol until 1:30 pm today. I will be updating the model for the heater mount to be thicker in certain areas, so that it can feasibly be 3D printed. Specifically, the radius of the center cartridge mount has been increased to add thickness to the pipe and the arms of the bridge. This will allow us to print with a much smaller chance for error, as the printer can print objects with a minimum length of 1 mm.
        Entry  Mon Jul 11 14:29:45 2022, Jon, Omnistructure, General, HEPA filter installed IMG_1530.png
        Today I unpacked and installed the new HEPA filter for the lab. It is an Omni CleanAir OCA1210 capable of 1200 CFM. This flow rate is sufficient to turn over the air in the room once every 4 minutes, or 14 times per hour. Hopefully this will cut down on our particulate accumulation issues.
        Entry  Tue Jun 21 18:31:49 2022, Cassidy and Phoebe, Update, Cameras, IR Absorbing Screen and FLIR Camera Setup IMG_6751.pngIMG_1146.pngIMG_6756.png
        Today we set up the IR absorbing screen and the camera on the optical table, as well as tested that the camera was functioning as expected (picking up heat sources beyond the screen).

        Screen Setup

        The screen was set up by clamping it between two rectangular posts on each side. First, two posts were set up with 22 in. between them (thus allowing the screen to span a total distance of up to 24 in. when clamped down). To best stabilize the screen and to allow for it to be "pulled" taut by exploiting the give in the L-bracket, the L-bracket was bolted on the outside of the post, along the same axis as the screen itself.

        On first attempt, the screen was too thin to be fully clamped between the posts. In order to have it fit snugly, sections of heat shrink tubing was used as a shim at the points where the posts were clamped together. The tubing was slid into the track of one optical post at the desired points. In order to accommodate the shim, the two posts had to be held together, ideally clamped, with the screen and shim in place. Then, the post clamps could be slid into the tracks of the post, moved to the optimal location, and tightened down. This required at least three people: two to tighten one side while the third holds up the screen on the other side. The screen was placed ~1/8" from the edge of the posts and flush with the top.

        Camera Stage Setup

        Once the screen was in place, the camera stage was set up by placing the XY-Translational with Rotation stage on four 3" optical posts. Then, the z-axis stage was placed in the center of that, with another 3" optical post on top, which was then topped with the camera. This was set and clamped down ~22.5" from the screen. This was about 1" closer than expected based on our theoretical models.

        Fine Alignment

        We used the visible camera to fine align the screen and to test the setup. Notably, the visible camera is placed below the infrared and thus requires a calibration in order to ensure the two are aligned on the computer image. This can be set by hand using the FLIR proprietary software (FLIR CamWeb) and adjusting the "MSX alignment". The image mode "Thermal MSX" allows both the visible and IR camera to be displayed at once and the difference in their positioning can be seen. We found an offset of ~0.5m to be nearly accurate (note: using this method, although you can get more accurate than this, the displayed value only has one significant figure).

        In order to align the camera, we first used the exposed top edge to judge whether the camera was appropriately centered on the screen. We set the rotation as close as possible to being in line by eye, then adjusted the y-axis until the gap on both corners was a similar size, thus indicating that the rotation and y-position were correctly set. Rotationally, the camera required only a refinement of -1/2 degree. The y-axis is set at 1.25. Then, the camera was pulled as far from the screen as possible using the x-axis to allow the screen to be easily centered using the z-axis. Once the outlined test mass was centered, the x-axis was used to bring the camera close until the screen just barely filled the field of view. The x-axis is at 2.25. The z axis is set to it full dynamic range at 10. Unfortunately, the camera is still slightly too tall for the screen, likely requiring the purchase of a new optical post about 0.5in shorter the current one. This interchange will likely require a new fine alignment after.

        Basic Imaging Tests

        The camera was also focused on the screen based on the manufacturer's printed distance on the camera itself (using 22.5", or 0.572 m). Using the FLIR proprietary software, the camera appears to be in focus in IR (a hand was used as a good focusing tool for this). Additionally, the camera does pick up heat on the other side of the screen. A hand can be lightly seen warming the screen, as can a soldering iron tip. This was a very imprecise visual tool, but does indicate that the camera and screen are working roughly as expected.

        Next Steps

        A new optical post that is ~2.5" tall should be ordered to replace the one under the camera currently. The heating system also needs to be ordered and set up. Currently we are debating between a parabolic reflector with a hole in the back, and one without, as each would require a different mounting mechanism for the cartridge heater.

        Entry  Thu Jun 2 21:55:02 2022, Jon, Update, Cameras, FLIR Camera Setup IMG_1473.pngIMG_1474.png

        The new FLIR A70 infrared camera has arrived. Tyler and I unpacked it in the lab yesterday. In less than an hour, we succeeded in powering it on and connecting it to the lab network. We have assigned it the static IP address 192.168.1.6.

        Online Configuration Portal

        The FLIR camera can be configured, as well as stream live data, through a web browser interface. It can be accessed from any workstation on the lab network by navigating in the browser to http://192.168.1.6. The login credentials are stored here (log in with your LIGO.ORG credentials).

        Next Steps

        The next step is to install FLIR's Python API for controlling and reading out the camera on chimay. The API comes with demo codes which we can use to test the basic connectivity and which will serve as a reference for developing our own Python interface over the summer.

            Reply  Fri Jun 3 13:03:33 2022, Jon, Update, Cameras, FLIR Camera Setup 

        Summary

        I have installed the requisite software on chimay for interfacing the FLIR A70 camera in Python. There are two packages required from FLIR:

        • Spinnaker SDK, which provides the low-level camera drivers and a C/C++ API.
        • PySpin, a wrapper of the Spinnaker library which provides the Python API.

        These installations did not work out-of-the-box for Debian 11 (only Ubuntu is officially supported). I had to make several modifications which are documented below for future reference.

        This setup has not yet been tested with the camera connected to chimay.

        Documentation and Demo Codes

        The PySpin package comes with a number of Python demo codes and a complete API reference. These can be found on chimay at the following locations.

        • Example codes: /opt/spinnaker/python/Examples/Python3/
        • Python API reference manual: /opt/spinnaker/python/docs/PySpinDoc.pdf

        Installing Spinnaker SDK

        Below were the steps required to install Spinnaker on chimay (Debian 11).

        1. Download the Spinnaker binaries (AMD64 architecture) and copy the tarball to, e.g., /home/controls on chimay.

        2. Unpack the tarball contents and enter the new directory:
          $ tar -xf spinnaker-2.6.0.160-Ubuntu20.04-amd64-pkg.tar.gz
          $ cd spinnaker-2.6.0.160-amd64


        3. Next, install the dependencies (on chimay, these were all already installed):
          $ sudo apt-get install libavcodec58 libavformat58 \
          libswscale5 libswresample3 libavutil56 libusb-1.0-0 \
          libpcre2-16-0 libdouble-conversion3 libxcb-xinput0 \
          libxcb-xinerama0
           
        4. There is one additional dependency, qt5-default, which is obsolete in Debian and no longer available via the package manager (that is, its functionality was absorbed into other Qt packages). I was able to find a workaround based on these instructions.

          1. Install all the dependencies of qt5-default:
            $ sudo apt-get install qtbase5-dev qtchooser qt5-qmake qtbase5-dev-tools
             
          2. Manually remove the qt5-default dependency from the Spinnaker package.

            Unpack the spinview-qt_2.6.0.160_amd64.deb package:
            $ mkdir tmp
            $ cd tmp
            $ ar -x ../spinview-qt_2.6.0.160_amd64.deb
            $ tar xf control.tar.xz

            Open the file control in a text editor and delete the qt5-default dependency from the Depends list.

            Then repackage the contents:
            $ tar cfJ control.tar.xz control
            $ ar rcs ../spinview-qt_2.6.0.160_amd64.deb debian-binary control.tar.xz data.tar.xz
            $ cd ..
            $ rm -rf tmp

            This overwrites the original package with a version no longer containing the qt5-default dependency.


        5. Now proceed with running the install script:
          $ sudo sh install_spinnaker.sh

        This will install the Spinnaker library at /opt/spinnaker. Spinnaker also provides a standalone GUI application, SpinView, which can be executed from the terminal (from any directory) via the command spinview.

        Installing PySpin

        The main challenge with installing PySpin was that it is currently only supported for Python <=3.8. The system installation on Debian 11 is Python 3.9 and 3.8 is not available within the package manager. Following these instructions, I manually installed a second version of Python (3.8) on chimay, in a way that should not interfere with the system installation.

        The Python 3.8 executable is in the system path and can be run only via the command python3.8. It is not symlinked to python or to python3. Those remain linked to the preexisting Python 3.9.

        After installing Python 3.8, I proceeded with the installation as follows:

        1. Download the PySpin package (x86_64 architecture) and copy the tarball to, e.g., /home/controls on chimay.

        2. Unpack the tarball contents and into a new directory:
          $ mkdir python
          $ mv spinnaker_python-2.6.0.160-Ubuntu20.04-cp38-cp38-linux_x86_64.tar.gz python
          $ tar xf spinnaker_python-2.6.0.160-Ubuntu20.04-cp38-cp38-linux_x86_64.tar.gz

        3. Move the new directory into the Spinnaker installation directory:
          $ sudo mv python /opt/spinnaker
          $ cd /opt/spinnaker/python
           
        4. Install the dependencies:
          $ sudo python3.8 -m pip install --upgrade numpy matplotlib

        5. Finally, install PySpin itself:
          $ sudo python3.8 -m pip install spinnaker_python-2.6.0.160-cp38-cp38-linux_x86_64.whl

        If this succeeded, you should now be able to enter import the package PySpin as

        $ python3.8
        >>> import PySpin

        without error.

               Reply  Mon Jun 6 17:11:48 2022, Jon, Update, Cameras, FLIR Camera Setup IMG_1480.pngIMG_1481.png

        Today I tested the Spinnaker/PySpin software installations (detailed in ELOG #4) with the FLIR camera connected to chimay. It works!

        Example codes

        I was able to run several of the PySpin example codes. In particular, there is one which connects to the camera and streams live data to a pop-up Matplotlib window that looks very useful. It is called AcquireAndDisplay.py.

        When running these, it is important to keep in mind that PySpin requires Python 3.8, which is not the default system version on chimay. So to run AcquireAndDisplay.py, for example, you must explicitly call the correct version of Python:

        $ python3.8 AcquireAndDisplay.py

        The standard python and python3 aliases are still linked to the system version (3.9), so calling these will result in a PySpin import error.

        Git repository

        I have set up a git repo for our FLIR camera control code. I have populated it with an Examples directory which contains the PySpin Reference Manual as well as all the example codes (see the README). There is a local copy of this repo on chimay at /home/controls/FLIR.

        Other FLIR streaming software

        In addition to the PySpin demos, there are several fully developed applications provided by FLIR. While we do not plan to use these long term, they may be very useful for debugging and cross-validation of our Python interface during development:

        • Browser interface: From any web browser on the local lab network, navigate to http://192.168.1.6 and log in (credentials here). This interface supports live data streaming as well as full control of the camera settings.

        • SpinView: A standalone application provided as part of the Spinnaker SDK. It supports streaming live camera data as well as saving images and videos. It can be launched from the terminal on chimay via the command: $ spinview

        • Research Studio: This is FLIR's proprietary software, for which we have a one-year license. It can be launched from the terminal on chimay via the command: $ FLIRResearchStudio

        Permanent cabling

        Since everything appears to be working, I ran a permanent Cat 6 cable from the lab switch to the camera's power+I/O adapter. The adapter is plugged into a UPS-protected power strip overhanging the optical table, as pictured below. To prevent the adapter from unplugging itself under its own weight, I attached a zip tie around the adapter to hold it securely in place.

        Entry  Thu Jun 2 16:14:58 2022, Jon, HowTo, General, Custom conda environment on JupyterHub 

        Cross-linking instructions: How to run a Jupyter notebook in your custom Conda environment

        Entry  Sun Apr 10 15:39:49 2022, Rutuja Gurav, HowTo, Computer Scripts/Programs, HowTo: Renew the Let's Encrypt SSL certificate using certbot 

        Port 80 is kept closed by default. This might be causing the certbot auto-renewal cronjob to fail. Therefore we must renew the certificate manually.


        Step 1: Open port 80. (This is needed as the certificate renewal process runs some tests which requires client communication over port 80)


        Step 2: Run the following command


        sudo certbot certonly --force-renew -d richardsonlab.ucr.edu


        Step 3: Confirm the certificate was renewed by running the following command


        sudo certbot certificates

        ELOG V3.1.3-7933898