  546   Thu Apr 3 13:23:37 2025 shaneUpdateCDSUPS interfacingUpdate on UPS serial interfacing: the driver
for the UPS webcard has been installed on
spica (for UPS1 in room 1119) and logrus
  
  565   Wed Apr 30 13:42:45 2025 ShaneUpdateCDSUPS comms successfulUpdate on UPS1 serial interfacing: communication
is now successful. On 4/15/25 we connected
to UPS1 via ethernet rather than USB, and
  
  570   Tue May 6 12:25:03 2025 TylerConfigurationCDSCymac ADC CSD measurementAn initial measurement of the cymbal ADC CSD
is attached below. As of now, it seems that
the sensitivity limit is roughly the same
 cymac_adc_rin_v1.pdf 
  585   Tue Jun 3 11:50:08 2025 PooyanUpdateCDSCDS updateThere are three major issues with the lab's
CDS system that should be addressed. They
are ordered from the highest priority to
  
  590   Tue Jun 10 12:11:14 2025 PooyanUpdateCDSCDS update
The MEDM models issue was fixed.
The issue was that building the c1msc model
alone was not enough and we had to re-build
  
  592   Wed Jun 11 16:19:37 2025 PooyanUpdateCDSCDS update
Fast channels recorded to .gwf frame
files

Had to add a DAQ Channels
block to the c1msc model for those channel
 Screenshot_20250611_154834.pngf3k.pdf 
  8   Fri Jul 22 13:20:28 2022 PhoebeUpdate ComsolI will be using comsol until 1:30 pm today.
I will be updating the model for the heater
mount to be thicker in certain areas, so
  
  37   Tue Feb 28 19:33:51 2023 PeterUpdate 532 M2 MeasurementsY axis of plot in units of micrometers. X
axis in units of millimeters. 
  
  46   Wed Mar 8 18:35:52 2023 PamellaUpdate Lab cleaning Today Pamella finished cleaning of the cleanroom,
starting with the HEPA vacuuming,  mopping
and clearing all floor with IPA wipes. 
Also
  
  371   Fri May 31 19:37:47 2024 LukeUpdate Vacuum chamber Disassembly [Luke, Aiden, Jon, Michel, Tyler]

Work
done:
On Tuesday (5/28) we removed the RGA
line with minimal difficulty. On Wednesday
 IMG_1681.jpgIMG_1680.jpgIMG_1680.jpgIMG_1681.jpg 
  378   Wed Jun 19 18:45:14 2024 LukeUpdate Vacuum chamber reassembly [Luke, Aiden, Mohak , Tyler]

On Tuesday
we had the silver screws for the spherical
cube shortened by a quarter of an inch so
 image_2024-06-19_182556383.pngimage_2024-06-19_182631737.pngIMG_1710.jpg 
  423   Mon Aug 12 16:35:30 2024 Luke Update Ringheater modeling Update   HR_surface_deformation.pngIrradiation_pattern_input.pngHR_surface_deformation_other.png 
  451   Wed Oct 2 10:31:46 2024 Xuesi MaConfiguration Group Meeting Slides 10/2/2024
Group Meeting slides for Non-deterministic
Heater Response.
 Group_Meeting_10_2.pdf 
  452   Wed Oct 2 12:05:42 2024 Luke Update Ringheater modeling UpdatePower
point slides
  
  455   Wed Oct 2 14:49:59 2024 LiuUpdate FROSTI ETM actuationProposed FROSTI ETM actuation on the HOM7
resonance.  

Animation
  
  460   Wed Oct 16 14:13:31 2024 LiuUpdate FROSTI with non uniform absorption scattering sourcesSlides   
  Draft   Wed Oct 23 12:33:54 2024 Luke Update Zernike calculation updatePowerPoint
slides new

PowerPoint
  
  503   Mon Jan 27 11:29:38 2025 Xuesi MaUpdate Heater Element Test[Ma, Cece, Luke, Mary, Shane]

On Friday (Jan 24), we installed
the heater elements on the stand. The heater
 20250124_165434.png20250124_165342.png20250214_132811.jpg 
  504   Mon Jan 27 23:35:28 2025 Xuesi MaUpdate  [Ma]
Installed all the pins to the peek
DB 25 connectors
 20250127_142647.jpg20250127_153454.jpg20250127_154516.jpg 
  506   Fri Jan 31 15:03:09 2025 Xuesi MaUpdate Heater Element Circuit Check
        table {
            width:
100%;
            border-collapse: collapse;
/* Merges borders into a single line */
  
  508   Mon Feb 3 13:17:21 2025 Xuesi MaUpdate  [Ma]
changed all zip ties to peek zip
ties, and grouped wires together. The setup
 20250203_123153.jpg20250203_123213.jpg 
  514   Tue Feb 18 10:01:07 2025 Xuesi MaUpdate  [Ma, Pooyan, Tyler]
On Friday, we connected the vacuum
chamber with the Cymac.
 IMG_7916.jpegIMG_7915.jpegIMG_7917.jpeg 
  515   Tue Feb 18 10:02:16 2025 Xuesi MaUpdate Group Meeting Slides 2/18/2025https://docs.google.com/presentation/d/1WiV2VqS0BzXNCK6VYYQ-Ty8xlHnzXatQaFbMf1-0rsY/edit?usp=sharing   
  525   Tue Feb 25 10:02:32 2025 Xuesi MaUpdate  1424039912.625576 2025/02/19 22:38:14 UTC Time
start
24V 2.8A right after start all 8
 resistance_vs_time_all_channels_all_time.pdftemperature_vs_time_all_channels_all_time.pdfresistance_vs_time_rise_time.pdfresistance_vs_time_fall_time.pdf 
  529   Tue Mar 4 03:33:18 2025 Xuesi MaUpdate UpdateSpikes Appear Again, need to address it
systematically.
Power on and off before reaching
 6x 
  539   Tue Mar 11 10:43:57 2025 Xuesi MaUpdate  Continue investigation in the spikes
Pulsed ADC with a function generator
and find no spikes. Rules out ADC for causing
 20250310_171936.jpg 
  544   Mon Mar 31 15:41:56 2025 Xuesi MaUpdate  The result from AI Chassis bypass test
showed that the AI Chassis may be the problem.
There are no spikes from DAC's direct output.
  
  545   Tue Apr 1 11:47:08 2025 LiuUpdate     Thermal_state_decoder_update.pdf 
  547   Mon Apr 7 13:28:49 2025 Xuesi MaUpdate  Test 1: Adapter Board Connected to Filter
Board

  Setup:
AI Chassis is powered on. Signal is measured
 20250403_151946.jpgELOG_Spike_adapter_filter_on.png20250404_143624.jpgELOG_Spike_adapter_isolate.png20250407_105846.jpg 
  553   Tue Apr 15 11:13:43 2025 Xuesi MaUpdate  Test 4: AI Chassis ground isolation


 Setup: AI Chassis isolated
from the ground with readout directly connected
 20250414_120428.jpg20250414_120423.jpg20250411_163105.jpg 
  559   Tue Apr 22 12:08:46 2025 Xuesi MaUpdate  Test 7: Reconnect ribbon cables


 Setup: Reconnect all
the ribbon cables, and turned on the AI Chassis
 20250415_161755.jpg20250416_174640.jpg20250422_105614.jpg 
  572   Tue May 6 13:19:31 2025 Xuesi MaUpdate     resistance_vs_time_RV_rise_time_24.pdfresistance_vs_time_all_channels_all_time_RV.pdf 
  576   Tue May 13 12:35:01 2025 Xuesi MaUpdate     resistance_vs_voltage_all.pdfresistance_vs_voltage_overlay.pdfresistance_vs_time_all_channels_all_time_RV.pdf 
  579   Mon May 19 10:59:14 2025 Xuesi MaInfrastructure  

  Status Update


 Previous Status:
  
  583   Tue May 27 12:52:22 2025 Xuesi MaUpdate  Using the configuration in section 2.11.1
in the Sorensen installation and operation
manual (attached below), I'm able to remote
 6x 
  586   Tue Jun 3 11:54:06 2025 Cece OchoaUpdate CE Cavity Design UpdateUpdate on the design for the CE Cavity Mirrors  CE_Arm_Cavity_.pdf 
  588   Tue Jun 3 13:08:47 2025 Xuesi MaUpdate  We currently have the parts for a DB9 connector
but need parts for a DB25 connector, where
did we get the parts for the DB9 connector?
 934.jpg933.jpg 
  589   Tue Jun 3 13:16:53 2025 Xuesi MaInfrastructure  
    Date and Time:
Around 3:50 PM on June 2, 2025
    Location and Temperature:
 928.jpg929.jpg931.jpg930.jpg932.jpg 
  591   Tue Jun 10 12:13:00 2025 Xuesi MaUpdate  
  By measuring the resistance of the
ladder, I obtained a graph of resistance
as a function of voltage.
 resistance_vs_voltage.pdfresistance_vs_voltage_element_5.pdfresistance_vs_time_all_channels_all_time_RV.pdf 
  594   Tue Jun 17 12:22:43 2025 Xuesi MaUpdate  



   
    
 11x 
  596   Tue Jun 24 11:50:15 2025 Xuesi MaUpdate  



   
    
 resistance_vs_time_all_channels_channel_switch.jpgresistance_vs_time_all_channels_channel_switch_one_cycle_before.jpgresistance_vs_time_all_channels_channel_switch_one_cycle_after.jpgresistance_vs_voltage.jpg 
  603   Tue Jul 1 13:41:36 2025 Xuesi MaUpdate  [Ma, Liu]
 Slides
  