ligo-ex ligo-ds
  Richardson Lab Experimental Log, Page 11 of 14  Not logged in ELOG logo
ID Date Authordown Type Category Subject
  303   Mon Jan 15 22:29:34 2024 JonInfrastructureGeneralCabinet installation & lab clean-up completed

[Jon, Tyler, Aiden, Shane, Pooyan, Michael, Cynthia, Luke]

On Wednesday, we completed long list of work towards making the new lab (1129) fully operational and enabling the next phase of FROSTI testing. 

Cabinet Installation

Three new VWR cabinets with sliding glass doors were installed in 1129. Each unit measures 48" (W) x 22" (D) x 84" (H) and sits along the back wall (see attachment 1). The 350-lb. cabinets were laid in place by Facilities on Monday and permanentized on Wednesday. Work included:

  • Earthquake anchoring to the masonry wall
  • Sliding glass doors leveled
  • Shelving installed
  • Wiping down of interior and exterior surfaces with IPA wipes

Server Rack Installation

A new Tripp Lite 42U open-frame rack was laid in place in 1129 and anchored to the floor (see attachment 1). This rack will house all of our general-purpose and simulation computers, which will be relocated from the 1119 rack at a later time.

Lab Clean-Up

Following installation of the new cabinets and rack, we proceeded to organize and clean both labs. Work included:

  • Moved parts and equipment into permanent storage in 1129 cabinets
  • Wiped down surfaces in 1119 and 1129 with polypropylene IPA wipes
  • HEPA-vacuumed floors of 1119 and 1129
  • Mopped floor in 1119 with Liquinox solution
  • Installed new sticky mats in 1119 and 1129
  • Regular cleanroom cleaning and particle counts (see 302)
  • Positioned new stainless steel gowning bench outside the cleanroom (see attachment 2)

At this point, the only piece of lab equipment still to be delivered is a HEPA garment cabinet for reusing our (semi-disposable) bunny suits. It is schedule to arrive in mid-February and will sit outside the cleanroom in 1119, in the former location of the HEPA flow bench.

Attachment 1: 1129.png
1129.png
Attachment 2: 1119.png
1119.png
  313   Fri Feb 2 16:56:56 2024 JonUpdateCDSRTS model implemented for FROSTI RTD readouts

Summary

Today I finished implementing an RTS model to read out the integrated FROSTI RTDs (temperature sensors) via the CyMAC. The model is named "MSC" and is located at cymac:/opt/rtcds/usercode/models/c1msc.mdl. We successfully tested it with the heater elements operating in vacuum at low power (12 VDC), finding them to reach an average steady-state temperature of 160 C.

From the cymac host, the MEDM control screen can be accessed with the terminal command "sitemap" (from any directory).

Measurement Technique

Each FROSTI heater element [299] contains an internal two-wire RTD placed near the front emitting surface, which enables the temperature of the blackbody emitter to be directly monitored. From the measured temperature and the emissivity of the uncoated aluminum nitride surface (known to be ~1 in the IR), the radiated source-plane power can also be estimated.

The resistance of each RTD is measured via a ratiometric technique. The RTDs are powered in series with a 1 kΩ reference resistor located inside the readout chassis [305], whose temperature is not changing. The signal is obtained by taking the ratio of the voltage difference across each individual RTD to the voltage difference across the reference resisitor. The advantage of this technique is that the ratio of  the voltage differences is insensitive to changes in the current through the resistors (since they are all in series; see [271] for wiring diagram).

Implementation Detail

The signal flow is shown in Attachment 1. The eight RTD signals enter through ADC channels 0-7, along with the reference resistor signal on channel 8. The first set of filter modules apply a calibration gain to convert the signals from raw ADU counts to units of input-referred voltage. The ratio of each RTD signal to the reference resistor signal is then taken. The second set of filter modules multiply the voltage-difference ratios by the resistance of the reference resistor, 1 kΩ ± 0.01%, to obtain the RTD resistances in physical units of ohms.

Finally, a freeform math module is used to invert the quadratic relation between each RTD's resistance and temperature. The final signals passed to the third set of filter modules are the RTD temperatures in physical units of degrees C. The temperatures of the tungsten RTDs are estimated assuming TCR coefficients of A=0.0030 C-1 (±10%) and B=1.003E-6 C-2, which were provided by the manufacturer.

One DAC channel is used to provide the excitation voltage for the RTD measurement, which is visible on the far right of the control screen. At its maximum output voltage of +10 V, the DAC can drive a maximum current of 10 mA.

Attachment 1: sitemap_screen.png
sitemap_screen.png
  327   Fri Feb 16 18:37:28 2024 JonUpdateVACBake ended 6:23 pm

I ended the bake of the UHV system (that began on Monday) at 6:23 pm today by switching OFF both PID controllers. The heaters elements were run at max power (24 V DC / 200 mA per element) during this bake, and I left them powered at the same level.

At the time, the instrument readings were as follows:

  • Left high-limit controller: 138 C
  • Right high-limit controller: 128 C
  • Left PID controller: 100 C
  • Right PID controller: 100 C
  • Main volume pressure: 8.17e-7 Torr
  • RGA volume pressure: 4.63e-7 Torr
  330   Tue Feb 20 08:01:30 2024 JonInfrastructureGeneralPower and network equipment installed in 1129 rack
[Jon, Tyler, Pooyan, Luis, Luke, Peter]

On Thursday we installed the power conditioning/distribution equipment and networking equipment in the new 1129 rack. The hardware is identical to the setup in the 1119 rack and includes:

  • Tripp Lite SU5KRT3UTF - 208V, 5kVA on-line UPS with 120V transformer
  • CyberPower PDU20M2F12R - metered power distribution unit, (14) NEMA 5-20R
  • Ubiquiti USW-Pro-48 - 48 port 10Gbps network switch

The UPS is connected to a 208V NEMA 6-30R outlet in the overhead cable tray, which is on the building's "standby" (backup power) circuit. An 8-ft L6-30 extension cord has been ordered to permanently run the power cable through the cable tray.

The network switch will be connected to a Cat6 cable that was recently run by ITS from the 1119 rack, allowing the lab's LAN to be extended into 1129. This Ethernet link remains to be tested.

Quote:

Server Rack Installation

A new Tripp Lite 42U open-frame rack was laid in place in 1129 and anchored to the floor (see attachment 1). This rack will house all of our general-purpose and simulation computers, which will be relocated from the 1119 rack at a later time.

Attachment 1: IMG_0924.jpeg
IMG_0924.jpeg
Attachment 2: IMG_0925.jpeg
IMG_0925.jpeg
Attachment 3: IMG_0921.jpeg
IMG_0921.jpeg
Attachment 4: IMG_0922.jpeg
IMG_0922.jpeg
  335   Thu Feb 22 21:48:16 2024 JonUpdateVACVacuum vent for RGA testing of reflector
[Jon, Tyler, Luke, Aiden]

Summary

Following Wednesday's cleanroom cleaning [333], we proceeded to vent the vacuum chamber, remove the heater elements and their mount structure, and install the FROSTI reflectors. The reflectors are the final components to undergo RGA testing before the FROSTI prototype can be assembled. After installing the reflectors, we pumped the chamber back down and initiated a 48-hour 125 C bake.

Vacuum Vent

At ~1:00 pm, we shut off power to all eight of the FROSTI heater elements. Prior to shutoff, all were operating in vacuum at roughly 300 C. We then waited approximately 30 minutes for the elements' temperatures to fall below 50 C.

At this point, we isolated the RGA volume from the main volume by closing both gate valves, leaving the RGA volume to continue to be pumped through the bypass line. We then backfilled the main volume via the needle valve connected to one of the 2.75" ports. Once the pressures had equalized, we removed the chamber lid via our usual procedure (requiring only a small amount of flathead-screwdriver prying) and extracted the heater element assembly.

Reflector Assembly

We then removed the FROSTI reflectors from their protective packaging (for the very first time) on the cleanroom tabletop. We tested the fit of the Macor and stainless steel hardware in the reflectors' tapped holes. The Macor standoffs and bolts appear to fit perfectly. However, the 1/4-20 tapped holes for joining the two reflector halves are too shallow by ~1/4". As a temporary fix, we used some on-hand stainless steel washers (which had already been cleaned and baked) to securely fasten the two halves together. In the final assembly we will replace these with slightly shorter 1/4-20 vented bolts.

Pumpdown and Bake

The two fastened reflector halves were placed inside the chamber, sitting on top of the two mounting legs (see attached photos). We then reinstalled the lid. In order to rough the main volume, we isolated the RGA volume from the pumpline (by closing the bypass line valve), shut down the pumps, and then backfilled the pumpline via the manual vent valve on the turbo pump.

Once the pressures had equalized, we opened the 6" gate valve separating the pumpline from the main volume and powered on the roughing pump. Once the main volume pressure fell below 0.5 Torr, we powered on the turbo pump as well. The main volume pressure reached 5e-6 Torr within ~30 minutes, consistent with previous experience, and was continuing to slowly fall.

Lastly, we initiated a 125 C bake-out of the entire system following our usual procedure. We plan to run this bake for 48 hours (i.e., through the end of the day Friday).

Attachment 1: IMG_0938.png
IMG_0938.png
Attachment 2: IMG_0939.png
IMG_0939.png
  339   Sat Feb 24 08:53:38 2024 JonInfrastructureComputersMatlab upgraded to 2023b on Chimay
I upgraded Matlab on chimay to the latest stable release, 2023b. From some quick tests, it appears to be in working order. Let me know of any issues.
  341   Mon Feb 26 21:23:27 2024 JonUpdateTCSFROSTI Assembly - Day 1
[Jon, Tyler, Luis, Luke, Mohak, Cynthia, Michael, Aiden]

FROSTI assembly began today. After a final set of RGA scans were taken, the vacuum chamber was vented and the reflectors were removed. The chamber was then resealed and pumped down again. 

Today we completed the installation of the Macor hardware and heater elements between the two reflector halves. Tomorrow we will route, bundle, and terminate the power and sensor cables. 

Attachment 1: IMG-20240226-WA0008.jpg
IMG-20240226-WA0008.jpg
Attachment 2: IMG-20240226-WA0006.jpg
IMG-20240226-WA0006.jpg
Attachment 3: IMG-20240226-WA0011.jpg
IMG-20240226-WA0011.jpg
Attachment 4: IMG-20240226-WA0010.jpg
IMG-20240226-WA0010.jpg
Attachment 5: IMG-20240226-WA0012.jpg
IMG-20240226-WA0012.jpg
Attachment 6: IMG_0944.png
IMG_0944.png
Attachment 7: IMG_0946.png
IMG_0946.png
  379   Thu Jun 20 18:01:11 2024 JonInfrastructureComputersNew workstation ws3 in 1129
I have repurposed a spare Intel NUC to serve as the first of two planned workstations in 1129. Today I set it up with a fresh installation of Debian 12.5, assigned it the static IP address 192.168.1.15, and installed the LIGO CDS workstation packages. It is assigned the host name ws3. Temporarily, the mouse is borrowed from ws1 in 1119. We need to order another mouse as well as a 25-ft Ethernet cable for connecting the workstation to the 1129 switch, via the ceiling.
  385   Wed Jun 26 15:33:41 2024 JonInfrastructureComputersNew workstation ws3 in 1129

Set-up of the first CDS workstation for 1129, ws3, is complete and the machine is ready for use. The login credentials are the same as the other lab machines.

All that now remains is to install a permanent cable tray for running the new Ethernet cables between the electronics rack and bench (they are currently dangling from the suspended lights).

Quote:
I have repurposed a spare Intel NUC to serve as the first of two planned workstations in 1129. Today I set it up with a fresh installation of Debian 12.5, assigned it the static IP address 192.168.1.15, and installed the LIGO CDS workstation packages. It is assigned the host name ws3. Temporarily, the mouse is borrowed from ws1 in 1119. We need to order another mouse as well as a 25-ft Ethernet cable for connecting the workstation to the 1129 switch, via the ceiling.

Attachment 1: IMG_1368.jpg
IMG_1368.jpg
  402   Thu Jul 11 21:01:37 2024 JonInfrastructureGeneralCable tray installed in 1129
Today I installed a 10' cable tray in 1129, for permanently routing Ethernet lines to the workstations. It is securely bolted to C-channels in the side wall and in the center cable tray.
Attachment 1: IMG_1395.png
IMG_1395.png
Attachment 2: IMG_1396.png
IMG_1396.png
  412   Fri Jul 26 17:25:42 2024 JonInfrastructureComputersNew workstation ws4 installed in 1129

Today I installed the second desktop workstation in 1129. The new machine is an Intel NUC13ANHi5, with a 12-Core Intel i5-1340P CPU, 32GB DDR4 RAM, and a 1TB SSD.

I loaded it with a fresh installation of Debian 12 and installed the LIGO CDS workstation (control room) tools. It is assigned the hostname ws4 and and the static IP address 192.168.1.19 on the local lab network. Like the other CDS workstations, there is just one user account accessible with the usual credentials.

The machine is fully set up and ready for use.

Attachment 1: ws4.jpg
ws4.jpg
  418   Tue Jul 30 07:42:47 2024 JonInfrastructureGeneralCable tray installed in 1119
Yesterday I installed another 5' cable tray in 1119, for permanently routing Ethernet lines to the L-bench. It is securely bolted to the top of the electronics rack, on one end, and to the top of the glass-door storage cabinet, on the other. This eliminates the need for the cable ramp which previously sat behind the rack.
Attachment 1: cable_tray_1119.jpg
cable_tray_1119.jpg
  670   Thu Jan 22 10:10:31 2026 JonInfrastructureGeneralLab floor plans
Attached are the starting and final floor plans for the February 2026 expansion into the Physics 1125 lab.
Attachment 1: Pre-Feb-2026.png
Pre-Feb-2026.png
Attachment 2: Post-Feb-2026.png
Post-Feb-2026.png
  676   Thu Feb 5 11:42:47 2026 JonInfrastructureGeneralLab floor plans

[Audrey, Cece, Jon, Ma, Mary, Michael, Pooyan, Tyler, Shane]

We have completed the preliminary reorganization of our Physics 1119 lab space. This includes:

  • Moving all cabinets to their final positions
  • Clearing out all equipment from the cleanroom in prep for HVAC work, and storing them in either the HEPA cabinet or double-bagging in regular storage.
  • Moving all non-essential equipment into other lab spaces.
  • Wrapping vacuum system and VLC for protection
  • Removing all ceiling tiles and fans from the ceiling of the cleanroom
  • Moving the cleanroom frame towards the front of the room.

Prepping the new clean-and-bake station in 1125 will begin within the next week, along with the construction of the stainless steel table planned to be put into the cleanroom.

Quote:
Attached are the starting and final floor plans for the February 2026 expansion into the Physics 1125 lab.

 

Attachment 1: image.jpg
image.jpg
Attachment 2: image_1.jpg
image_1.jpg
Attachment 3: image_3.jpg
image_3.jpg
  26   Fri Feb 10 16:34:45 2023 Huy Tuong CaoInfrastructureClean & BakeNitrogen gas tank ready to use
Cao,

Today I fixed the final bit related to the nitrogen gas tank, which is to apply sealing tape to M-NPT connector of the hose to prevent leakage (file: AirGunSealed.jpg)
After application of the tape, no audible leak can be heard from connection between the hose and the air gun.

The general operating procedure for the gas tank is as following:

  1. Turn the regulator (blue handle) anti-clockwise still it's loose
  2. Turn the valve on nitrogen as tank anti-clockwise, immediately the RHS meter of the regulator would jump to approx 2000 psi. This is the standard pressure for high pressure gas tank
  3. Turn the regulator clock-wise slowly until the pressure one the LHS meter face reads approx 60 psi. This is sufficient for drying parts with. At this point, the flow pressure still should register zero
  4. Press the trigger on the air gun, a high pressure air flow should come out and the flow meter should increase
  5. When finished, close the gas tank valve, turn the regulator anti-clockwise, then press the air gun trigger to release gas left in the hose/gun

Attachment 1: AirGunSealed.jpg
AirGunSealed.jpg
  359   Mon Apr 8 14:57:41 2024 Cynthia, PooyanUpdateInterferometer Simulationsperformed cavity scans for O4 O5, and coupled cavity
Attachment 1: LIGO_update_week1.pdf
LIGO_update_week1.pdf
  688   Thu Feb 26 20:25:10 2026 Cynthia LiangUpdateInterferometer SimulationsPoint Absorber+Miscentering Simulation
Attachment 1: update_2_18_Merged.pdf
update_2_18_Merged.pdf
  343   Tue Feb 27 09:06:29 2024 Cynthia UpdateInterferometer Simulationscavity scan with higher order input laser
I performed a few cavity scan with the inputing laser with a different mode (not pure 00). For each laser I included a graph for just plotting the order with highest power (for example 1st order laser input the first plot only scanned for 1st order in that cavity), and I have also included a graph scanning for order 1-10.
Attachment 1: ligoPre_2_27.pdf
ligoPre_2_27.pdf
  363   Mon Apr 22 15:06:33 2024 Cynthia UpdateInterferometer Simulationscavity scan update
[Cynthia,Pooyan] Completed some simulations injecting 0-10th order modes. Some graphs will be used for the poster after some further titles, axis, and range adjustments.
Attachment 1: LIGO_4_22.pdf
LIGO_4_22.pdf
  381   Mon Jun 24 14:28:51 2024 Cynthia UpdateInterferometer SimulationsSIS cavity with thermal effect
tried to run a cavity scan with thermal deformation and ring heater for ITM04 ETM08 (aLIGO mirrors). Not sure about the accuracy of the graph as there is some commands that still need to verified.
Attachment 1: ETM08thermal.png
ETM08thermal.png
  392   Mon Jul 1 15:19:42 2024 Cynthia UpdateInterferometer SimulationsO4 and O5 mirror cavity scans with thermal effect
Attachment 1: cavityScan_07_01.pdf
cavityScan_07_01.pdf
  408   Mon Jul 15 15:44:52 2024 Cynthia UpdateInterferometer Simulationsperformed cavity scans with thermal effects and ring heater
Attachment 1: cavity_scan_07_15.pdf
cavity_scan_07_15.pdf
  424   Mon Aug 12 17:09:04 2024 Cynthia UpdateInterferometer SimulationsO4 vs O5 cavity scans with ITM plume guess or ETM
So far the proposed solution for what to use for O5 ITM mirror for SIS simulations is either the plume guess file or using the O5 ETM mirror for ITM. I had ran a cavity scan for both of these possibilities and it seems like the results produced are fairly different. The next step is most likely moving on to adding the Frosti effects including both of the proposed possibilities, and before this, a few confirmations and verifications are needed using similar previous studies to make sure my code produce the right result.
Attachment 1: O5_plots_and_tables.pdf
O5_plots_and_tables.pdf
Attachment 2: O4_plots_and_tables.pdf
O4_plots_and_tables.pdf
Attachment 3: ETM12mapO5.png
ETM12mapO5.png
Attachment 4: Screenshot_2024-08-12_at_5.05.31_PM.png
Screenshot_2024-08-12_at_5.05.31_PM.png
  428   Mon Aug 26 14:42:04 2024 Cynthia UpdateInterferometer Simulationscurrent status on cavity scan with effects of FROSTI
I used the code and arm cavity model used for previous O5 study on mirrors and HOM (the pdf of the study and the result can be found at https://dcc.ligo.org/LIGO-G2100878), but it seems like the result I obtained is different from the study result. Since my cavity scans codes have a large portion of it relying on this code, I will have to go over the study result and the code to make sure there is no issue with that code itself first. There are also some other updates or issued encountered when I tried to plot the mirror maps with effects of FROSTI.
Attachment 1: LIGO_updates_8_26.pdf
LIGO_updates_8_26.pdf
  443   Mon Sep 16 15:18:59 2024 Cynthia UpdateInterferometer Simulationsa breakdown of FROSTI and thermal effects and the resulting cavity scan
Attachment 1: ligo_update_9_16_(1).pdf
ligo_update_9_16_(1).pdf
  446   Mon Sep 23 15:00:41 2024 Cynthia UpdateInterferometer Simulationscorrections on assumption for O5 coating
The document recording ETM07 and ETM08 coating (T2300093) was discussed: the current plume files are not necessarily correct in a way that LIGO lab have tried to add it on uncoated ETM such as ETM07 and it does not match what the coated ETM07 would look like. the plume should be added on top of the uncoated ETM instead of assuming an ideal ETM. According to Garilynn, the imperfection on uncoated ETM matters. So far the possible ETM data used for O5, ETM 11,14,19, and 20 are all uncoated, and different ways could be used to predict the plume, including the plume data on LIGO dcc or subtract the uncoated data from the coated for O4 ETM and use that as another guessed plume.
Attachment 1: Uncoated_S1_ETM07-v2.pdf
Uncoated_S1_ETM07-v2.pdf
  587   Tue Jun 3 12:16:13 2025 Cynthia UpdateInterferometer SimulationsPoint absorber simulation on radially averaged profile
Attachment 1: update_6_3.pdf
update_6_3.pdf
  679   Thu Feb 5 13:34:13 2026 Cynthia UpdateInterferometer SimulationsPoint absorber + miscentering simulation
Attachment 1: update2_5_(3).pdf
update2_5_(3).pdf
  361   Mon Apr 15 15:25:10 2024 CynthiaUpdateInterferometer Simulationsprogress on simulation so far
Attachment 1: LIGO_update_week3_(2).pdf
LIGO_update_week3_(2).pdf
  374   Mon Jun 3 14:59:44 2024 CynthiaUpdateInterferometer SimulationsCreated cavity scan with LG modes
Attachment 1: ligo_update_6_3.pdf
ligo_update_6_3.pdf
  426   Mon Aug 19 07:11:55 2024 CynthiaUpdateInterferometer Simulationscavity scans with FROSTI effects
Attachment 1: LIGO_update_8_19.pdf
LIGO_update_8_19.pdf
  454   Wed Oct 2 13:38:00 2024 CynthiaUpdateInterferometer Simulationscavity scan with averaged O4 ETM coating as plume
Attachment 1: O5plumevsCoating.png
O5plumevsCoating.png
Attachment 2: O5CoatAvgpt5.png
O5CoatAvgpt5.png
Attachment 3: O5AVgcoatingFROSTIpt5.PNG
O5AVgcoatingFROSTIpt5.PNG
  526   Tue Feb 25 10:56:25 2025 CynthiaUpdateInterferometer Simulationsmirror coating added for simulation rerun
I have tried to rerun the simulation on finesse after adding the mirror coating. The result has a large fluctuation in required input power vs arm power that is concerning. I am currently working on potentially resolve this issue and get a reasonable graph before I proceed to optimizing the thermal maps.
Attachment 1: updats_(3).pdf
updats_(3).pdf
  530   Tue Mar 4 10:18:43 2025 CynthiaUpdateInterferometer Simulationsattempted to remove curvature and tilt for the coating
Attachment 1: 3_4_updates.pdf
3_4_updates.pdf
  540   Tue Mar 11 11:28:52 2025 CynthiaUpdateInterferometer Simulationsflattening mirror to study power discrepency
Attachment 1: updates_3_11_(1).pdf
updates_3_11_(1).pdf
  554   Tue Apr 15 11:37:17 2025 CynthiaUpdateInterferometer SimulationsFinishing up mirror coating map step
Attachment 1: updates_4_15_2025.pdf
updates_4_15_2025.pdf
  686   Thu Feb 19 12:34:18 2026 CynthiaUpdateInterferometer SimulationsPoint absorber simulation
Attachment 1: update_2_18.pdf
update_2_18.pdf
  692   Thu Mar 12 12:48:58 2026 CynthiaUpdateInterferometer SimulationsNew Result of point absorber+miscentering
Attachment 1: Untitled_presentation_(1).pdf
Untitled_presentation_(1).pdf
  635   Tue Aug 26 12:45:41 2025 Christina, Ma, TylerUpdateCDSRIN Update
Slides
  600   Fri Jun 27 15:38:22 2025 ChristinaUpdateTCSFROSTI Reconstruction

[Tyler, Ma, Christina, Luke]

We threaded the wiring of the heater elements through the reflective surfaces and were able to attach each piece with the Macor spacers and connect both sides. We used the guide rails and screws to ensure proper alignment. The only necessary step left is to add the additional external screws for the reconstruction.

Attachment 1: IMG_4009.png
IMG_4009.png
  601   Tue Jul 1 11:04:00 2025 ChristinaUpdateTCSFROSTI Reconstruction II

[Ma, Tyler, Christina]

Finished external reconstruction of the FROSTI by installing all the pins to the 2 DB 25 connectors. To ensure everything was operating correctly, we did electrical testing by testing continuity and by checking each of the heater elements' RTD and power resistance values and comparing them to what was tabulated in January. Additionally, we organized the wires and added the stands.

Attachment 1: IMG_4042.png
IMG_4042.png
  604   Mon Jul 7 16:39:18 2025 ChristinaUpdateTCSPomona Box Drawings

Below are the drawings for the pomona box modifications

Attachment 1: pbdwg1.PDF
pbdwg1.PDF
Attachment 2: pbdwg2.pdf
pbdwg2.pdf
  608   Thu Jul 10 16:41:18 2025 ChristinaUpdateTCS 

[Christina, Ma, Tyler]

Pomona Box completed and is now on the server rack in 1119. Additionally, the photodetectors were connected to the box and set up in front of the heater elements.

Attachment 1: 2994921113032912040.JPG
2994921113032912040.JPG
Attachment 2: 4717009101108174053.JPG
4717009101108174053.JPG
Attachment 3: 5782646701589802125.JPG
5782646701589802125.JPG
  611   Tue Jul 15 10:40:23 2025 ChristinaUpdateTCS 

[Christina, Ma, Tyler]

Yesterday, Ma and I started taking data for the PSD/CSD measurements while the photodetectors and one of the heater elements are on (8) and are using the Red Pitaya to compare it to the data we took for the same measurements on the CyMAC. It will be finished Wednesday morning, and then we plan on starting to take additional recordings in order to conduct the same type of comparison for the dark noise measurements.

Attachment 1: rpon.png
rpon.png
  614   Tue Jul 15 13:13:48 2025 ChristinaUpdateTCSPhotodetector optical post assembly
Attachment 1: pdreassembly.png
pdreassembly.png
  615   Tue Jul 22 12:20:29 2025 ChristinaUpdateTCS 

[Ma, Christina, Tyler]

Figure 1 shows the following PSDs for channels 0-15 from the 14 hour test. Figure 2 shows the reduced chi squared and CSD plots for both the 2 Hz and 16 Hz resolutions.

Attachment 1: PSDch0-15.png
PSDch0-15.png
Attachment 2: CSD2hz_16hz.png
CSD2hz_16hz.png
  619   Tue Jul 29 12:30:00 2025 ChristinaUpdateTCS260 hour ADC update

[Ma, Christina, Tyler]

ADC CyMAC 260 hr, 8192Hz sampling rate channels V3 and Vref6

Attachment 1: CSD_06_28_25_270hr.png
CSD_06_28_25_270hr.png
  624   Mon Aug 11 22:19:50 2025 ChristinaUpdateTCSRed Pitaya Data Streaming

[Ma, Tyler, Christina]

This past week, we were able to set up the data streaming for continuous acquisition to the PCs, and can conduct the initial tests now. We were able to do this by:

  • Installing the correct OS ecosystems to each Red Pitaya
  • Installing the terminal streaming client
  • Debugging formatting and file saving issues by saving the data in a TDMS file on the host PC.
We have started streaming the ADC data on Monday from both boards for 2 days, which are currently in the clean room. Below are the ADC tests we performed before starting the 2-day run. (Time in ms)

Attachment 1: 3.png
3.png
Attachment 2: 3-1.png
3-1.png
  629   Tue Aug 12 13:46:56 2025 ChristinaUpdate  
Attachment 1: 3.png
3.png
Attachment 2: 3-1.png
3-1.png
  631   Tue Aug 19 12:08:40 2025 ChristinaUpdateTCSRP Initial vs CyMAC Plot Comparisons
[Tyler, Ma, Christina]

These are the frequency averaged and veto binned plots for the initial Red Pitaya and CyMAC systems.

Attachment 1: 11hzCSD.png
11hzCSD.png
Attachment 2: 11hzstrain.png
11hzstrain.png
ELOG V3.1.3-7933898