Thu Jul 11 15:53:39 2024, Luke, Update, VAC, RGA line upgrade  
|
Fri Aug 23 16:08:32 2024, Luke, Update, VAC, RGA line leak testing
|
Tue Aug 27 15:01:26 2024, Luke, Update, VAC, RGA line leak testing
|
Wed Jul 10 17:31:07 2024, Luke, Update, VAC, RGA line disassembly and upgrade   
|
Fri Nov 10 08:32:34 2023, Jon, Update, VAC, RGA experiments
|
Tue Nov 14 17:21:40 2023, Jon, Update, VAC, RGA best practices
|
Wed Dec 11 16:06:05 2024, Luis, Update, VAC, RGA Status
|
Wed May 10 10:49:34 2023, Aiden, Update, General, RGA Software
|
Mon Sep 16 13:51:23 2024, Luis Martin, Update, VAC, RGA Scans  
|
Wed Sep 25 09:06:09 2024, Luis Martin, Update, VAC, RGA Scans 
|
Thu Dec 12 13:06:39 2024, Luis, Update, VAC, RGA Scan and vacuum system updates 
|
Thu Dec 5 10:31:13 2024, Luis , Update, VAC, RGA Scan and RGA updates
|
Thu May 8 17:41:56 2025, Luis, Update, VAC, RGA Scan Post Bake 
|
Wed Oct 16 13:58:59 2024, Luis Martin, Update, VAC, RGA Scan
|
Wed Oct 23 12:08:36 2024, Luis Martin, Update, VAC, RGA Scan
|
Thu Feb 20 17:07:36 2025, Luis, Update, VAC, RGA Scan
|
Mon Feb 24 17:50:13 2025, Luis, Update, VAC, RGA Scan
|
Wed Nov 6 13:48:55 2024, Liu, Update, Interferometer Simulations, QN modeling update
|
Mon Jul 15 13:30:49 2024, Luke , Update, VAC, Problem with 2.75" to 1.33" zero length reducer
|
Thu Apr 17 12:12:29 2025, Liu, HowTo, Interferometer Simulations, Preventing Thread Contention in Multiprocessing with Finesse and Cython
|
Mon Mar 10 17:03:52 2025, Shane, Update, CDS, Pressure Gauge successful connect
|
Mon Nov 6 11:29:24 2023, Tyler, Update, Electronics, Preliminary RTD Calculations, RP Software Update  
|
Tue Aug 1 12:48:41 2023, Aiden, Update, Cleanroom, Pre Filter Change  
|
Wed Jun 28 15:58:56 2023, Shane, Cao, Infrastructure, VAC, Power trip problem remains, source of smoke is insulation    
|
Tue Feb 20 08:01:30 2024, Jon, Infrastructure, General, Power and network equipment installed in 1129 rack   
|
Tue Jun 3 12:16:13 2025, Cynthia , Update, Interferometer Simulations, Point absorber simulation on radially averaged profile
|
Tue Jul 18 16:35:06 2023, Pamella, Update, FLIR, Plot-Data with the new configuration without the mask and reflector.
|
Thu Aug 29 16:39:34 2024, Luke, Update, VAC, Photos of heater tape 6x
|
Tue Apr 22 13:00:04 2025, Nathan, Update, VLC Update, Photodiode signal check and additional signal check due to 20Mhz signal and amplifier 
|
Tue May 9 15:49:20 2023, Jon, Infrastructure, VAC, Permanent cable routing
|
Mon Nov 28 18:10:23 2022, shane, Update, ELOG, Particle counts in the clean room
|
Tue Apr 4 16:52:08 2023, Jon, Update, Cleanroom, Particle counter docking station
|
Wed Apr 12 16:17:50 2023, shane, Update, General, Particle Counter moved
|
Mon Oct 9 11:29:37 2023, Tyler, Update, Electronics, PSD/CSD Plot Updates 
|
Mon Mar 10 21:13:12 2025, Nathan, Update, VLC Update, PDH Lock Progress and Next Steps   
|
Tue Apr 8 20:04:35 2025, Nathan, Update, VLC Update, PDH Lock Progress 
|
Wed Mar 1 21:27:20 2023, Jon, Infrastructure, Cleanroom, Over-table shelf height raised
|
Mon Jan 23 17:26:15 2023, Peter Carney, Update, General, Oven cleaning
|
Thu Jan 26 18:58:25 2023, Aiden, Update, General, Oven Heating
|
Fri Feb 23 18:03:27 2024, Tyler, Update, FLIR, Optical Test Setup in Cleanroom
|
Tue Jul 26 14:10:35 2022, Cassidy, Update, Cameras, Optical Post Replacement and Realignment  
|
Thu Feb 27 18:22:21 2025, Shane, Update, CDS, Ongoing work in server rack and desk area (1119)
|
Mon Aug 12 17:09:04 2024, Cynthia , Update, Interferometer Simulations, O4 vs O5 cavity scans with ITM plume guess or ETM   
|
Mon Jul 1 15:19:42 2024, Cynthia , Update, Interferometer Simulations, O4 and O5 mirror cavity scans with thermal effect
|
Thu May 15 12:03:41 2025, Xuesi Ma, Infrastructure, Electronics, Notice
|
Tue Apr 11 13:15:40 2023, Cao, Infrastructure, Clean & Bake, Nitrogen gas tank replaced
|
Fri Feb 10 16:34:45 2023, Huy Tuong Cao, Infrastructure, Clean & Bake, Nitrogen gas tank ready to use
|
Fri Jul 26 17:25:42 2024, Jon, Infrastructure, Computers, New workstation ws4 installed in 1129
|
Thu Jun 20 18:01:11 2024, Jon, Infrastructure, Computers, New workstation ws3 in 1129
|
Wed Jun 26 15:33:41 2024, Jon, Infrastructure, Computers, New workstation ws3 in 1129
|
|